During a period 17, 500 labour hours were worked at a standard cost of Rs 6.50 per hour. The 

labour efficiency variance was Rs 7,800 favourable.

How many standard hours were produced?

(a) 1,200

(b) 16,300

(c) 17,500

(d) 18,700

1 Answer

Answer :

(d) 18,700

Related questions

Description : During September, 300 labour hours were worked for a total cost of Rs 4800. The variable  overhead expenditure variance was Rs 600 (A). Overheads are assumed to be related to direct labour  hours of active working. What was the standard cost per labour hour? (a) Rs 14 (b) Rs 16.50 (c) Rs 17.50

Last Answer : (a) Rs 14

Description : CG Co manufactures a single product T. Budgeted production output of product T during June is  200 units. Each unit of product T requires 6 labour hours for completion and CG Co anticipates 20 per  cent idle time. Labour is paid at ... for March is (a) Rs 6,720 (b) 8,400 (c) 10,080 (d) 10,500

Last Answer : (d) 10,500

Description : Calculate the most appropriate unit cost for a distribution division of a multinational company using the following information. Miles travelled 636,500 Tonnes carried 2,479 Number of drivers 20 Hours worked by drivers 35,520 Tonnes miles ... 800 (a) Rs .88 (b) Rs 1.50 (c) Rs 15.84 (d) Rs28, 140

Last Answer : (d) Rs28, 140

Description : . A job is budgeted to require 3,300 productive hours after incurring 25% idle time. If the total labour  cost budgeted for the job is Rs36,300. What is the labour cost per hour( to the nearest cent)? (a) Rs 8.25 (b) Rs 8.80 (c) Rs 11.00 (d) Rs 14.67

Last Answer : (a) Rs 8.25

Description : Process B had no opening inventory. 13,500 units of raw material were transferred in at Rs 4.50  per unit. Additional material at Rs1.25per unit was added in process. Labour and overheads were Rs 6.25  per completed unit and Rs ... 6562.50 (b) Rs. 12,250.00 (c) Rs. 14,437.50 (d) Rs. 25,375.00

Last Answer : (a) Rs 142,485

Description :  The actual output of 162,500 units and actual fixed costs of Rs. 87000 were exactly as budgeted.  However, the actual expenditure of Rs 300,000 was Rs. 18,000 over budget. What was the budget variable cost per unit?

Last Answer : (a) Rs 1.20

Description : Following information is available of PQR for year ended March, 2013: 4,000 units in process, 3,800 units output, 10% of input is normal wastage, Rs. 2.50 per unit is scrap value and Rs. 46,000 incurred towards total process cost ... be:- (a) Rs. 2,500 (b) Rs. 2,000 (c) Rs. 4,000 (d) Rs. 3,500

Last Answer : (a) Rs. 2,500

Description : Q.61. CA Co manufactures a single product and has drawn up the following flexed budget for the year.  60% 70% 80%  Rs Rs Rs Direct materials 120,000 140,000 160,000 Direct labour 90,000 105,000 120,000 Production ... activity? (a) Rs 330,300 (b) Rs 370,300 (c) Rs 373,300 (d) Rs 377,300

Last Answer : (b) Rs 370,300

Description : Calculate the value of closing stock from the following according to Weighted Average method: 1st January, 2014: Opening balance: 50 units @ Rs. 4 Receipts: 5th January, 2014: 100 units @ Rs. 5 12th January, 2014: 200 units ... 2014: 150 units (a) Rs. 765 (b) Rs. 805 (c) Rs. 786 (d) Rs. 700

Last Answer : (c) Rs. 786

Description : Calculate the value of closing stock from the following according to LIFO method: 1st January, 2014: Opening balance: 50 units @ Rs. 4 Receipts: 5th January, 2014: 100 units @ Rs. 5 12th January, 2014: 200 units @ Rs. 4.50 ... , 2014: 150 units (a) Rs. 765 (b) Rs. 805 (c) Rs. 786 (d) Rs. 700

Last Answer : (b) Rs. 805

Description : Calculate the value of closing stock from the following according to FIFO method: 1st January, 2014: Opening balance: 50 units @ Rs. 4 Receipts: 5th January, 2014: 100 units @ Rs. 5 12th January, 2014: 200 units @ Rs. 4.50 ... , 2014: 150 units (a) Rs. 765 (b) Rs. 805 (c) Rs. 786 (d) Rs. 700

Last Answer : (a) Rs. 765

Description : Which of the following would explain an adverse variable production overhead efficiency variance? 1. Employees were of a lower skill level than specified in the standard 2. Unexpected idle time resulted from a series of machine breakdown 3. ... b) (1) and (2) (c) (2) and (3) (d) (1) and (3)

Last Answer : (d) (1) and (3)

Description : Calculate Re-order level from the following: Consumption per week: 100-200 units Delivery period: 14-28 days (a) 5600 units (b) 800 units (c) 1400 units (d) 200 units

Last Answer : (b) 800 units

Description : The ratio of the monthly salaries of A and B is in the ratio 15 : 16 and that of B and C is in the ratio 17 : 18. Find the monthly income of C if the total of their monthly salary is Rs 1,87,450. A) Rs 66,240 B) Rs 72,100 C) Rs 62,200 D) Rs 65,800 E) Rs 60,300

Last Answer : Answer: A A/B = 15/16 and B/C = 17*18 So A : B : C = 15*17 : 16*17 : 16*18 = 255 : 272 : 288 So C’s salary = [288/(255+272+288)] * 1,87,450= Rs 66,240

Description : The formula used for calculation of labour rate variance is A. Total standard labour cost of actual output - Total actual cost of actual output B. (Standard rate per hour - Actual rate per hour) ... time - Actual time) * Standard rate per hour D. Abnormal idle hours * Standard hourly rate

Last Answer : B. (Standard rate per hour - Actual rate per hour) * Actual Hours

Description : worker is allowed 60 hours to complete the job on a guaranteed wage of Rs. 10 per hour. Under  the Rowan Plan, he gets an hourly wage of Rs. 12 per hour. For the same saving in time, how much he  will get under the Halsey Plan? (a) Rs. 720 (b) Rs. 540 (c) Rs. 600  (d) Rs. 900

Last Answer : (b) Rs. 540

Description : Calculate value of closing stock from the following: Opening stock of finished goods (500 units) : Rs. 2,000 Cost of production (10000 units) : Rs. 50,000Closing stock (1000 units):? (a) Rs. 4,000 (b) Rs. 4,500 (c) Rs. 5,000 (d) Rs. 6,000

Last Answer : (b) Rs. 4,500

Description : The following information is available for the W hotel for the latest thirty day period. Number of rooms available per night 40 Percentage occupancy achieved 65% Room servicing cost incurred Rs. 3900 The room servicing cost per occupied room- ... (a) Rs 3.25 (b) Rs 5.00 (c) Rs 97.50 (d) Rs 150.00

Last Answer : (b) Rs 5.00

Description : Calculate EOQ (approx.) from the following details: Annual Consumption: 24000 units Ordering cost: Rs. 10 per order Purchase price: Rs. 100 per unitCarrying cost: 5% (a) 310 (b) 400 (c) 290 (d) 300

Last Answer : (a) 310

Description : Calculate the labour turnover rate according to Separation method from the following: No. of workers on the payroll: - At the beginning of the month: 500 - At the end of the month: 600 During the month, 5 workers left ... engaged for an  expansion scheme. (a) 4.55% (b) 1.82% (c) 6% (d) 3%

Last Answer : (a) 4.55%

Description : Calculate the labour turnover rate according to replacement method from the following: No. of workers on the payroll: - At the beginning of the month: 500 - At the end of the month: 600 During the month, 5 workers left ... engaged for an expansion scheme. (a) 4.55% (b) 1.82% (c) 6% (d) 3%

Last Answer : (b) 1.82%

Description : 3. S produces and sells one product, P, for which the data are as follows: Selling price Rs 28 Variable cost Rs 16 Fixed cost Rs 4 The fixed costs are based on a budgeted production and sales level of 25 ... period(a) 10.1% decrease (b) 11.2% decrease (c) 13.3% decrease (d) 16.0% decrease

Last Answer : (a) 10.1% decrease

Description : Which of the following is not a method of cost absorption? (a) Percentage of direct material cost (b) Machine hour rate (c) Labour hour rate (d) Repeated distribution method

Last Answer : d) Repeated distribution method

Description : Calculate the prime cost from the following information: Direct material purchased: Rs. 1,00,000 Direct material consumed: Rs. 90,000 Direct labour: Rs. 60,000 Direct expenses: Rs. 20,000 Manufacturing overheads: Rs. 30,000 (a) Rs. 1,80,000 (b) Rs. 2,00,000 (c) Rs. 1,70,000 (d) Rs. 2,10,000

Last Answer : (c) Rs. 1,70,000

Description : Normal quantity of urobilinogen excreted in the feces per day is about (A) 10–25 mg (B) 50–250 mg (C) 300–500 mg (D) 700–800 mg FATS AND FATTY ACID METABOLISM 79

Last Answer : Answer : B

Description : A company makes a single product and incurs fixed costs of Rs. 30,000 per annum. Variable cost per unit is Rs. 5 and each unit sells for Rs. 15. Annual sales demand is 7,000 units. The breakeven point is: (a) 2,000 units (b) 3,000 units (c) 4,000 units (d) 6,000 units

Last Answer : (b) 3,000 units

Description : A company manufactures a single product for which cost and selling price data are as follows: Selling price per unit - Rs. 12 Variable cost per unit - Rs. 8 Fixed cost for a period - Rs. 98,000 Budgeted sales for a period - 30,000 units

Last Answer : (a) 20%

Description : Following information is available of XYZ Limited for quarter ended June, 2013 Fixed cost Rs. 5,00,000 Variable cost Rs. 10 per unit Selling price Rs. 15 per unit Output level 1,50,000 units

Last Answer : (a) Rs. 2,50,000

Description : From the following information, calculate the extra cost of material by following EOQ: Annual consumption: = 45000 units Ordering cost per order: = Rs. 10  Carrying cost per unit per annum: = Rs. 10  Purchase price per unit = Rs. ... ) No saving (b) Rs. 2,00,000 (c) Rs. 2,22,010 (d) Rs. 2,990

Last Answer : (d) Rs. 2,990

Description : A contractor wishes to determine a suitable combination of manual labour and machine work for the excavation of a multistory construction. For every cum of excavation, 3 man-hours are needed; or 0.2 machine-hour. Costs ... total cost will be (a) 1500 cum (b) 1800 cum (c) 2250 cum (d) 2500 cum

Last Answer : (d) 2500 cum

Description : Labour turnover means: (a) Turnover generated by labour (b) Rate of change in composition of labour force during a specified period (c) Either of the above (d) Both of the above

Last Answer : (b) Rate of change in composition of labour force during a specified period

Description : A transport company is running five buses between two towns, which are 50 kms apart. Seating capacity of each bus is 50 passengers. Actually passengers carried by each bus were 75% of seating capacity. All buses ran on all days of ... (a) 2,81,250 (b) 1,87,500 (c) 5,62,500 (d) None of the above

Last Answer : (c) 5,62,500

Description : Total cost of a product: Rs. 10,000 Profit: 25% on Selling Price Profit is: (a) Rs. 2,500 (b) Rs. 3,000 (c) Rs. 3,333 (d) Rs. 2,000

Last Answer : (b) Rs. 2,80,000

Description : A company's break even point is 6,000 units per annum. The selling price is Rs. 90 per unit and the variable cost is Rs. 40 per unit. What are the company's annual fixed costs? (a) Rs. 120 (b) Rs. 2,40,000

Last Answer : 5,40,000

Description : AT Co makes a single product and is preparing its material usage budget for next year. Each unit of  product requires 2kg of material, and 5,000 units of product are to be produced next year. Opening inventory of material is budgeted ... (a) 8,000 Kg((b) 9,840 kg ((c) 10,000 Kg (d) 10,160 Kg

Last Answer : ((c) 10,000 Kg

Description : According to U. N. O. there were about ______ disasters per year between 1992 - 2000 in the world? a. 100 b. 300 c. 500 d. 800

Last Answer : c. 500

Description : . Which of the following is not a reason for an idle time variance? (a) Wage rate increase (b) Machine breakdown (c) Illness or injury to worker (d) Non- availability of material

Last Answer : (a) Wage rate increase

Description : How many units must be sold if company wants to achieve a profit of Rs. 11,000 for the year? (a) 2,500 units (b) 9,833 units (c) 10,625 units (d) 13,409 units

Last Answer : (d) 13,409 units

Description : The summarized balance sheet of Rakesh udyog Limited shows the balances of previous and current year of provision for taxation Rs. 50,000 and Rs. 65,000. If taxed paid during the current year amounted to Rs. 70,000 then amount charge ... a) Rs. 55,000 (b) Rs. 85,000 (c) Rs. 45,000 (d) Rs. 1,85,000

Last Answer : (b) Rs. 85,000

Description : The cost per unit of a product manufactured in a factory amounts to Rs. 160 (75% variable) when the production is 10,000 units. When production increases by 25%, the cost of production will be Rs. per unit. (a) Rs. 145 (b) Rs. 150

Last Answer : (c) Rs. 152

Description : Which constant pressure altitude chart is standard for a 30,065 ft pressure level (FL 300)?  a. 200 hPa  b. 700 hPa  c. 500 hPa  d. 300 hPa

Last Answer : d. 300 hPa

Description : Which constant pressure altitude chart is standard for a 30,065 ft pressure level (FL 300)? a. 200 hPa b. 700 hPa c. 500 hPa d. 300 hPa

Last Answer : d. 300 hPa

Description : The P/v ratio of a company is 50% and margin of safety is 40%. If present sales is Rs. 30,00,000 then Break Even Point in Rs. will be (a) Rs. 9,00,000 (b) Rs. 18,00,000 (c) Rs. 5,00,000 (d) None of the above

Last Answer : (b) Rs. 18,00,000

Description : Which of the following statements is/are correct? 1. A materials requisition note is used to record the issue of direct material to a specific job. 2. A typical job cost will contain actual costs for material, labour and production ... 1) and (2) only (c) (1) and (3) only (d) (2) and (3) only

Last Answer : (c) (1) and (3) only

Description : Element/s of Cost of a product are: (a) Material only (b) Labour only (c) Expenses only (d) Material, Labour and expenses

Last Answer : (d) Material, Labour and expenses

Description : In a heat treatment shop, steel components are heat-treated in batches of 80 Tons. The  heat treatment cycle is as follows;  Increase temperature from 30 OC to 850 OC in 3 hours.  ... efficiency of 80%, for same requirement. The investment towards installation of  the new furnace is Rs. 50

Last Answer : Quantity of steel treated per batch - 80 Tons a. Efficiency of Furnace: Useful heat supplied to steel - 80000 x 0.12 x (850 - 30)   = 7872000 kcal/batch .1 mark Total heat ... = Rs. 64400/batch Efficiency of new LPG furnace - 80% Heat supplied in new LPG furnace - 7872000/0.8

Description : Calculate workers recruited and joined from the following: Labour turnover rates are 20%, 10% and 6% respectively under Flux method, Replacement method and  Separation method. No. of workers replaced during the quarter is 80. (a) 112 (b) 80

Last Answer : (a) 112

Description : Calculate workers left and discharged from the following: Labour turnover rates are 20%, 10% and 6% respectively under Flux method, Replacement method and  Separation method. No. of workers replaced during the quarter is 80. (a) 112 (b) 80 (c) 48 (d) 64

Last Answer : (c) 48

Description : In glycoproteins the carbohydrate is in the form of disaccharide units, the number of units are (A) 50–100 (B) 200–300 (C) 400–500 (D) 600–700

Last Answer : Answer : D