Change X requires a higher level of authority than Change Y in which of the
following pairs? Change X Change Y
A. Code in development Code in production
B. Specifications during requirements analysis Specifications during systems test
C. Documents requested by the technical development group Documents requested by customers
D. A product distributed to several sites A product with a single user

1 Answer

Answer :

D. A product distributed to several sites A product with a single user

Related questions

Description : We use the output of the requirement analysis, the requirement specification as the input for writing :- a) User Acceptance Test Cases b) Integration Level Test Cases c) Unit Level Test Cases d) Program specifications

Last Answer : a) User Acceptance Test Cases

Description : Acceptance testing means A. Testing performed on a single stand - alone module or unit of code B. Testing after changes have been made to ensure that no unwanted changes were introduced C. ... the needs of the organization and end user. D. Users test the application in the developers environment

Last Answer : C. Testing to ensure that the system meets the needs of the organization and end user.

Description : Deciding how much testing is enough should take into account:- i. Level of Risk including Technical and Business product and project risk ii. Project constraints such as time and budget iii. Size of Testing Team iv. Size ... ii are true and iii, iv are false d) ii, iii, iv are true and i is false

Last Answer : c) i, ii are true and iii, iv are false

Description : Match every stage of the software Development Life cycle with the Testing Life cycle: i. Hi-level design a Unit tests ii. Code b Acceptance tests iii. Low-level design c System tests iv. Business requirements d Integration tests a) i-d , ii ... i-b , ii-a , iii-d , iv-c d) i-c , ii-a , iii-d , iv-b

Last Answer : d) i-c , ii-a , iii-d , iv-b

Description : The primary goal of comparing a user manual with the actual behavior of the running program during system testing is to A. Find bugs in the program B. Check the technical accuracy of the document

Last Answer : B. Check the technical accuracy of the document

Description : Software testing activities should start A. As soon as the code is written B. During the design stage C. When the requirements have been formally documented D. As soon as possible in the development lifecycle

Last Answer : C. When the requirements have been formally documented

Description : Defects are least costly to correct at what stage of the development cycle? A. Requirements B. Analysis & Design C. Construction D. Implementation

Last Answer : A. Requirements

Description : Evaluating testability of the requirements and system are a part of which phase:- a) Test Analysis and Design b) Test Planning and control c) Test Implementation and execution d) Evaluating ... text box which accepts alphabets in lower or upper case. Identify the invalid Equivalence class value.

Last Answer : a) Test Analysis and Design

Description : Which of the following is the task of a Test Lead / Leader: i. Interaction with the Test Tool Vendor to identify best ways to leverage test tool on the project. ii. Write Test Summary Reports based on the ... is true and ii,iii,iv are false d) iii and iv is correct and i and ii are incorrect

Last Answer : a) i, ii, iii is true and iv is false

Description : For final software acceptance testing, the system should include A. Delivered software B. All user documents C. Final version of oth

Last Answer : D. All of the above

Description : The selection of test cases for regression testing A. Requires knowledge on the bug fixes and how it affect the system B. Includes the area of frequent defects C. Includes the area which has undergone many/recent code changes D. All of the above

Last Answer : D. All of the above

Description : Test Conditions are derived from :- a) Specifications b) Test Cases c) Test Data d) Test Design

Last Answer : a) Specifications

Description : A test harness is a A. A high level document describing the principles, approach and major objectives of the organization regarding testing B. A distance set of test activities collected into a manageable phase ... conduct a test D. A set of several test cases for a component or system under test

Last Answer : C. A test environment comprised of stubs and drives needed to conduct a test

Description : “The tracing of requirements for a test level through the layers of a test documentation” done by A. Horizontal tracebility B. Depth tracebility C. Vertical tracebility D. Horizontal & Vertical tracebilities

Last Answer : A. Horizontal tracebility

Description : Which of the following uses Impact Analysis most? a) Component testing b) Non-functional system testing c) User acceptance testing d) Maintenance testing

Last Answer : d) Maintenance testing

Description : Coverage based analysis is best described as: A. A metric used to show the logic covered during a test session providing insight to the extent of testing. B. A tool for documenting the unique ... their status through to resolution. D. The most traditional means for analyzing a system or a program

Last Answer : A. A metric used to show the logic covered during a test session providing insight to the extent of testing.

Description : Historically, Knox PLC sold industrial clamps directly to firms using these items in their production process. Knox's Chairman believes that it may be time to start using an industrial distributor because ... D)carry a more complete line of Knox clamps. E)market the products to Knox specifications.

Last Answer : A)provide Knox with market information.

Description : Which of the following techniques is NOT a black box technique? a) State transition testing b) LCSAJ (Linear Code Sequence and Jump) c) syntax testing d) boundary value analysis

Last Answer : b) LCSAJ (Linear Code Sequence and Jump)

Description : What is NOT a test log? A. Maps the test results to requirements B. Records test activities C. Maintains control over the test D. Contains pass or fail results.

Last Answer : A. Maps the test results to requirements

Description : In preparation for developing the acceptance criteria, the user should A. Know the defects in the application B. Acquire the basic knowledge of the application for which the system is ... D. Know new enhancement and basic understanding of how the application is implemented in users organization

Last Answer : Understand the risks and benefits of the development methodology that is to be used in correcting the software system

Description : Which of the following is not a type of test under phases in testing life cycle? A. Integration test B. Load test C. User Acceptance test D. Beta test

Last Answer : D. Beta test

Description : Which of the following is a part of Test Closure Activities? i. Checking which planned deliverables have been delivered ii. Defect report analysis. iii. Finalizing and archiving testware. iv. Analyzing lessons. a) i , ii , ... false c) i , iii , iv are true and ii is false d) All of above are true

Last Answer : c) i , iii , iv are true and ii is false

Description : Which of the following is not phase of the Fundamental Test Process? a) Test Planning and Control b) Test implementation and Execution c) Requirement Analysis d) Evaluating Exit criteria and reporting

Last Answer : c) Requirement Analysis

Description : Impact Analysis helps to decide :- a) How much regression testing should be done. b) Exit Criteria c) How many more test cases need to written. d) Different Tools to perform Regression Testing

Last Answer : a) How much regression testing should be done.

Description : In a system designed to work out the tax to be paid: An employee has £4000 of salary tax free. The next £1500 is taxed at 10%. The next £28000 after that is taxed at 22%. Any further amount is taxed ... of these is a valid Boundary Value Analysis test case? A. £28000. B. £33501. C. £32001. D. £1500

Last Answer : B. £33501.

Description : Assume postal rates for 'light letters' are: $0.25 up to 10 grams; $0.35 up to 50 grams; $0.45 up to 75 grams; $0.55 up to 100 grams. Which test inputs (in grams) would be selected using boundary value analysis? A. 0, 9,19, ... C. 0, 1,10,11, 50, 51, 75, 76,100,101 D. 25, 26, 35, 36, 45, 46, 55, 56

Last Answer : C. 0, 1,10,11, 50, 51, 75, 76,100,101

Description : A wholesaler sells printer cartridges. The minimum order quantity is 5. There is a 20% discount for orders of 100 or more printer cartridges. You have been asked to prepare test cases using various values for the number of printer cartridges ... A. 5, 6, 20 B. 4, 5, 80C. 4, 5, 99 D. 1, 20, 100

Last Answer : C. 0, 1,10,11, 50, 51, 75, 76,100,101

Description : Test data planning essentially includes A. Network B. Operational Model C. Boundary value analysis D. Test Procedure Planning

Last Answer : C. Boundary value analysis

Description : In case of Large Systems :- a) Only few tests should be run b) Testing should be on the basis of Risk c) Only Good Test Cases should be executed. d) Test Cases written by good test engineers should be executed.

Last Answer : b) Testing should be on the basis of Risk

Description : Acceptance tests are normally conducted by the A. Developer B. End usersC. Test team D. Systems engineers

Last Answer : B. End users

Description : A primary advantage of the concentration targeting strategy is that: A)it requires less market research and information B)it requires less intensive analysis of customers needs C)it maintains the ... market segments D)it permits development of a special marketing mix for a single market segment

Last Answer : D)it permits development of a special marketing mix for a single market segment

Description : Which one of the following statements is incorrect ? (A) Pareto analysis is a statistical method used for analyzing causes, and is one of the primary tools for quality management. (B) Reliability of ... (D) In white-box testing, the test cases are decided from the specifications or the requirements.

Last Answer : (D) In white-box testing, the test cases are decided from the specifications or the requirements.

Description : Exit Criteria may consist of :- i. Thoroughness measures , such as coverage of code, functionality or risk ii. Estimates of Defect density or reliability measures. iii. Residual risk such as defects not fixed or ... correct and i,ii,iii are incorrect d) iii and iv are correct and i,ii are incorrect

Last Answer : b) i,ii,iii is correct and iv is incorrect

Description : Test planning should begin A. At the same time that requirement definitions begins B. When building starts C. When code build is complete D. After shipping the first version

Last Answer : A. At the same time that requirement definitions begins

Description : Your company has asked you to be the project manager for the product introduction  of its new DeskTop Rock media system. You recently published the project scope  statement. Which ... . Constraints  B. Project specifications  C. Requested changes D. Project configuration management requirements

Last Answer : C. Requested changes

Description : There is one application, which runs on a single terminal. There is another application that works on multiple terminals. What are the test techniques you will use on the second application that ... B. Concurrency test, Scalability C. Update & Rollback, Response time D. Concurrency test, Integrity

Last Answer : C. Update & Rollback, Response time

Description : Acceptance requirements that a system should meet is A. Usability B. Understandability C. Functionality D. Enhancements

Last Answer : C. Functionality

Description : System test can begin when? I. The test team competes a three day smoke test and reports on the results to the system test phase entry meeting II. The development team provides software to the test team 3 business days prior ... . I and II only B. II and III only C. I and III only D. I, II and III

Last Answer : D. I, II and III

Description : During the testing of a module tester X' finds a bug and assigned it to developer. But developer rejects the same, saying that it's not a bug. What X' should do? A. Report ... same bug to another developer D. Send to the detailed information of the bug encountered and check the reproducibility

Last Answer : D. Send to the detailed information of the bug encountered and check the reproducibility

Description : During the testing of a module tester X' finds a bug and assigned it to developer. But developer rejects the same, saying that it's not a bug. What X' should do? A. Report ... same bug to another developer D. Send to the detailed information of the bug encountered and check the reproducibility

Last Answer : D. Send to the detailed information of the bug encountered and check the reproducibility

Description : Which is not the responsibility of customer/ user of the software A. Plan how and by whom each acceptance activity will be performed B. Prepare the acceptance plan C. Prepare resource plan D. Plan resources for providing information on which to base acceptance decisions

Last Answer : C. Prepare resource plan

Description : In practice, which Life Cycle model may have more, fewer or different levels of development and testing, depending on the project and the software product. For example, there may be component integration testing ... after system testing. A. Water Fall Model B.V-Model C. Spiral Model D. RAD Model

Last Answer : B.V-Model

Description : In practice, which Life Cycle model may have more, fewer or different levels of development and testing, depending on the project and the software product. For example, there may be component integration testing after component testing, and

Last Answer : B.V-Model

Description : Which of the following has highest level of independence in which test cases are : a) Designed by persons who write the software under test b) Designed by a person from a different sectionc) Designed by a person from a different organization d) Designed by another person

Last Answer : c) Designed by a person from a different organization

Description : It is difficult to create test scenarios for high-level risks A. True B. Fals

Last Answer : A. True

Description : _________must be developed to describe when and how testing will occur. A. Test Strategy B. Test Plan C. Test Design D. High Level document

Last Answer : B. Test Plan

Description : )The fixed price contract is advantageous to the buyer because it: 1. requires extremely well defined specifications  2. requires formal procedures for scope changes  3. contractor assumes financial and technical risk  4. has a known cost

Last Answer : 3. contractor assumes financial and technical risk