What Are The Different Project Scheduling Techniques?

1 Answer

Answer :

Program evaluation and review technique (PERT) and the critical path method (CPM) are two project scheduling methods that can be applied to software development. CPM provides critical path to analyze project and duration. PERT uses
TE = (O + 4M + P) / 6 formula for the expected completion time. Where
O=optimistic time
P=pessimistic time
M=most likely time
TE =expected time
Describe the risk in software engineering.
Risk is a potential problem, it may come or it may not come while developing the software. Risks are uncertain. It is a good idea to analysis the risk, what is the chance to occur the risk, what will be the impact on the project and what are the positive planes to overcome of these risks is. There are two types of risk strategies: Reactive risk strategies and proactive risk strategies. In reactive risk strategies software team come in action when something goes wrong. A proactive risk strategy starts with long before technical work is initiated. Potential risks are identified and their impacts are analyzed. Then, the software team establishes a plan for managing risk.

Related questions

Description : What Are The Csfs In The Software Project Management ?

Last Answer : The CSFs (critical success factors) for a successful software project management are listed blow:  Change management is very essential.  Leadership & motivating employees for giving direction.  Team ... be done diligently in the given time frame.  Lucidity in communication is very essential.

Description : Describe The 4 P’s In Software Project Management?

Last Answer : Software project management focuses on the four P's: people, product, process, and project. The People: For success of any type of project, the most important factor is the skilled people. ... obtained. 9. The project team lacks people with appropriate skills. 10. Managers [and practitioners]

Description : How Does A Project Manager Can Avoid The Above Given Ten Points For The Success Of Project?

Last Answer : Reel suggests these five-part commonsense approaches to software projects:  Start on the right foot.  Maintain momentum.  Track progress.  Make smart decisions.  Conduct a postmortem analysis.

Description : What Is The Meaning Of Scope Of The Project?

Last Answer : The functions and features that are to be delivered to the customer is called the scope of the project. Performance, user interface design, and constraints should meet the customer ... developed after communication with all members those are directly or indirectly involved in the project.

Description : What Is Software Project Planning?

Last Answer : It is a set of activities that are collectively called project planning. In project planning a software company considers the following points:  Scope of the project.  Feasibility analysis.  Deadline of the project.  Estimation of resource cost and schedule.  Risk analysis.  Overall Budget.

Description : What Are The Different Software Reengineering Activities?

Last Answer : Different software activities are as follows: Inventory analysis: The inventory is nothing but a type of spreadsheet model that contain detailed description of every active application. It should be ... information to change the existing system. It will improve the overall quality of the system.

Description : What Are The Different Types Of Software Risks?

Last Answer : The different types of risks are as follows: Project risks: This type of risk can destroy your project plan. The release date of project may postpone further and cost will increase. Technical risks: ... of business risk such as market risk, strategic risk, sales risk, management risk, budget risk.

Description : Describe Capability Maturity Model (cmm)?

Last Answer : Every organization has some process to develop the software. Software Engineering Institute (SEI) has developed a model that provides the different levels of process maturity. In this model, in every level there are ... Repeatable. 3. Level 3: Defined. 4. Level 4: Managed. 5. Level 5: Optimizing.

Description : What Is A Process?

Last Answer : It is a set of structured and related activities which are performed to achieve a specific business goal. They can be categorized into 3 sub categories:  Management processes  Operational processes  Supporting processes

Description : Which of the following disk scheduling techniques has a drawback of starvation? (A) SCAN (B) SSTF (C) FCFS (D) LIFO 

Last Answer : Which of the following disk scheduling techniques has a drawback of starvation? (A) SCAN (B) SSTF (C) FCFS (D) LIFO 

Last Answer : The scheduler is very important in Real-Time Operating System (RTOS). Selection of tasks for execution is provided by the scheduler. Which task to execute when it is provided by the ... . Non-preemptive scheduling is simple.Preemptive scheduling is flexible while non-preemptive scheduling is rigid.

Description : Scheduling can best be defined as the process used to determine: a. overall project duration. b. project cost estimating. c. the project management plan. d. sub-contractor’s responsibilities.

Last Answer : a. overall project duration.

Description : Which of the following activity is not the part of project planning? A. project estimation B. project scheduling C. project monitoring D. risk management

Last Answer : C. project monitoring

Description : Which of the following activity is undertaken immediately after feasibility study and before  the requirement analysis and specification phase? A. Project Planning B. Project Monitoring C. Project Control D. Project Scheduling

Last Answer : A. Project Planning

Description : In project scheduling, resources are allocated so that project objectives are attained within a ……… a. sensible time span b. lavish time c. excessive d. undue

Last Answer : a. sensible time span

Description : According to leading experts in software development, the margin of error when  estimating project costs is 100% and the margin of error in project scheduling time is  25%.

Last Answer : Ans: True

Description : Scheduling can best be defined as the process used to determine:  a. overall project duration.  b. project cost estimating.  c. the project management plan.

Last Answer : a. overall project duration.

Description : A prerequisite of effective time management is:  1. Knowing the dictated project completion date  2. Having the most advanced software package for project planning, scheduling and control  3. ... and the  person responsible for each of them  4. Having a well staffed scheduling department

Last Answer : 1. Knowing the dictated project completion date

Description : )Which of the following is NOT one of the primary needs for good project scheduling? 1. Cutting costs and reducing time  2. Decreasing the time required for decision making  3. Eliminating idle time  4. Developing better trouble shooting procedures.

Last Answer : 4. Developing better trouble shooting procedures.

Description : What is the benefit of using PERT/CPM network as integral component of project management? a. They furnish a consistent framework for planning, scheduling, monitoring and controlling project b. They illustrate ... that the project will be completed by a specific date d. All of the above

Last Answer : d. All of the above

Description : While scheduling a project by C.P.M. (A) A project is divided into various activities (B) Required time for each activity is established (C) Net work is drawn by connecting the activities and the events (D) All the above

Last Answer : (D) All the above

Description : The technique for establishing and maintaining priorities among the various jobs of a project, is known (A) Event flow scheduling technique (B) Critical ratio scheduling (C) Slotting technique for scheduling (D) Short interval scheduling

Last Answer : (B) Critical ratio scheduling

Description : What Should The Project Manager Look For In A Scheduling System?

Last Answer : The three basic elements that the project scheduling systems should provide are; a common basis for communication at all operational levels of the project, a basis for regular status reporting, the use of the management by exception technique.

Description : How do project scheduling help achieve project execution?

Last Answer : When the activity effort and resource estimates are known getting the work done depends on how the tasks are sequenced. Dependencies with other activities have to be clearly known. The basic ... no constraints there. Scheduling is done from activities list prepared after WBS has been finalized.

Description : ____________ is a graphical representation of the various activity and event relating to a project. A. Network analysis. B. Scheduling technique. C. Logical Model. D. Network Diagram

Last Answer : D. Network Diagram

Description : _____________ is used to accomplish the project economically in the minimum available time with limited resources A. Project Scheduling. B. Network Analysis. C. Budget Analysis. D. Critical Planning.

Last Answer : A. Project Scheduling.

Description : What is project scheduling?

Last Answer : Software project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks. During early stages of project ... (CPM) are two project scheduling Methods that can be applied to software development.

Description : Explain four basic principles of software project scheduling.

Last Answer : Basic principles software project scheduling:  Compartmentalization: The project must be compartmentalized into a number of manageable activities and tasks. To accomplish compartmentalization, both the product and ... or part of a work product - Work products are often combined in deliverables 

Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of activities ... endeavor undertaken to achieve a desired outcome. d. A project is a method of planning work.

Last Answer : c. A unique transient endeavor undertaken to achieve a desired outcome.

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : According to the Project Management Institute (PMI), project  management is defined as the application of knowledge, _____, _____, and  techniques to project activities to meet the project requirements . Select ... b. tools, analysis c. analysis, theories d. skills, tools e. skills, theories

Last Answer : d. skills, tools

Description : Which of the following items should not be included in the  project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development  organisation, project responsibilities, managerial  objectives and priorities e) None of the above.

Last Answer : c) The life cycle model to be used

Description : Project management includes the tools, techniques, and essential to  deal with the growth of products a. Knowledge b. Skill c. Attitude d. Confidence

Last Answer : a. Knowledge

Description : Monte Carlo analysis can help predict the impact of risks on project deliverables.  This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis

Last Answer : B. Quantitative Risk Analysis

Description : Which one of the following statements best describes a project?  a. A project is a set of tools and techniques often used when delivering organisational change.  b. A project is the sum of ... endeavour undertaken to achieve a desired outcome.  d. A project is a method of planning work.

Last Answer : c. A unique transient endeavour undertaken to achieve a desired outcome.

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time.  b. to deliver the project objectives to ... benefits.  d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : For a project manager to have an effective means of identifying and communicating the planned activities and their interrelationships, he must use a network technique. One of the network ... evaluation review technique c. Path evaluation review technique d. Project execution review technique

Last Answer : b. Program evaluation review technique

Description : FP-based estimation techniques require problem decomposition based on (A) information domain values (B) project schedule (C) software functions (D) process activities

Last Answer : (C) software functions

Description : PERT stands for __________. A. Programme Evaluation and Research Techniques. B. Project Evaluation and Review Techniques. C. Programme Evaluation and Review Techniques. D. Project Evaluation and Research Techniques.

Last Answer : C. Programme Evaluation and Review Techniques.

Description : A company wants to manage job scheduling centrally and has the requirements toexecute job chains across different SAP systems. Which batch scheduling tool do you recommend? A. SAP Central Process ... Process Scheduling (full version) D. The Job Management work center in SAP Solution Manager

Last Answer : C. SAP Central Process Scheduling (full version)

Description : Which of the following statements is not true for Multi Level Feedback Queue processor scheduling algorithm? (A) Queues have different priorities. (B) Each queue may have different scheduling algorithm (C) ... to a queue (D) This algorithm can be configured to match a specific system under design

Last Answer : (C) Processes are permanently assigned to a queue

Description : Which scheduling service is used to handle traffic with different priorities? (1) Traffic management (2) QoS traffic scheduling (3) QoS Scheduler (4) Qos Manager

Last Answer : QoS traffic scheduling

Description : For optimum generator scheduling for different power plants, the minimum fuel cost is obtained when

Last Answer : For optimum generator scheduling for different power plants, the minimum fuel cost is obtained when The incremental fuel cost of each plant multiplied by the penalty factor is the same

Description : Can Arduino be used for building a smart irrigation scheduling system?

Last Answer : Yes, Arduino can be used for building a smart irrigation scheduling system by using sensors to measure soil moisture levels and weather conditions, and by using communication modules to transmit data to a control system to optimize irrigation scheduling.

Description : When exactly did the over-scheduling of kids occur, and is there a way to reverse this?

Last Answer : answer:I’m considering taking bolt cutters to the gates outside the Little League baseball fields about a mile from my house. It’s a county-maintained park, and we’re not allowed to use the batting cages because we’re not members of Little League. That pisses me RIGHT the fuck off.

Description : Does anyone know of a good employee shift scheduling app?

Last Answer : Hope this helps: 2013 Best Employee Scheduling Software Comparisons ShiftPlanning On The Go With Apple iPhone Schedule App Simple Online Employee Scheduling

Description : Should single working parents get some sort of scheduling preferences?

Last Answer : No, they should not.

Description : Nuvaring scheduling/safety question.

Last Answer : My guess and it is only a guess is that you are protected. However, I’m not a doctor and cannot be 100% sure. Give your gynecologist a call on Monday morning. He/she should have the best answer.

Description : Do you like block scheduling in high school that is?

Last Answer : I liked block scheduling in high school. It game me more time to complete my homework and meant that I didn’t have to see the teachers I didn’t like every day.