State any four factors governing Selection of site for thermal power station. 

2 Answers

Answer :

Following points are considered while selecting site for thermal power station:- 

1. Distance from coal mines :- The power plant should be located near the coal mines, to reduce cost of transportation. 

2. Availability of Water :- Plant should be located near large water reservoir, lake, river or ocean as water is as good as secondary fuel. 

3. Distance from populated area:- As TPP produces air pollution, PP should be located away from populated area. 

4. Easy access:- There should be easy access towards site of power plant for transportation of construction material, machinery, equipment, man power, fuel etc.

5.Near Load Centre:- Power Plant should be located near load center to reduce transmission cost & Losses in transmission line. 

6. Availability of land :- Sufficient large space should be available to build the power plant, for storage of coal, for storage of ash, for staff quarters and also for Future expansion of the power plant. 

7. Condition of land soil:- The land should have high bearing capacity for better foundation of machinery, equipment and buildings. Also, the plant should be constructed on plane land. 

8. Cost of land :- Cost of land should be less to reduce capital cost of power plant. 

9. Away from airport:- As height of chimney is very high, it should be located away from airport. 

10. Earthquake:- Area should be free from earthquake and other natural hazards. 

11. Availability of labour:- Skilled and unskilled labour should be available nearby.

Answer :

Following Factors are to be considered:- 1. It should locate near coal mine. 2. Sufficient quantity of water should be available. 3. Sufficient large space should be available. 4. It should be located near load centre. 5. There should be easy access towards power plant. 6. Cost of land should be less. 7. Land should be of good bearing capacity. 8. It should be located away from populated area. 9. Skilled & unskilled labor should be available. 10. Area should be free from earthquake. 


OR 


1. A large extent of land is required for the erection of thermal plant. So, the cost of the land has a considerable bearing on the working of a thermal plant. So, the cost of the site should be reasonable. 2. The private land should be as minimum as possible. 3. The operation of a thermal plant requires huge quantities of water. So, it is preferable to have the site near the canal or a river. 4. Facilities should exist for the transport of fuel. 5. The soil should not be too loose or too rocky. 6. The site should be level. There should be no excavation nearby. 7. The site should be far away from the residential localities so as to avoid the nuisance of smoke, noise, etc. 8. Future extensions of the power station should be possible. 9. Sufficient land must be available nearby the power station to build the residential accommodation to the operation and maintenance staff. 10. Ash disposal should not create any problem. 11. To the extent possible, the thermal station should be far away from an aerodrome. 12. If canal or river water is used, it should not be polluted to ensure that the interests of the other users are not affected. 13. The design should be in conformity with the by-laws of the land and the town planning. 14. The interests of national defense must be served.

Related questions

Description : State the various factors governing selection of site for TPS. 

Last Answer : Following various factors governing selection of site for TPS.:- 1. It should locate near coal mines. 2. Sufficient quantity of water should be available. 3. Sufficient large space should ... availalbe nearly. To the extent possible, the thermal station should be far away from an aerodrome   

Description : State and explain any four factors governing selection of induction motor.

Last Answer : The factors governing the selection of Induction motor: 1) Load torque required at normal speed matches with available torque of motor. 2) Break down torque or pull out torque or maximum torque ... If selecting energy efficient motor the cost benefit analysis over the long run must be worked out.

Description : State any four factors for selection of hydro power plant site. 

Last Answer : Following Factors to be kept while site selecting for Hydro power plant: 1) Quantity of water available :-Where high rainfall occures so that sufficent quantity of water can be stored for generation of ... be possible to divert the stream. 11. Sand, gravel, etc., should be available nearby.

Description : State any four factors for selection of site of wind power plant.

Last Answer : The Factors for selection of site for Wind Mills: 1) The site should be selected where winds are strong i.e. where pressure of wind is high and there is continuity (14.4- 16.2 km/h) ... 50m of the turbine which can affect the system's overall performance 10)Possibility to connect to power grid. 

Description : State the function of cooling tower and condenser in thermal power station.

Last Answer : 1. Condenser:   Function of condenser is to convert exhaust steam again into water by reducing its temperature with the help of cold water. Also it reduces back pressure of steam turbine 2 ... tower : The function of cooling tower is to reduce the temperature of water coming from condenser.

Description : Classify condensers used in thermal power station. Explain each type in brief. 

Last Answer : Types of condenser: Classification: 1. Jet Condenser (Mixing Type) 2. Surface condenser (non Mixing type)  Explanation:-   1. Jet Condenser (Mixing Type) In Jet condenser the steam ... there in no direct contact between the steam and cooling water. This condensate is reused in boiler. 

Description : "Efficiency of thermal power station is low". — Justify. 

Last Answer : Justification: Efficiency of thermal power station is low":- Overall efficiency of T.P.P depends upon efficiency of boiler, turbine and alternator. The heat produced due to combustion of coal ... losses in thermal power plant is 71%, So efficiency of thermal power plant is less about 29% 

Description : State any four factors for selecting location of nuclear power plant.

Last Answer : i) Seismicity: If the area of a nuclear site is seismically active, it may not be used for nuclear power plant.  ii) Water Availability: The nuclear power plants would need a ... Therefore, the site selected for such plant should have adequate arrangement for the disposal of radioactive waste.

Description : Write any four advantages and four disadvantages of thermal power plant.

Last Answer : .embed-container { position: relative; padding-bottom: 56.25%; height: 0; overflow: hidden; max-width: 100%; } .embed-container iframe, .embed-container object, .embed-container embed { position: absolute; top: 0; left: 0; width: 100%; height: 100%; }

Description : List and state any four limitations of inter connected power station.

Last Answer : Limitations of inter connected power station:- 1) Initial cost of infrastructure of transmission line increases as length increases. 2) Interconnection required more automation which increases cost on ... capacity. But in absence of surplus power merits of interconnection cannot be obtain.

Description : State advantages of Pulverized coal w.r.t. thermal power plant. 

Last Answer : Advantages of Pulverized coal w.r.t. thermal power plant.  1. Due to pulvarization amount of fuel required to produce same amount of heat reduces. 2. Time required for combution reduces ... of air and thorough mixing of air and fuel, very high-combustion temperatures can be attained.

Description : State the function of super heater of a thermal power plant. 

Last Answer : Function of Super heater: -  Its function is to increase the temperature of steam by absorbing heat from exhausted hot flue gases.

Description : Explain ash disposal and dust collection in a thermal power plant.

Last Answer : Ash disposal:-  Various methods of disposal of ash are:  Mechanical handling system.  Pneumatic system. Hydraulic system  Steam jet system  Commonly used ash handling ... be done either manually or automatically.  This removed fly ash is collected in separate container

Description : The unit heat rate characteristic of a thermal power unit shows :  (A) Heat input per kWh of output versus the megawatt output of unit  (B) Heat input per kW of output versus the megawatt output ... hour output of unit  (D) Heat input per kW of output versus the megawatt hour output of unit

Last Answer : The unit heat rate characteristic of a thermal power unit shows : Heat input per kWh of output versus the megawatt output of unit 

Description : State the function of following components of a nuclear power station: i) Moderator ii) Shielding iii) Control rod iv) Coolant 

Last Answer : i) Function of Moderator :- Moderator is to moderate or reduce the speed of fast neutron to help the fission process.  ii) Function of sheilding : Shielding is to protect environment, ... from reactor core and transfer it in heat exchanger for producing steam at high pressure and temperature. 

Description : State the types of radioactive waste generated in a nuclear power station. Explain the methods employed for their disposal.

Last Answer : Types of radioactive waste: The waste produced in nuclear power plant is in the form of solid, liquid & gases, 1. Solid Waste Disposal:-  Solid wastes removed from the reactor are very ... are measured. If it is safe then released to atmosphere at high level through large height chimney.

Description : State the functions of fuel system and exhaust system of a diesel power station.

Last Answer : Fuel system: It supplies fuel to engine for combustion purpose. It consists of Fuel Pump: - It supplies fuel to engine for combustion purpose. Strainer: - Are provided to remove suspended impurities and ... most of the noise. Chimney:- To exhaust gases in the atmosphere as high as possible. 

Description : State the purpose of surge tank and spill way in hydroelectric power station.

Last Answer : Surge tank :- A surge tank is the small reservoir or tank. It is open at the top. It is installed near Vale house of turbine. It avoids water hammer effect when load on turbine reduces. (It ... ; during floods etc. In this way spill way avoids damage of dam due to excess pressure of water.

Description : Compare the Nuclear power station with Hydro power station. 

Last Answer : SR. No.  Points Nuclear Power plant  Hydro Power station  1 Site/ Location Where there is ample supply of water is available, away from thickly populated areas to avoid radioactive ... Field Application As base load  Used as base load during as well as peak load 

Description : Explain the working of Hydro power station with schematic layout. 

Last Answer : Working of Hydro- Electric Power Plant: Water stored at high level by constructing dam across river. This stored water has potential energy. This stored water is passed to run the water ... energy and Alternator is coupled to water turbine which converts mechanical energy into electrical energy. 

Description : Applications of Diesel power station

Last Answer : Applications of Diesel Power Station:  1. It can be used as a standby (emergency) power plant to maintain continuity of supply. (Incase failure of main supply like hospital, Telephone exchange Radio ... 10. Diesel plants are widely used for generating power ranging from 100 to 5,000 H.P. 

Description : List out main components of Diesel power station. 

Last Answer : Main components of Diesel power station: 1) Diesel Engine 2) Engine Air intake system 3) Engine Fuel System 4) Engine Exhaust system 5) Engine cooling system 6) Engine Lubricating system 7) Engine Starting system 8) Diesel Engine Generator (Alternator) 

Description : "Hydro electric power station are not perennial power station". Justify.

Last Answer : Justification: The water utilized by the hydro power plants comes mostly from storage dams/reservoirs which get filled up during the monsoon rainy season. Such reservoirs are utilized for supplying ... are important. Hence "Hydro electric power stations are not perennial power station" 

Description : Write down any two advantages of nuclear power station.

Last Answer : Advantages of nuclear power station :-  1) Fuel required: Fuel requirment of Nuclear Power Plant is less than Thermal Power Plant. So it reduces transportation cost of fuel and space required for fuel storage ... By use of nuclear fuel.,it saves the other fossile fuels like-coal, gas, oil, etc.

Description : The overall efficiency of Thermal Power Plant is equal to _______________ .  (A) Regenerative Cycle Efficiency (B) Renkine Cycle Efficiency (C) Carnot cycle efficiency (D) None of the above

Last Answer : The overall efficiency of Thermal Power Plant is equal to Regenerative Cycle Efficiency. 

Description : In a thermal power plant, ash is collected in

Last Answer : In a thermal power plant, ash is collected in hoppers or bunkers

Description : The main disadvantages of having poor power factors are:  (A) High cost of station and distribution equipment (B) Poor voltage regulation (C) High energy loss in conductor (D) All of the above

Last Answer : The main disadvantages of having poor power factors are:  (A) High cost of station and distribution equipment (B) Poor voltage regulation (C) High energy loss in conductor (D) All of the above

Description : How Do I Build a Low Power FM Radio Station?

Last Answer : How Do I Build a Low Power FM Radio Station? A low power FM radio station offers individuals or small groups the ability to go on the air and communicate with the general public using FM radio ... FCC or your local government to determine which, if any FM frequencies you are allowed to transmit on.

Description : Power station having Load factor = 70%, capacity factor = 50%, used factor = 60%, maximum demand = 20MW then annual energy production is  (1) 122.8 GWh (2) 198.55 GWh (3) 128.2 GWh (4) 188.82 GWh

Last Answer : Power station having Load factor = 70%, capacity factor = 50%, used factor = 60%, maximum demand = 20MW then annual energy production is 122.8 GWh

Last Answer : For high value of diversity factor, a power station of given installed capacity will be in a position to supply more number of consumers.

Last Answer : Load factor of a power station is generally less than unity.

Last Answer : Load factor of a power station is defined as average load/maximum demand.

Last Answer : For the protection of power station buildings against direct strokes the requirements are interception, conduction and dissipation.

Description : State the selection criterion of the lamp for various purposes.

Last Answer : Selection criterion of the lamp for various purposes:  While selecting a lamp for a particular purpose, the available lamps are compared on the basis of following criteria: * Light output ... such as ballasts * Compatibility with the electrical system * Suitability for the operating environment

Description : State criteria for selection of contractor. 

Last Answer : Following the criteria for selection of contractor: 1. Contractor should be well reputed 2. Past experience of the Contractor 3. Contractor licenses should be valid 4. Works in hand of ... Material availability of the contractor. 6. Tax clearance certificate & financial power of contractor.

Description : Selection Criteria of PLC

Last Answer : Selection criteria :- To select PLC for any particular application following points are to be considered. a) Type of PLC: Analog or Digital b) Number of inputs and outputs to PLC c) Operating voltage ... Type of memory of PLC g) Type of programming h) Reliability of PLC i) Flexibility of PLC

Description : Explain selection of starters for Industrial Installation. 

Last Answer : selection of starters for Industrial Installation: Every motor must be provided with a starter to start and stop the motor. It shall be within the sight of a person at the motor. It shall be so arranged as ... -Auto transformer starter  Slip ring I.M.------------------Rotor resistance starter

Description : State the factors affecting hysteresis loss.

Last Answer : i) Flux density ii) Frequency iii) Volume of the magnetic material iv) Nature of magnetic material

Description : Define thermal runaway.

Last Answer : Thermal runaway  The problem with increasing temperature causing increasing collector current is that more current increase the power dissipated by the transistor which, in turn, increases its temperature ... self-reinforcing cycle is known as thermal runaway, which may destroy the transistor. 

Description : Sketch block diagram of satellite earth station and state functions of each block

Last Answer : The figure below shows the general block diagram of an earth station capable of transmission, reception and antenna tracking. The following are the major subsystems of ... , possible monitoring of satellite characteristics and occasionally for the measurement of special characteristics. 

Description : Write any two factors on which earth resistance depends.

Last Answer : Factors on which earth resistance depends: (1) The shape and material used for the electrode (2) Depth of the electrode in the ground. (3) The specific resistance of the soil around the electrode (4) Moisture content in the soil. (5) Nature of soil 

Description : What factors affect resistivity?

Last Answer : 1)type of material 2)temperature 3)length and area of cross section of conductor

Description : Define the following terms : (i) Base Station (ii) Control Channel (iii) Mobile Station (iv) Page 

Last Answer : i) Base Station: - A fixed station in a mobile radio system used for radio communication with mobile stations. Base stations are located at the center or on the edge of a coverage region ... the page throughout the service area using base stations which broadcast the page on a radio carrier.

Description : State two factors deciding size of conduit.

Last Answer : Following factors deciding size of conduit: 1) Types of wiring method 2) No. of wires carried out through conduit 3) Size of wires required for sub circuits which is carried out through conduit 4) Future expansion.

Description : Explain the thermal triggering method of SCR. Enlist different triggering methods of SCR.

Last Answer : Types of Triggering: 1) Forward voltage triggering 2) Thermal triggering (Temperature triggering) 3) Radiation triggering (Light triggering) 4) dv/dt triggering 5) Gate triggering ... generated leakage current increases. This current gets multiplied internally and thyristor is turned on. 

Description : Describe thermal runaway of transistor and explain how it can be avoided.

Last Answer : Concept of thermal runaway:  1.We know that  IC = β IB + (1+ β) ICO  Where ICO is the leakage current and ICO is strongly dependent on temperature. 2. Leakage current approximately doubles for ...   Thermal runaway can be avoided by : 1) Using stabilization circuitry 2) Heat sink 

Last Answer : Thermal overload relays are used to protect the motor against overcurrent due to heavy loads.

Last Answer : Thermal circuit breaker has delayed trip action.

Last Answer : A thermal protection switch can protect against overload.

Description : List out factors affecting proximity effect. 

Last Answer : Factors affecting proximity effect: 1. Conductor size (diameter of conductor) 2. Frequency of supply current. 3. Distance between conductors. 4. Permeability of conductor material