Considers the total cost of ownership, or development plus support costs, for a project.

A. Learning Curve Theory

B. Life Cycle Costing

C. Parametric Modeling

D. Rate of

Performance

1 Answer

Answer :

B. Life Cycle Costing

Related questions

Description : One of the reasons a project life cycle is split into phases is to: a. facilitate formal go/no-go decision making during the project. b. balance the costs of work in each phase of ... the major deployments of resources throughout the project. d. chunk work into time periods of similar durations.

Last Answer : a. facilitate formal go/no-go decision making during the project.

Description : One of the reasons a project life cycle is split into phases is to:  a. facilitate formal go/no-go decision making during the project.  b. balance the costs of work in each phase ... the major deployments of resources throughout the project.  d. chunk work into time periods of similar durations.

Last Answer : a. facilitate formal go/no-go decision making during the project.

Description : A Unit Price (UP) contract provides: 1. a reimbursement of allowable costs plus a fixed fee which is paid proportionately as the  contract progresses  2. a reimbursement of allowable cost of services ... unit rates and the  final price is dependent on the quantities needed to carry out the work.

Last Answer : 4. a fixed price where the supplier agrees to furnish goods and services at unit rates and the  final price is dependent on the quantities needed to carry out the work

Description : Which of the following are parameters involved in  computing the total cost of a development project? a) Hardware and costs b) Effort costs c) Travel and training costs d) All of the mentioned

Last Answer : d) All of the mentioned

Description : Cost controls can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Last Answer : 4. The process of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Description : Cost budgeting can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on an on- going basis

Last Answer : 3. The process of establishing budgets, standards, and a monitoring system by which the  investment cost of the project can be measured and managed

Description : Which of the following project baselines provides the basis for measurement of  the expected cash flow against requirements over time and is often displayed as an  S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline

Last Answer : b. Cost performance baseline

Description : A cost performance index (CPI) of 0.89 means:  A. At this time, we expect the total project to cost 89 percent more than planned  B. When the project is completed we will have spent 89 ... at 89 percent of the rate planned  D. The project is only getting 89 cents out of every dollar invested

Last Answer : D. The project is only getting 89 cents out of every dollar invested

Description : )Life Cycle Costing is a term that is:  1. used when making decisions between alternatives  2. employed principally by the government 3. typically used in the construction industry  4. not used within the government  5. A and B

Last Answer : 5. A and B

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  a. The life cycle phases.  b. The logical order of tasks.  c. The scope of the project.  d. Project costs

Last Answer : c. The scope of the project.

Description :  A project with total budget cost of 30 crores is scheduled to be completed in 80 weeks. A periodic review was carried out at end of 60 weeks and results are as given:  Budgeted cost of work performed (EV) = 17 ... crores What is the cost performance index?  A.0.895  B.0.81  C.0.90  D.1.12

Last Answer : A.0.895

Description : Which of the following is/are main parameters that you should use when computing the costs of a software development project? a) travel and training costs b) hardware and software costs c) effort costs (the costs of paying software engineers and managers) d) all of the mentioned

Last Answer : d) all of the mentioned

Description : Which of the following is not project management goal? a) Keeping overall costs within budget b) Delivering the software to the customer at the agreed time c) Maintaining a happy and well-functioning development team

Last Answer : d) Avoiding customer complaints

Description : Which of the following is/are main parameters that you should use when computing the costs of a  software development project? a) travel and training costs b) hardware and software costs c) effort costs (the costs of paying software engineers and managers) d) all of the mentioned

Last Answer : d) all of the mentioned

Description : This set of Software Engineering Multiple Choice Questions & Answers (MCQs) focuses on Project  Management . 1. Which of the following is not project management goal? a) Keeping overall ... agreed time c) Maintaining a happy and well-functioning development team d) Avoiding customer complaints

Last Answer : d) Avoiding customer complaints

Description : computing the costs of a development project? (A)travel and training costs (B) hardware and costs (C) effort costs (the costs of paying engineers and managers) (D)All of the mention

Last Answer : (D)All of the mention

Description : Which of the following is not project management goal? a) Keeping overall costs within budget. b) Delivering to the customer at the agreed time. c) Maintaining a happy and well-functioning development team. d) Avoiding costumer complaints.

Last Answer : d) Avoiding costumer complaints.

Description : According to leading experts in software development, the margin of error when  estimating project costs is 100% and the margin of error in project scheduling time is  25%.

Last Answer : Ans: True

Description : The phases of a project life cycle are: a. starting, planning, control and closing. b. concept, definition, development, handover and closure. c. initiation, definition, planning, monitoring and operations. d. concept, definition, implementation and operations.

Last Answer : b. concept, definition, development, handover and closure.

Description : Life cycle of a project manager ____ with the development life cycle.

Last Answer : Ans. Overlaps

Description : Which of the following items should not be included in the  project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development  organisation, project responsibilities, managerial  objectives and priorities e) None of the above.

Last Answer : c) The life cycle model to be used

Description : Project management is the second major component of the planning phase of the  systems development life cycle (SDLC), and it includes three steps: creating the work  plan, staffing the project, and controlling and directing the project.

Last Answer : Ans: True

Description : The phases of a project life cycle are:  a. starting, planning, control and closing.  b. concept, definition, development, handover and closure.  c. initiation, definition, planning, monitoring and operations.  d. concept, definition, implementation and operations.

Last Answer : b. concept, definition, development, handover and closure.

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Normally a performance bond, depending upon the state, only stipulates that the contractor will guarantee the work for a certain period of time.  Answer: D  (8)Which contract type places the most risk on ... fee  3. Cost plus fixed fee  4. Fixed price plus incentive fee  5. Firm fixed price

Last Answer : 5. Firm fixed price

Description : State which of the following are the characteristics of service costing. 1. High levels of indirect costs as a proportion of total costs 2. Use of composite cost units 3. Use of equivalent units (a) (1) only (b) (1) and (2) only (c) (2) only (d) (2) and (3) only

Last Answer : (b) (1) and (2) only

Description : Which of the following statements is/are correct? 1. A materials requisition note is used to record the issue of direct material to a specific job. 2. A typical job cost will contain actual costs for material, labour and production ... 1) and (2) only (c) (1) and (3) only (d) (2) and (3) only

Last Answer : (c) (1) and (3) only

Description : Internal costs include a) Developers salaries b) Managers and support personnel salaries c) The cost of overheads such as utilities, rent and senior  managers d) Materials (such as manuals) and services such as travel e) All of the above.

Last Answer : a) Developers salaries

Description : ___ should be made of all cost factors so as to reflect on all relevant investment and  operational costs of the project including contingencies.

Last Answer : Ans. Realistic estimates

Description : In Project crashing, rent and overheads are treated as  A.Significant Cost  B.Insignificant costs  C.Direct Costs  D.Indirect Costs

Last Answer : D.Indirect Costs

Description : A profitability index (PI) of .92 for a project means that . A. The project's costs (cash outlay) are (is) less than the present value of the project's benefits B. The project's NPV is ... is greater than 1 D. The project returns 92 cents in present value for each current rupee invested (cost)

Last Answer : C. The project's NPV is greater than 1

Description : Costs that are not directly related to the products or services of the project, but are indirectly related to performing the project. A. Intangible Costs B. Sunk Cost C. Tangible Costs D. Indirect Costs

Last Answer : D. Indirect Costs

Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.

Description : Which one of the following statements best defines an estimate?  a. An approximation of project time and cost targets, refined throughout the project life  cycle.  b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life  cycle.

Description : The cost impact of a risk event occurring as a project proceeds through its life cycle tends to A. Slowly rise B. Slowly drop C. Drop sharply and then level out D. Rise sharply and then level out

Last Answer : A. Slowly rise

Description : Project performance consists of (A) Time (B) Cost (C) Quality (D) All of the above

Last Answer : (C) Quality

Description : A(n) _ is a review of the quality plan, procedures, data collection, and analysis by  an outside group. Select one: a. scope document b. project appraisal c. cost performance index d. analogous estimate e. quality audit

Last Answer : e. quality audit

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : Project performance consists of (A)Time (B)Cost (C)Quality (D)All of the above

Last Answer : (D)All of the above

Description : Project Manager must ensure that it develops appropriate trade off/s as  A. Time, cost and performance  B. Time, value and performance  C.Men, Materials and Machines  D.Money, Cost and Return on Investment

Last Answer : A. Time, cost and performance

Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.  B. ... approach that combines the scope and cost baseline into a project performance and  progress measurement tool.

Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description :  A time-phased budget that project managers use to measure and monitor cost performance. A. Cost Baseline B. Cost Budgeting C. Cost Estimating D. Cost Variance

Last Answer : A. Cost Baseline

Description : )A new project was initiated that involves new technology and subsequently has never been  done before. What type of contract would to owner want to issue to reduce or eliminate as much  risk as possible. 1. Firm ... 2. Cost plus fix fee  3. Cost plus incentive fee  4. Lump sum  5. A and D

Last Answer : 5. A and D

Description : Which of the following type of contracts is most preferable to the contractor doing the project  work? 1. Cost plus fixed fee  2. Fixed price  3. Fixed price plus incentive free 4. B and C

Last Answer : 1. Cost plus fixed fee

Description : )Quality costs include : 1. the total of all costs incurred to assure the production and delivery of acceptable products and services.  2. Only costs classified as prevention, detection and ... rework due to defects, customer returns and warranty costs.  4. The expense of upper management

Last Answer : 1. the total of all costs incurred to assure the production and delivery of acceptable products and services.

Description : In estimation of cost functions, variations in a single activity level represents the A. related total costs B. related fixed cost C. related variable cost D. related per unit cost

Last Answer : A. related total costs