A profitability index (PI) of .92 for a project means that .

A. The project's costs (cash outlay) are (is) less than the present value of the project's

benefits

B. The project's NPV is greater than zero

C. The project's NPV is greater than 1

D. The project returns 92 cents in present value for each current rupee invested (cost)

1 Answer

Answer :

C. The project's NPV is greater than 1

Related questions

Description : A project has a Profitability Index of 1.30. What does it mean?  A.The NPV is less than zero B.The payback period is more than one year  C.That the project returns Rs 1.30 for every Re 1 invested in the project  D.That IRR is 1.30 times that of the Hurdle Rate

Last Answer : C.That the project returns Rs 1.30 for every Re 1 invested in the project

Description : When operating under a single-period capital-rationing constraint, you may first want to try selecting projects by descending order of their in order to give yourself the best chance to select the mix of ... net present value (NPV) C. internal rate of return (IRR) D. payback period (PBP)

Last Answer : B. net present value (NPV)

Description : When operating under a single-period capital-rationing constraint, you may first want to try selecting projects by descending order of their in order to give yourself the best chance to select the mix of ... net present value (NPV) C. internal rate of return (IRR) D. payback period (PBP)

Last Answer : B. net present value (NPV)

Description : Which of the following statements is incorrect regarding a normal project? A. If the NPV of a project is greater than 0, then its PI will exceed 1. B. If the IRR of a project is 8%, its NPV, using ... the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Last Answer : D. If the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Description : A cost performance index (CPI) of 0.89 means:  A. At this time, we expect the total project to cost 89 percent more than planned  B. When the project is completed we will have spent 89 ... at 89 percent of the rate planned  D. The project is only getting 89 cents out of every dollar invested

Last Answer : D. The project is only getting 89 cents out of every dollar invested

Description : The criteria for acceptance of a project on the basis of Profitability Index (PI) is   A.PI=0 B. PI > 0   C. PI < 0   D. PI > 1

Last Answer : D. PI > 1

Description : A Firm is considering undertaking a project that would yield annual profits (after  depreciation) of Rs 68,000 for 5 years. The initial outlay of the project would be Rs  800,000 and the project's assets would have ... accounting rate of return for this project?  A 16%  B 8.5%  C 8.0%  D 9.1%

Last Answer : A 16%

Description : To the nearest rupee, what is the net present value of a replacement project whose cash flows are -Rs.104,000; Rs.34,444; Rs.39,877; Rs.25,000; and Rs.52,800 for years 0 through 4, respectively? The firm has decided to ... -free rate is 6%. A. Rs.15,115 B. Rs.26,798 C. Rs.33,346 D. Rs.48,121

Last Answer : C. Rs.33,346

Description : Which of the following is true regarding IRR? A. IRR assumes reinvestment at the cost of capital. B. IRR is the discount rate when NPV is greater than zero. C. IRR is a constrained optimization method. D. IRR is the discount rate when NPV is equal to zero.

Last Answer : D. IRR is the discount rate when NPV is equal to zero.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated.

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : In case of the indivisible projects, which of the following may not give the optimum result? A. Internal Rate of Return B. Profitability Index C. Feasibility Set Approach D. All of the above

Last Answer : C. Feasibility Set Approach

Description : Which of the following is true?  A. Discounted cash flow analysis is the least precise of the cash flow techniques, because  it does not consider the time value of money. B. NPV is ... least precise of the cash flow analysis techniques, because it assumes  reinvestment at the cost of capital.

Last Answer : C. Payback period is the least precise of the cash flow analysis techniques, because it  does not consider the time value of money.

Description : A Project control system: 1. Monitors and controls the project's schedule, costs, scope, budgets etc  2. Is a mechanism which reacts to the current project status in order to endure ... 4. Is a system for controlling and executing project documentation in an uniform and timely  manner

Last Answer : 1. Monitors and controls the project's schedule, costs, scope, budgets etc

Description : Which of the following is not a potential for a ranking problem between two mutua lly exclusive projects? A. The projects have unequal lives that differ by several years. B. The ... dramatically. D. One of the mutually exclusive projects involves replacement while the other involves expansion.

Last Answer : A. The projects have unequal lives that differ by several years.

Description : Which of the following is not a potential for a ranking problem between two mutua lly exclusive projects? A. The projects have unequal lives that differ by several years. B. The ... dramatically. D. One of the mutually exclusive projects involves replacement while the other involves expansion

Last Answer : A. The projects have unequal lives that differ by several years

Description : Which of the following is not a potential for a ranking problem between two mutua lly exclusive projects? A. The projects have unequal lives that differ by several years B. The ... dramatically D. One of the mutually exclusive projects involves replacement while the other involves expansion

Last Answer : A. The projects have unequal lives that differ by several years

Description : An investment should be accepted if its Net Present Value (NPV) is (A) 0 (B) 1 (C) positive (D) negative

Last Answer : C) positive

Description : An Expected Monetary Value (EMV) of $100000 on a potential project event in the  project means which of the following? Select one: a. A number that can be ignored b. An opportunity that ... Actual investment returns on the event e. A threat that must be considered to minimize the project risk

Last Answer : b. An opportunity that must be explored

Description : Which of the following is least likely to be part of the calculation of the terminal- year incremental net cash flow for an energy-related expansion project? A. An initial working capital ... Disposal/reclamation costs C. Capitalized expenditures D. Salvage value of any sold or disposed assets

Last Answer : D. Salvage value of any sold or disposed assets

Description : BCR>1 indicates which of the following? Select one: a. Benefits are greater than the costs. b. Costs are greater than the benefits. c. Costs and benefits are well balanced. d. Benefits are less than the costs e. Costs are less than the benefits.

Last Answer : a. Benefits are greater than the costs.

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A) Algorithmic model (B) Expert judgment (C) Top down (D) Analogy

Last Answer : (D) Analogy

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A)Algorithmic model (B)Expert judgment (C)Top down (D)Analogy

Last Answer : (D)Analogy

Description : Which of the following is true regarding NPV?  A. NPV assumes reinvestment at the cost of capital. B. NPV decisions should be made based on the highest value for all the selections.  C. NPV assumes reinvestment at the prevailing rate.  D. NPV assumes reinvestment at the NPV rate.

Last Answer : A. NPV assumes reinvestment at the cost of capital.

Description : A company is considering investing surplus funds in a project. Calculate the NPV at  10 % discount rate for the following data  Project-A Year 0- (100) Year 1-100 Year 2-100  A. 73.5  B. 173.5  C. 273.5  D.100

Last Answer : A. 73.5

Description : A firm is about to undertake a project and has computed the NPV of the project using a variety of discount rates:  Discount Rate used NPV 10% 130  15% 50  20% -50  What is the approximate IRR of this project?  A 20%  B 17.5%  C 15%  D 22.5%

Last Answer : B 17.5%

Description : A project has the following cash inflows Rs.34,444; Rs.39,877; Rs.25,000; and Rs.52,800 for years 1 through 4, respectively. The initial cash outflow is Rs.104,000. Which of the following four statements ... than or equal to 14%, but less than 18%. D. The IRR is greater than or equal to 18%.

Last Answer : C. The IRR is greater than or equal to 14%, but less than 18%.

Description : )Quality costs include : 1. the total of all costs incurred to assure the production and delivery of acceptable products and services.  2. Only costs classified as prevention, detection and ... rework due to defects, customer returns and warranty costs.  4. The expense of upper management

Last Answer : 1. the total of all costs incurred to assure the production and delivery of acceptable products and services.

Description : _________ method for profitability evaluation of a project does not account for investment cost due to land. (A) Net present worth (B) Pay out period (C) Discounted cash flow (D) Rate of return on investment

Last Answer : (B) Pay out period

Description : Identify the incorrect statement in connection with working capital management. A. Long-term funds are more expensive than short-term funds but also riskier B. The objectives of ... fluctuating current assets E. Aggressive financing policies increase profitability at the cost of higher risk

Last Answer : A. Long-term funds are more expensive than short-term funds but also riskier

Description : Net Present Value of a machine is  A. PV of cash inflows less cost of investment  B. PV of cash inflows ÷ cost of investment  C. PV of net profit after tax less cost of investment  D.PV of cash inflows less average cost of investment

Last Answer : A. PV of cash inflows less cost of investment

Description : Determining the policies that are needed for the smooth execution of a project  relates to which of the following agenda items of alignment sessions? Select one: a. Developing a common ... role clarification on projects e. Agreeing on the means and methods for accomplishing the purpose

Last Answer : d. Developing role clarification on projects

Description : The estimated benefits from a capital budgeting project are expected as cash flows rather than income flows because . A. it is more difficult to calculate income flows than cash flows B. it ... is central to the firm's capital budgeting decision C. this is required by the accounting profession

Last Answer : B. it is cash, not accounting income, that is central to the firm's capital budgeting decision

Description : An Organizational Breakdown Structure (OBS) is used to identify: a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of communication ... . d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : The traditional Work Breakdown Structure makes it easy to compare the current  project with past projects.

Last Answer : Ans: False

Description : One of the greatest weaknesses of systems consulting firms is that they try to apply  estimates and methodologies that they have developed over time and applied to other  projects, most of which are very different from the current project.

Last Answer : Ans: False

Description : . It is not wise to identify tasks for a current project using existing methodology,  because methodologies that have been used by an organization for other projects probably will not work for this project without extensive changes.

Last Answer : Ans: False

Description : Unlike traditional Work Breakdown Structures (WBS), evolutionary WBSs are  a. organized in a standard manner across all projects  b. created in an iterative and incremental manner  c. designed so one can compare the current project to past projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : Traditional Work Breakdown Structures tend to  a. focus on the design of the system as oppose to the needs of the current phase and  iteration  b. force too many levels of detail early on for large ... project and difficult to compare across projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : An Organisational Breakdown Structure (OBS) is used to identify:  a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of ... project. d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.