Which technique is applicable when other projects in the same

analogy application domain have been completed?

a) Algorithmic cost modelling

b) Expert judgement

c) Estimation by analogy

d) Parkinson’s Law

1 Answer

Answer :

c) Estimation by analogy

Related questions

Description : A is developed using historical cost information that relates  some metric to the project cost. a) Algorithmic cost modelling b) Expert judgement c) Estimation by analogy d) Parkinson’s Law

Last Answer : a) Algorithmic cost modelling

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A) Algorithmic model (B) Expert judgment (C) Top down (D) Analogy

Last Answer : (D) Analogy

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A)Algorithmic model (B)Expert judgment (C)Top down (D)Analogy

Last Answer : (D)Analogy

Description : Which of the following states that work expands to fill the time  available. a) CASE tools b) Pricing to win c) Parkinson’s Law d) Expert judgement

Last Answer : c) Parkinson’s Law

Description : Algorithmic cost estimation in different organisations may be different for the same application development, because a) Different organisations consider complexity factors differently b) Different organisations may use ... measurement of productivity may vary e) All of the above may be true.

Last Answer : e) All of the above may be true.

Description : . Which of the following is empirical estimation technique? (i) expert judgement (ii) Delphi estimation (iii) COCOMO (iv) Critical path Method A. only i, ii & iii B. only i & ii C. only i, iii & iv D. All of the above

Last Answer : B. only i & ii

Description : Each component of the software product is separately estimated and the results aggregated to produce an estimate for the overall job. (A) Algorithmic model (B) Expert judgment (C) Bottom-up (D) Top down

Last Answer : (C) Bottom-up

Description : Each component of the product is separately estimated and the results aggregated to produce an estimate for the overall job. (A)Algorithmic model (B)Expert judgment (C)Bottom-up (D)Top down

Last Answer : (C)Bottom-up

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : The most successful project manager usually: 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience with formal ... . Has considerable experience as a functional manager before moving into the project  management arena.

Last Answer : 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience

Description : Heuristics estimation technique depends on A. educated guess B. prior experience C. Common sense D. All of the above

Last Answer : D. All of the above

Description : Which of the following serves as project estimation technique? A. Empirical estimation B. Heuristic technique C. Analytical estimation D. All of the above

Last Answer : D. All of the above

Description : All of the following are true regarding the Qualitative Risk Analysis process except  which one?  A. Probability and impact and expert interview are used to help correct biases that occur  in the data ... of this process used to determine  which risks need near-term response plans.

Last Answer : C. Qualitative Risk Analysis is an easy method of determining risk probability and  impact that usually takes a good deal of time to perform.

Description : Identify, from among the following, the correct statement. a) One of the main challenges Engineering facing today is the requirement of most systems to work with a multitude of  homogenous systems ... of component based assembly, we find  that onlyless than 20% of today's is still custom built

Last Answer : c) does not wear-out in the traditional sense of the term, but  does tend to deteriorate as it evolves

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : During project estimation, project manager estimates following A. project cost B. project duration C. project effort D. all of the above

Last Answer : D. all of the above

Description : This activity is undertaken once the development activities start? A. Project Planning B. Project Monitoring and Control C. Project size estimation D. Project cost estimation

Last Answer : B. Project Monitoring and Control

Description : Which is the Estimation size should be known? a. Time estimation b. Effort estimation c. Cost estimation d. size estimation

Last Answer : b. Effort estimation

Description : _____ is the process of planning and controlling the development of a system within a  specified time frame at a minimum cost with the right functionality.  a. Project management  b. Symantic timeline  c. Task identification  d. Time estimation  e. Work plan

Last Answer : a. Project management

Description : In estimation of cost functions, variations in a single activity level represents the A. related total costs B. related fixed cost C. related variable cost D. related per unit cost

Last Answer : A. related total costs

Description : Relationship based on unrelated level of activity and past data of cost is measured with help of A. cost estimation B. price estimation C. unit estimation D. production estimation

Last Answer : A. cost estimation

Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : Which one of the following best describes project management?  a. Using APM's Body of Knowledge 6th edition as a guide to all projects.  b. Employing a project manager who has undertaken ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : Amount of work completed to date compared with planned in the Earned Value  Management method is  A. Schedule Performance Index  B. Cost Performance Index  C. Percentage Complete  D .Percentage Spent

Last Answer : C. Percentage Complete

Description :  A project with total budget cost of 30 crores is scheduled to be completed in 80 weeks. A periodic review was carried out at end of 60 weeks and results are as given:  Budgeted cost of work performed (EV) = 17 ... crores What is the cost performance index?  A.0.895  B.0.81  C.0.90  D.1.12

Last Answer : A.0.895

Description : A cost performance index (CPI) of 0.89 means:  A. At this time, we expect the total project to cost 89 percent more than planned  B. When the project is completed we will have spent 89 ... at 89 percent of the rate planned  D. The project is only getting 89 cents out of every dollar invested

Last Answer : D. The project is only getting 89 cents out of every dollar invested

Description : . It is not wise to identify tasks for a current project using existing methodology,  because methodologies that have been used by an organization for other projects probably will not work for this project without extensive changes.

Last Answer : Ans: False

Description : Analogy between mass and heat transfer is not applicable in case of (A) Same velocity profile or equal eddy diffusivities (B) Thermal or pressure mass diffusion (C) Viscous heating or chemical reaction (D) Both (B) and (C)

Last Answer : (D) Both (B) and (C)

Description : Which of the following serves as metrics for project size estimation? A. Lines of codes B. function point C. Number of persons D. Only A & B

Last Answer : D. Only A & B

Description : Which of the following activity is not the part of project planning? A. project estimation B. project scheduling C. project monitoring D. risk management

Last Answer : C. project monitoring

Description : Science bases its estimation of the size of a product on a) Files (Fi), Flows (Fl) and Processes (Pr) b) Lines of Code (kLOC) c) Function Points (FP) d) operands and operators e) Feature Points (FeP).

Last Answer : d) operands and operators

Description : Which stage of project management life cycle requires the maximum time of  completion  A.Conceptualization  B.Planning  C.Execution  D.Estimation

Last Answer : C.Execution

Description : When using a function point estimation worksheet, there are 14 factors that impact the complexity of a project. These factors include _____.  a. data communications, time tradeoffs, and ... programming language  d. reports printed and PCA  e. x-rays, extensibility, and operational conversion

Last Answer : b. end-user efficiency, data communications, and reusability

Description : The process of assigning values for the time and effort needed to perform a system  project is called _____.  a. analysis  b. estimation  c. identifying  d. planning

Last Answer : b. estimation

Description : In the stock-price beta estimation for the Coca-Cola Company, the dependent variable is the: A. return on Coca-Cola. B. price of Coca-Cola stock. C. return on the S&P 500. D. value of the S&P 500 Index.

Last Answer : A. return on Coca-Cola.

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : When developing a project's scope statement, which of the following should not be  included? 1. Project justification.  2. Cost/benefit analysis  3. Project deliverables  4. Measurable objectives

Last Answer : 1. Project justification.

Description : A profitability index (PI) of .92 for a project means that . A. The project's costs (cash outlay) are (is) less than the present value of the project's benefits B. The project's NPV is ... is greater than 1 D. The project returns 92 cents in present value for each current rupee invested (cost)

Last Answer : C. The project's NPV is greater than 1

Description : Mathematical models using linear, dynamic, integer, or algorithm models are  considered  A. Project selection criteria B. A form of expert judgment C. Project selection methods D. A form of historical information

Last Answer : C. Project selection methods

Description : )Which form of power is the LEAST effective from the project manager's viewpoint in terms of influencing functional managers? 1. Formal power  2. Expert power  3. Penalty power  4. Referent power

Last Answer : 3. Penalty power

Description : An expert based test estimation is also known as A. Narrow band Delphi B. Wide band Delphi C. Bespoke Delphi D. Robust Delphi

Last Answer : A. Narrow band Delphi

Description : The sales prediction technique that is based on the relationship between sales and other factors such as population density, income and family size is: A)executive judgement B)time series analysis C)a market survey D)the correlation method

Last Answer : D)the correlation method

Description : When a project has completed the handover and closure phase: a. the project deliverables are ready for commissioning. b. the project deliverables are ready for handing over to the users. c. the project ... must be disposed of. d. the capability is now in place for the benefits to be realized.

Last Answer : d. the capability is now in place for the benefits to be realized.

Description : Which one of the following is least likely to be a success criteria? a. A target for the project to receive zero change requests. b. The date by which the project is to be completed. c. Delivery of products that meet required specifications. d. The awarding of bonuses to senior management.

Last Answer : d. The awarding of bonuses to senior management.

Description : Petri is working for Nokia in Finland. He has completed 10 months of his 12-month project, budgeted at $800,000. His earned value analysis shows that variance at  completion is $75,000. What is the estimate at completion value ... : a. 725,000 b. -725,000 c. -$875,000 d. $875,000 e. $800,000

Last Answer : d. $875,000

Description : A project includes a number of activities that must be completed in some ………… a. particular order b. sequence c. both d. all the above

Last Answer : d. all the above