What are the schedules of maintenance done on transformers?

1 Answer

Answer :

Ans. Following are the schedules of maintenance on transformers.
a. Daily maintenance.
b. Monthly maintenance.
c. Quarterly maintenance.
d. Half yearly maintenance.
e. Yearly maintenance.
f. 5 Yearly maintenance.

Related questions

Description : What are the maintenance schedules of a pumping station and type of starters?

Last Answer : Ans. Following are maintenance schedule of the pumping installation: Switch gear in every quarter and the motor & pump section every half yearly. Starters are DOL starter, star delta starter, Auto T/F starter.

Description : 74)Power transformers are generally designed to have maximum efficiency around A. No load B. Half load C. Near full load D. 10% overload

Last Answer : C. Near full load

Description : [23] Transformers are rated in KVA instead of KW because A. load power factor is often not known B. KVA is fixed whereas KW depends on load power factor C. Total transformer loss depends on volt ampere D. It has become customary

Last Answer : C. Total transformer loss depends on volt ampere

Description : TRANSFORMERS MCQ

Last Answer : 101. A shell-type transformer has (a) high eddy current losses (b) reduced magnetic leakage (c) negligibly hysteresis losses (d) none of the above Ans: b 102. A transformer can have regulation closer to zero (a ... (6) much smaller (c) much higher (d) somewhat smaller (e) none of the above Ans: c

Description : Why a transformer requires cooling. What are the methods of cooling transformers?

Last Answer : Ans. Transformers requires cooling as they get heated up due to various losses taking place in the transformer. (like iron of copper losses) Following are the methods of cooling of transformer. a. Natural ... . Forced oil air Natural Cooling (OFAN). d. Forced oil and forced Air cooling (OFAF).

Description : What are the loses in Transformers, Explain?

Last Answer : Ans. (1) Iron loses (2) Copper loses Iron Loss : Iron loss occurs in the transformers Iron core due to hysteresis and eddy currents taking place. They are almost fixed irrespective of ... losses in the primary and the secondary windings of the transformer which with the loading of transformer.

Description : Classify the transformers based on the construction, frequency and power.

Last Answer : Classification of Transformer Based On: i) Construction: Shell type, Core type, Berry type ii) Change in voltage level: Step-Up, Step-Down, iii) Number of phases: Single phase, Three phase iv) ... Control vi) Cooling: Self-cooled, Air-cooled, Forced-air cooled, Oil-cooled, Forced-oil cooled. 

Description : Which of the following connection of transformers will give highest value of secondary voltage ? (A) Delta primary delta secondary (B) Delta primary star secondary (C) Star primary star secondary (D) Star primary delta secondary

Last Answer : Which of the following connection of transformers will give highest value of secondary voltage ? (A) Delta primary delta secondary (B) Delta primary star secondary (C) Star primary star secondary (D) Star primary delta secondary

Description : Two transformers A and B having equal outputs and voltage ratios but unequal percentage impedances of 4 and 2 are operating in parallel. The transformer A will be overloaded by 

Last Answer : Two transformers A and B having equal outputs and voltage ratios but unequal percentage impedances of 4 and 2 are operating in parallel. The transformer A will be overloaded by 33%

Description : Core type transformers are popular in___________.  (A) High voltage applications (B) Low voltage applications (C) All of the above (D) None of the above

Last Answer : Core type transformers are popular in High voltage applications

Description : In a transmission line if booster transformers are to be used, preferred location will be  (A) At the receiving end (B) At the sending end (C) At the intermediate point (D) Anywhere in the line 

Last Answer : In a transmission line if booster transformers are to be used, preferred location will be At the intermediate point

Description : The friction losses in Real Transformers are :  (A) 0% (B) 5% (C) 25% (D) 50%

Last Answer : A

Description : Two 3-phase transformers cannot be operated in parallel, if their :  (A) kVAs are different (B) phase sequences are different (C) % impedances are different (D) voltage ratios are different

Last Answer : Two 3-phase transformers cannot be operated in parallel, if their : phase sequences are different

Description : An additional condition for parallel operation of three-phase transformers over single-phase transformers is that

Last Answer : An additional condition for parallel operation of three-phase transformers over single-phase transformers is that the transformers should belong to the same vector group

Description : Which of the following is the advantage of using CRGO steel in transformers? A) High magnetic flux density B) Low permeability C) Both A and B D) None of these

Last Answer : It definitely High Magnetic Flux Density since a crgo steel has always a more around 3% of silicon proportion among the remaining ferrite which make cold rolled grain oriented steel having high flux magnetic ... for more about the crgo core you can learn here https://nicoreindia.com/crgo-core/

Last Answer : Instrument transformers are potential transformers, current transformers.

Last Answer : Natural oil cooling is used for transformers up to a rating of 3000 kVA.

Description : If the percentage impedances of the two transformers working in parallel are different, then?

Last Answer : If the percentage impedances of the two transformers working in parallel are different, then parallel operation will still be possible, but the power factors at which the two transformers operate will be different from the power factor of the common load.

Last Answer : Distribution transformers are generally designed for maximum efficiency around 50% load.

Last Answer : Power transformers are generally designed to have maximum efficiency around near full-load.

Description : Two transformers are connected in parallel. These transformers do not have equal percentage impedance. This is likely to result in?

Last Answer : Two transformers are connected in parallel. These transformers do not have equal percentage impedance. This is likely to result in loading of the transformers not in proportion to their kVA ratings.

Last Answer : Short circuit test on transformers is conducted to determine copper losses.

Last Answer : Necessary conditions required to be satisfied in order to ensure successful parallel operation of single phase transformers:  1. Only transformers having the same phase displacement between primary and secondary ... . 7. The phase sequence must be followed strictly on HV and LV side connection.

Last Answer : Natural air cooling is generally restricted for transformers up to 1.5 MVA .

Description : Losses which occur in rotating electric machines and do not occur in transformers are?

Last Answer : Friction losses windage losses 

Description : The efficiency of two identical transformers under load conditions can be determined by?

Last Answer : The efficiency of two identical transformers under load conditions can be determined by back-to-back test.

Description : The efficiencies of transformers compared with that of electric motors of the same power are?

Last Answer : Transformers have high efficiency than the same ratted motors

Last Answer : Current transformers (CT) : Current transformer (CT) actually step down the high current to low current for the operation of relays. Current transformer is use for measurement of ... use for relay. This is about potential transformer.

Description : Why do transformers make noise?

Last Answer : Transformers make noise based on it out put if an transformer outputs is 400v maximum than a 398v be apply to that transformer it also make a noise because of that 

Description : Batteries Maintenance –

Last Answer : a) Specific gravity. b) Voltage/Cell. ON Load/OFF Load(2.2V when fully charged and 1.8 when fully discharged.

Description : Explain Briefing the half yearly schedule maintenance of OH mains?

Last Answer : Ans. "(a) Check all the jumper connections (b) Check any connections of the strands of the conductor (c ) Check and ensure proper earth connection (d) Check proper fixation of insulators, stay wires, guard wires, etc. (e) Check proper tensioning and connection of service wires."

Description : What are the schedule maintenance to be carried out OH mains & UG Cables?

Last Answer : Ans. Following are the schedule to be maintained of HO mains and UG cables. a. OH mains – Every Half yearly b. UG.Cables – Every Yearly. During those schedules, for OH, Guarding condition of insulators, sag in OH line are to be checked for UG cables, cables are to be beggared for their IR values.

Description : Power Maintenance INDICATE TRUE OR FALSE TO THE FOLLOWING

Last Answer : 1) MCB is used in circuits for Overload protection. True or False Ans True 2) We can improve the earth resistance by packing common salt charcoal & water. (True or False) Ans True 3) Silica gel used ... False 15) Shorting of power diode test to be conducted at full load. (True or false) Ans True

Description : Power Maintenance FILL IN THE BLANKS

Last Answer : 1) The process of removing heat from low temperature level and rejecting at high temperature is called. REFRIGERATION. 2) Any substances for change of its state at constant temperature absorbs/give up heat is ... ) The capacity of alternator, batteries & fans in TL coach are 4.5KW, 120Ah & 35W.

Description : Power Maintenance ABBREVIATIONS

Last Answer : 1 W - Watts 2 KW - Kilowatts 3 KWH - Kilowatt Hour 4 KVA - Kilo Volt Amps 5 KVAR - Kilo Volt Ampers Reactive 6 H.P. - Horse Power 7 A.H. - Ampere Hours 8 P.F. - Power Factor 9 R.P.M. - ... L.T.U.G - Low Tension Under Ground 36 P.V.C. - Poly Vinly Chloride 37 H.R.C. - High Rapturing Capacity

Description : Power Maintenance MCQ

Last Answer : 1) Turbine pumps are used up to a suction head of ( b ) a. 1000 ft. c. 20 ft b. 100 ft d. 50 ft 2) The yard stick for provision of Electrical points in staff quarters can be changed by the Zonal railways ... is used for electrical fire ( b ) a. Water c. Foam b. Co2 & dry powder d. None of the above

Description : Septic System Maintenance

Last Answer : Nobody is interested in thinking about what happens when someone forgets to clean his or her septic system in the backyard. We don't need to tell you either. Not draining and cleaning your septic ... its regular cleaning schedule you don't have to worry about the system breaking down anytime soon.

Description : Maintenance and Care: How to clean your Vacuum Cleaner

Last Answer : Maintenance and Care: How to clean your Vacuum Cleaner There are numerous ways to clean your vacuum cleaner, depending on the brand (manufacturer) and design. However, it is best to ... will bother your work area. Remember, safety considerations are important to prevent any unwanted accidents.

Description : Explain on-line maintenance of Rotameter. 

Last Answer : On line maintenance of Rotameter: In a chemical plant, it is a normal practice to do on line maintenance work. This avoids total shutdown of the equipment or plant. This is possible, if proper ... . Thus it is possible to attend maintenance jobs in the line without stopping the production.

Description : Explain functions and responsibilities of maintenance department.  

Last Answer : Functions and duties of plant maintenance department 1)Inspection 2)Engineering 3) Maintenance 4) Repair 5) Overhaul 6)Construction 7) Salvage 8) Clerical work 1)Inspection: i) Inspection of ... , ii) of time progress on jobs pertaining to important features of building and production equipment.

Description : Explain breakdown maintenance. Give any two disadvantages of it.  

Last Answer : Breakdown maintenance: This method of maintenance implies that repairs are made after the equipment is out of order and it cannot perform its normal function any longer. In such situation, ... those plant items which are regulated by statutory provision eg. Cranes, lifts, and pressure vessels.

Description : Explain preventive maintenance. 

Last Answer : Preventive maintenance: It is a system of scheduled, planned maintenance tries to minimize the problem of breakdown maintenance. It is a stich- in- time procedure. It locates weak spots in all equipment ... 8. Lower unit cost of manufacture. 9. Increased equipment life. 10. Better product quality.

Description : Name types of maintenance. 

Last Answer : Types of maintenance: 1. Corrective or breakdown maintenance 2. Scheduled maintenance 3. Preventive maintenance 4. Predictive maintenance

Description : Describe scheduled maintenance. What are its advantages ? 

Last Answer : Scheduled maintenance: Scheduled maintenance is a stich-in-time procedure which is aimed at avoiding breakdowns. Breakdowns can be dangerous to life and hence should be minimized. Scheduled ... , such as lubricating and retightening screws Lower long term costs compared with breakdown maintenance 

Description : Explain predictive maintenance in detail.

Last Answer : Predictive maintenance: Predictive maintenance makes use of human sense or other sensitive instruments such as audio gauges, vibration analyser, amplitude meter , pressure , temperature and resistance ... 4. Pressure, temperature and resistance strain gauges: eg. Excessive temperature of equipment.

Description : Describe online maintenance with respect to rotameter. 

Last Answer : On line maintenance of Rotameter: In a chemical plant, it is a normal practice to do on line maintenance work. This avoids total shutdown of the equipment or plant. This is possible, if proper ... . Thus it is possible to attend maintenance jobs in the line without stopping the production.

Description : Give the importance of plant maintenance. 

Last Answer : Importance of Plant Maintenance : In modern industry, equipment and machinery are a very important part of the total productive effort. With the development of special purpose and sophisticated machines ... and services required by other section of the factory for the performance of their function.

Description : Explain the activities carried out during weekly maintenance of 3 ph. Induction motor. 

Last Answer : Activities Carried out During Weekly Maintenance of 3 ph. Induction Motor:  1) Check belt tension. In cases where this is excessive it should immediately be reduces and in the case of sleeve ... and cooled by oil mist systems its important to check the oil mist flow paths/pressure components.

Description : Explain the maintenance of lead acid battery.

Last Answer : Maintenance of lead acid battery: 1) Keep the container surface dry by using dry cloths. 2) Tighten the terminal connections. 3) Battery should not be discharged below a minimum voltage. 4) Never keep battery ... -container embed { position: absolute; top: 0; left: 0; width: 100%; height: 100%; }