Request Answer
What is the reasonable range of float you assume while checking the look ahead work activities?
0 like 0 dislike

Please log in or register to answer this question.

1 Answer

The float range is varied from a project to another. However, in my opinion 10% of project duration is the maximum reasonable float for any project. 
0 like 0 dislike
Next Question ⇨

Related questions

What is a constraint in primavera? 
Last Answer : Constrains in primavera is to fix the early or late start or finish dates of an activity as per following options: A-Project Must Finish by B-Mandatory Start / Mandatory Finish C-Start / Finish On or After D-Start / Finish On or Before E-Start / Finish On F-Expected Finish...

Show More
0 like 0 dislike
1 answer




0 like 0 dislike
0 answers




...