)In a program or project plan, there are always revisions to account for new or missing data.
Which one of the following provides the best reason for performing a revision of the plan?
1. A supplier has changed the way their product is delivered to your supplier
2. Project tasks are crashed to meet their end dates
3. Human resources will remain constant through out the project
4. Historical data on a similar project suggests that risk events are not included in the current
plan.