You are the project manager for a cable service provider. Your project team is 

researching a new service offering. They have been working together for quite some time 

and are in the performing stage of team development. A new member has been introduced

to the team. Which of the following statements is true?

A. The team will start all over again with the storming stage. 

B. The team will continue in the performing stage. 

C. The team will start all over again with the forming stage.

D. The team will start all over again at the storming stage but quickly progress to the 

performing stage.

1 Answer

Answer :

C. The team will start all over again with the forming stage.

Related questions

Description : You are the project manager for a cable service provider. Your team members are  amiable with each other and are careful to make project decisions jointly. Which of the  following statements is true?  ... stage of Develop Project Team. D. They are in the forcing stage of Develop Project Team.

Last Answer : B. They are in the norming stage of Develop Project Team.

Description : In which stage of team development, team members are worried about how they fit in  with the others and how their capabilities and skills compare.  A.Norming  B.Storming  C.Forming  D.Performing

Last Answer : C.Forming

Description : 1st stage of group development is ____________. (a) Storming ; (b) Norming ; (c) Forming ; (d) Performing

Last Answer :  (c) Forming ;

Description : You are working in CareerRide as a project manager. What will you do to minimize the risk of failure? a. Request a large budget b. You will increase the team size c. Track progress d. None of the above

Last Answer : c. Track progress

Description : After the celebration of the successful milestone completion, a project manager  will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.

Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.

Description : Complete the following statement. As a project manager, Darrell is  excited that he is assigned to be in charge of the most important project  this year. After being chartered for the project, he ... c. prepare for the template to monitor project progress. d. estimate the entire project budget.

Last Answer : b. start to define and develop the stakeholder needs and requirements

Description : Marco is an investor, and Jon is a project team member. Both have  intensive technical background for the project that you are managing.  However, recently they have disagreed on the next step to take ... b. Stakeholders c. The project team d. Investors e. The board of trustees of this company

Last Answer : c. The project team

Description : Which of the following statements is most correct? A. For small companies, long-term debt is the principal source of external financing. B. Current assets of the typical manufacturing firm account ... the financial manager to make a decision and not address the issue again for several months.

Last Answer : B. Current assets of the typical manufacturing firm account for over half of its total assets.

Description : Alice is a Project Manager. She is coordinating a bidder conference to allow vendors to get clarification on the work that needs to be performed. Which phase of Project Management is in progress. A. Conduct Procurements B. Plan Procurements C. Control Procurements D. Close Procurements

Last Answer : A. Conduct Procurements

Description : Alice is a Project Manager. She is coordinating a bidder conference to allow vendors to get  clarification on the work that needs to be performed. Which phase of Project Management is in  progress. A. Conduct Procurements B. Plan Procurements C. Control Procurements D. Close Procurements

Last Answer : A. Conduct Procurements

Description : )The critical element in a project's communication system is the: 1. Progress report * 2. Project directive  3. Project manager  4. Customer

Last Answer : 3. Project manager

Description : Which one of the following is true for the Project Management Plan (PMP)? a. The Project Management Plan is developed by the project manager and team and owned by the  sponsor. b. A ... The Project Management Plan is developed by the project manager and team and owned by the project manager.

Last Answer : d. The Project Management Plan is developed by the project manager and team and owned by the project manager.

Description : Which one of the following is true for the Project Management Plan (PMP)?  a. The Project Management Plan is developed by the project manager and team and owned by the  sponsor. b. ... Management Plan is developed by the project manager and team and owned  by the project manager.

Last Answer : d. The Project Management Plan is developed by the project manager and team and owned  by the project manager.

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : . A project leader or manager is expected to be completely accountable for his team  members and meeting the team’s targets. (True/False)

Last Answer : Ans. True

Description : The project manager works with the project sponsor to identify the necessary resources  and team members needed to further develop the key project parameters – Cost, Scope,  Schedule, and Quality (CSSQ). (True/False)

Last Answer : Ans. True

Description : Daniel has just been assigned as the project manager. To motivate his team properly,  Daniel’s first step is to award bonuses to team members

Last Answer : Ans: False

Description : Resorce requirement in project becomes constant while the project is in its _____ progress stage. (A) 40 to 55% (B) 55 to 70% (C) 70 to 80% (D) 80 to 95%

Last Answer : (D) 80 to 95%

Description : Controlling the changes in the project may affect (A)The progress of the project (B)Stage cost (C)Project scope (D)All of the abov

Last Answer : (D)All of the abov

Description : Resorce requirement in project becomes constant while the  project is in its progress stage. (A) 40 to 55% (B) 55 to 70% (C) 70 to 80% (D) 80 to 95%

Last Answer : (D) 80 to 95%

Description : The planning and scoping should be such that the project manager can assess every  stage of the project and the quality of the deliverable of the project at every stage. (True/False)

Last Answer : Ans. True

Description : You are a project manager for Cinema Snicker Productions. Your company  specializes in producing comedy films for the big screen. Your latest project has just been  cancelled because of budget cuts ... elsewhere. D. This project ended due to integration because the funding was cut off.

Last Answer : A. This project ended due to starvation because the funding was cut off.

Description : In ____ style, project manager shares his or her vision with the team but permits them to  use their respective ideas to come up with a solution.

Last Answer : Ans. Authoritative

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : Sergei, the project manager, is worried about completing the project on time. To  increase the productivity of his 15-person team he should create subteams with no more  than 10 people on a sub team.

Last Answer : Ans: True

Description : Which one of the following best describes project management?  a. Using APM's Body of Knowledge 6th edition as a guide to all projects.  b. Employing a project manager who has undertaken ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time.  b. to deliver the project objectives to ... benefits.  d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.

Description : Which one of the following statements best defines an estimate?  a. An approximation of project time and cost targets, refined throughout the project life  cycle.  b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life  cycle.

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description : Which one of the following statements is true?  a. Independent reviews and quality audits form part of quality assurance to ensure the project  manager delivers on time and to budget. ... planning enables the project manager to manage the trade-off between customer  expectations and budget.

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for  purpose and meet stakeholder expectations.

Description : Who are project team members primarily accountable to? a. External stakeholders. b. The end users. c. The finance director. d. The project manager.

Last Answer : d. The project manager.

Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.

Last Answer : a. It utilizes resources as and when required under direction of a project manager.

Description : Who owns the Project Management Plan (PMP)? a. The project team. b. The chief executive. c. The project manager. d. The project support office.

Last Answer : c. The project manager.

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager

Last Answer : b) project

Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager

Last Answer : b) project

Description : Complete the following statement. In a weak matrix environment, the  project manager, Eric, has to constantly make an effort to influence his  project team and stakeholders to ensure project success. ... managers. d. there are no functional managers. e. Eric has flexibility on authority.

Last Answer : b. Eric has no or little authority.

Description : Quality planning is the process of developing a quality plan for (A) team (B) project (C) customers (D)project manager

Last Answer : (D)project manager

Description : Who creates the project team?  A. Factory manager  B. Operation manager  C. Project manager  D.Purchase Manager

Last Answer : C. Project manager

Description : .Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : Who are project team members primarily accountable to?  a. External stakeholders.  b. The end users.  c. The finance director.  d. The project manager.

Last Answer : d. The project manager.