According to PMBOK, project management process groups are iterative, which
was originally defined by Walter Shewhart and later modified by Edward Deming.
Generally, one outcome from a previous process can serve as input for the next
process. Which of the following best identifies with the description of this concept?
Select one:
a. Project life cycle
b. Plan-Do-Check-Act cycle
c. Project phases
d. PM processes
e. HR process cycle