Which of the following statements
concerning audit planning is incorrect
a. Planning is a continual and iterative
process.
b. Planning is a discrete phase of an
audit.
c. In a recurring audit, planning often
begins shortly after (or in connection
with) the completion of the previous
audit and continues until the completion
of the current audit engagement.
d. In planning an audit, the auditor
considers the timing of certain planning
activities and audit procedures that are
to be completed prior to the performance
of further audit procedures
concerning audit planning is incorrect
a. Planning is a continual and iterative
process.
b. Planning is a discrete phase of an
audit.
c. In a recurring audit, planning often
begins shortly after (or in connection
with) the completion of the previous
audit and continues until the completion
of the current audit engagement.
d. In planning an audit, the auditor
considers the timing of certain planning
activities and audit procedures that are
to be completed prior to the performance
of further audit procedures