PERT emphasises on ...........................
a. Activity
b. Time
c. Cost
d. None of these

1 Answer

Answer :

b. Time

Related questions

Description : ......................... is activity oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : a. CPM

Description : Operations Research emphasises on the overall approach to the system. This characteristic of Operations Research is often referred to as ................................. a. System orientation b. System approach c. Inter-disciplinary d. Team approach

Last Answer : d. Team approach

Description : ................... is an event oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : b. PERT

Description : PERT stand for: a. Performance Evaluation Review Technique b. Programme Evaluation Review Technique c. Programme Evaluation Research Technique

Last Answer : b. Programme Evaluation Review Technique

Description : ........................... is the latest time by which an activity can be finished without delaying the completion of the project. a. LST b. LFT c. EFT d. EST

Last Answer : b. LFT

Description : The EST + activity duration = .............................. a. Earliest Finish Time b. Latest Start Time c. Latest Finish Time d. None of these

Last Answer : a. Earliest Finish Time

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : An activity which does not consume either resource or time is called ............................. a. Predecessor activity b. Successor activity c. Dummy activity d. Terminal activity

Last Answer : c. Dummy activity

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : In a network diagram, activity is denoted by ............................ a. Node b. Arrow c. Triangle d. None of these

Last Answer : b. Arrow

Description : An event which represents the beginning of more than one activity is a : a. Merge event b. Net event c. Burst event d. None of these

Last Answer : c. Burst event

Description : An activity which must be completed before commencement of one or more other activities is called................................. a. Successor activity b. Predecessor activity c. Dummy activity d. None of these

Last Answer : b. Predecessor activity

Description : The assignment problem is: a. Requires that only one activity be assigned to each resource b. Is a special case of transportation problem c. Can be used to maximise resource d. All the above

Last Answer : d. All the above

Description : Shadow price is also called ...................... a. Dual price b. Unit price c. Total cost d. None of these

Last Answer : a. Dual price

Description : In Transportation Problem, LCM stands for ............................. a. Lowest Common Multiplier b. Least Cost Method c. Lowest Cell Method d. None of these

Last Answer : b. Least Cost Method

Description : In Transportation Problem, NWCM stands for ............................. a. North West Cost Method b. Net Worth Corner Method c. North West Corner Method d. None of these

Last Answer : c. North West Corner Method

Description : A matrix which shows the gains and losses resulting from moves and counter moves is called.................................. a. Cost matrix b. Pay off matrix c. Both a and b d. None of these

Last Answer : b. Pay off matrix

Description : For a minimisation Transportation Problem, the objective is to minimise: a. Profit b. Cost c. Solution d. None of these

Last Answer : b. Cost

Description : A Transportation Problem is said to be unbalanced when total supply is not equal to ............ a. Total cost b. Total demand c. Both a and b d. None of these

Last Answer : b. Total demand

Description : The O R technique which helps in minimising total waiting and service cost is: a. Game theory b. Queuing theory c. Both a and b d. Decision theory

Last Answer : b. Queuing theory

Description : In a maximisation assignment problem, the objective is to maximise ............................. a. Profit b. Cost c. Optimisation d. None of these

Last Answer : a. Profit

Description : The dummy source/destination in a transportation problem is added to ........................ a. Satisfy rim constraints b. Prevent solution from becoming degenerate c. Ensure total cost does not exceed a limit d. None of the above

Last Answer : a. Satisfy rim constraints

Description : a customer’s behaviour of leaving the queue when he does not like to wait in the queue due to lack of time or space is called ..................... a. Jockying b. Reneging c. Collusion d. Balking

Last Answer : d. Balking

Description : Number of customers in the queue per unit of time is called ...................... a. Queuing system b. Length of queue c. Average length of queue d. None of these

Last Answer : c. Average length of queue

Description : .......................models consider time as one of the important variable. a. Dynamic b. Static c. Botha and b d. None of these

Last Answer : a. Dynamic

Description : ........................ models assume that the values of the variables do not change with time during a particular period. a. Dynamic b. Static c. Both a and b d. None of these

Last Answer : b. Static

Description : If a simplex table shows the values 2, -3, 0 against “θ”, which should be taken as the replacement ratio. a. 2 b. -3 c. 0 d. None of these

Last Answer : c. 0

Description : Controllable variables are also called.................................. a. Slack variables b. Surplus variables c. Artificial variable d. Decision variables

Last Answer : d. Decision variables

Description : The variables which cannot be manipulated by the decision maker are called.................... a. Controllable variables b. Uncontrollable variables c. Both a and b d. None of these

Last Answer : b. Uncontrollable variables

Description : The variables which can be manipulated by the decision maker are called.................... a. Controllable variables b. Uncontrollable variables c. Both a and b d. None of these

Last Answer : a. Controllable variables

Description : The outlet where the services are being provided to the customers is called................. a. Waiting line b. Service facility c. Idle facility d. Traffic intensity

Last Answer : b. Service facility

Description : .................... is the popular method for solving an assignment problem. a. Hungarian Method b. Enumeration Method c. Simplex Method d. None of the above

Last Answer : a. Hungarian Method

Description : Hungarian method was developed by ........................ a. T C Koopman b. F L Hitchcock c. D Konig d. George B Dantzig

Last Answer : c. D Konig

Description : Which of the following methods is used to solve an assignment problem: a. Enumeration Method b. Hungarian Method c. Simplex Method d. All of the above

Last Answer : d. All of the above

Description : VAM is also called........................ a. Matrix Minima Method b. Penalty Method c. MODI Method d. None of these

Last Answer : b. Penalty Method

Description : Transportation model was first introduced by ........................ in the year 1941. a. T C Koopman b. George B Dantzig c. Von-neumann d. F L Hitchcock

Last Answer : d. F L Hitchcock

Description : ................................is that element of the simplex table which lis both in the key row and key column. a. Key element b. Pivot element c. Both a and b d. None of these

Last Answer : c. Both a and b

Description : Which of the following is a characteristic of a dual problem: a. Dual of a dual is primal b. If dual has a finite optimal solution, then the primal also has finite optimal solution c. If dual has no feasible solution, then the primal also has no feasible solution d. All of the above

Last Answer : d. All of the above

Description : Game theory became popular when the book “Theory of Games and Economic Behaviour” was published in 1944 by .............................. a. Von Neumann b. Mc Closky c. Von-Neumann and Mc Closky d. Von-neumann and Morgenstern

Last Answer : d. Von-neumann and Morgenstern

Description : Traffic intensity is computed by using the formula: a. λ/μ b. μ/λ c. 1- λ/μ d. 1- μ/λ

Last Answer : a. λ/μ

Description : Traffic intensity in Queuing Theory is also called........................... a. Service factor b. Arrival factor c. Utilisation factor d. None of these

Last Answer : c. Utilisation factor

Description : ..............................was the first person who developed a viable queueing theory a. Von Neumann b. Morgenstern c. H M Wagner d. Simeon Dennis Poisson

Last Answer : d. Simeon Dennis Poisson

Description : Excess of service facilities over and above the number of customers results: a. Idleness of service capacity b. Queues c. Both a and b d. None of these

Last Answer : a. Idleness of service capacity

Description : ............................refers to the manner in which the customers behave while being in the queue. a. Service pattern b. Service pattern c. Queue discipline d. None of these

Last Answer : c. Queue discipline

Description : MODI Method to test the optimality of a feasible solution to TP is also called............... a. Stepping Stone Method b. u. v. Method c. both a and b d. none of these

Last Answer : b. u. v. Method

Description : Matrix Minima Method to find initial feasible solution to a TP is also called ....................... a. NWCM b. LCM c. VAM d. None of these

Last Answer : c. VAM

Description : Initial feasible solution to a transportation problem arrived through which of the following method is very near to the optimal solution: a. NWCM b. LCM c. VAM d. None of these

Last Answer : c. VAM

Description : In queuing theory, FCFS stand for .............................. a. First Cum First Served b. First Customer Fist Served c. Fast Channel First Served

Last Answer : a. First Cum First Served

Description : ...................... is a method of analysing the current movement of the some variable in an effort to predict the future movement of the same variable. a. Goal programming b. Queuing theory c. Markov Analysis d. Replacement theory

Last Answer : c. Markov Analysis

Description : In queuing theory, ............................ stands for mean service rate. a. μ b. λ c. t d. none of these

Last Answer : a. μ