An activity which must be completed before commencement of one or more other activities
is called.................................
a. Successor activity
b. Predecessor activity
c. Dummy activity
d. None of these

1 Answer

Answer :

b. Predecessor activity

Related questions

Description : Activities that cannot be started until one or more of the other activities are completed, are called.......................................... a. Dummy activities b. Initial activities c. Successor activities d. Predecessor activities

Last Answer : c. Successor activities

Description : An activity which does not consume either resource or time is called ............................. a. Predecessor activity b. Successor activity c. Dummy activity d. Terminal activity

Last Answer : c. Dummy activity

Description : Activities lying on critical path are called ............................ a. Critical activities b. Non-critical activities c. Dummy activities d. None of these

Last Answer : a. Critical activities

Description : Auditing standards require a successor auditor to communicate with the predecessor auditor. The Code of Professional Conduct requires confidentiality; therefore, the client's permission must be obtained ... since this is one of the exceptions to confidentiality in the Code of Professional Conduc

Last Answer : The successor auditor

Description : The dummy source/destination in a transportation problem is added to ........................ a. Satisfy rim constraints b. Prevent solution from becoming degenerate c. Ensure total cost does not exceed a limit d. None of the above

Last Answer : a. Satisfy rim constraints

Description : Before accepting an audit engagement, a successor auditor should make specific inquiries of the predecessor auditor regarding a. Disagreements the predecessor had with the client concerning auditing ... lawyer. d. The predecessor's assessments of inherent risk and judgments about materiality

Last Answer : Disagreements the predecessor had with the client concerning auditing procedures and accounting principles.

Description : Before accepting an audit engagement, a successor auditor should make specific inquiries of the predecessor auditor regarding the predecessor's a. Evaluation of all matters of continuing accounting ... . Opinion of any subsequent events occurring since the predecessor's audit report was issued

Last Answer : Understanding as to the reasons for the change of auditors

Description : When a CPA is approached to perform an audit for the first time, the CPA should make inquiries of the predecessor auditor. This is a necessary procedure because the predecessor may be able to provide ... 's work should be utilized. d. Whether the company follows the policy of rotating its auditors.

Last Answer : Whether the engagement should be accepted.

Description : A successor auditor most likely would make specific inquiries of the predecessor auditor regarding a. Specialized accounting principles of the client's industry. b. Disagreements with management as to ... the client's internal audit staff. d. The uncertainty inherent in applying sampling procedures.

Last Answer : Disagreements with management as to auditing procedures

Description : When an independent auditor is approached to perform an audit for the first time, he/she should make inquiries of the predecessor auditor. Inquiries are necessary because the predecessor may ... documentation by the predecessor auditor can be utilized. d. The engagement proposal should be accepted

Last Answer : The engagement proposal should be accepted

Description : ............................ is the sequence of activities which determines the total project duration. a. Critical path b. Network c. Non-critical activities d. None of these

Last Answer : a. Critical path

Description : ......................... is a series of activities related to a project. a. Network b. Transportation Model c. Assignment model d. None of these

Last Answer : a. Network

Description : ........................may be defined as a method of determining an optimal program of interdependent activities in view of available resources. a. Goal programming b. Linear programming c. Decision making d. None of these

Last Answer : b. Linear programming

Description : ............................ models involve the allocation of resources to activities in such a way that some measure of effectiveness is optimised. a. Sequencing b. Allocation c. Queuing theory d. Decision theory

Last Answer : b. Allocation

Description : An event which represents the beginning of more than one activity is a : a. Merge event b. Net event c. Burst event d. None of these

Last Answer : c. Burst event

Description : Activities which must be finished before a given event can occur are termed as _________. A. Preceeding Activities. B. Succeeding Activities C. Concurrent Activities D. Dummy Activities.

Last Answer : A. Preceeding Activities.

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : In a network diagram, activity is denoted by ............................ a. Node b. Arrow c. Triangle d. None of these

Last Answer : b. Arrow

Description : ........................... is the latest time by which an activity can be finished without delaying the completion of the project. a. LST b. LFT c. EFT d. EST

Last Answer : b. LFT

Description : The EST + activity duration = .............................. a. Earliest Finish Time b. Latest Start Time c. Latest Finish Time d. None of these

Last Answer : a. Earliest Finish Time

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : PERT emphasises on ........................... a. Activity b. Time c. Cost d. None of these

Last Answer : b. Time

Description : ......................... is activity oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : a. CPM

Description : The assignment problem is: a. Requires that only one activity be assigned to each resource b. Is a special case of transportation problem c. Can be used to maximise resource d. All the above

Last Answer : d. All the above

Description : An officer transferred may not, without urgent necessity or special orders of the Head of the circle, leave the station a) Before the arrival of the permanent successor b) After the arrival of the permanent successor c) After completed his tenure d) None of these

Last Answer : a) Before the arrival of the permanent successor

Description : Before formulating a formal L P model, it is better to: a. Verbally identify decision variables b. Express the objective function in words c. Express each constraint in words d. All of the above

Last Answer : d. All of the above

Description : . A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of: A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

Last Answer : A. Finish-to-Start

Description : A schedule activity may begin 10 days before the predecessor activity finishes. This is an  example of: A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

Last Answer : A. Finish-to-Start

Description : Mobilization advance up to 10% of the cost of work is given to a contractor (A) On commencement of work at site for payment of loan taken by him (B) For the purchase of construction ... staff (D) For all activities required to start the work at site on finalization of the contract document

Last Answer : (D) For all activities required to start the work at site on finalization of the contract document

Description : Graphic method can be applied to solve a liner programming problem when there are only ........................... variables a. A one b. Two c. Three d. More than three

Last Answer : b. Two

Description : If there are more than one optimal solutions for the decision variables, the solution is ........... a. Infeasible b. Unbounded c. Alternative d. None of these

Last Answer : c. Alternative

Description : ......................... models involve more risks and uncertainties. a. Probabilistic b. Deterministic c. Both a and b d. None of these

Last Answer : a. Probabilistic

Description : Controllable variables are also called.................................. a. Slack variables b. Surplus variables c. Artificial variable d. Decision variables

Last Answer : d. Decision variables

Description : The variables which cannot be manipulated by the decision maker are called.................... a. Controllable variables b. Uncontrollable variables c. Both a and b d. None of these

Last Answer : b. Uncontrollable variables

Description : The variables which can be manipulated by the decision maker are called.................... a. Controllable variables b. Uncontrollable variables c. Both a and b d. None of these

Last Answer : a. Controllable variables

Description : The outlet where the services are being provided to the customers is called................. a. Waiting line b. Service facility c. Idle facility d. Traffic intensity

Last Answer : b. Service facility

Description : VAM is also called........................ a. Matrix Minima Method b. Penalty Method c. MODI Method d. None of these

Last Answer : b. Penalty Method

Description : Shadow price is also called ...................... a. Dual price b. Unit price c. Total cost d. None of these

Last Answer : a. Dual price

Description : Traffic intensity in Queuing Theory is also called........................... a. Service factor b. Arrival factor c. Utilisation factor d. None of these

Last Answer : c. Utilisation factor

Description : MODI Method to test the optimality of a feasible solution to TP is also called............... a. Stepping Stone Method b. u. v. Method c. both a and b d. none of these

Last Answer : b. u. v. Method

Description : Matrix Minima Method to find initial feasible solution to a TP is also called ....................... a. NWCM b. LCM c. VAM d. None of these

Last Answer : c. VAM

Description : A customer’s behaviour of jumping from one queue to another is called ............................ a. Jockying b. Reneging c. Collusion d. Balking

Last Answer : a. Jockying

Description : A customer’s behaviour of leaving the queue due to impatience is called ....................... a. Jockying b. Reneging c. Collusion d. Balking

Last Answer : b. Reneging

Description : a customer’s behaviour of leaving the queue when he does not like to wait in the queue due to lack of time or space is called ..................... a. Jockying b. Reneging c. Collusion d. Balking

Last Answer : d. Balking

Description : The ration between mean arrival rate and mean service rate is called ................... a. Idle period b. Average length of queue c. Traffic intensity d. None of these

Last Answer : c. Traffic intensity

Description : Number of customers in the queue per unit of time is called ...................... a. Queuing system b. Length of queue c. Average length of queue d. None of these

Last Answer : c. Average length of queue

Description : When all the players of the game follow their optimal strategies, then the expected pay off of the game is called....................... a. Gain of the game b. Loss of the game c. Value of the game d. None of these

Last Answer : c. Value of the game

Description : A matrix which shows the gains and losses resulting from moves and counter moves is called.................................. a. Cost matrix b. Pay off matrix c. Both a and b d. None of these

Last Answer : b. Pay off matrix

Description : Each participant of the game is called................... a. Strategist b. Winner c. Player d. Loser

Last Answer : c. Player

Description : The allocated cells in the transportation table are called .............................. a. Occupied cells b. Empty cells c. Unoccupied cells d. None of these

Last Answer : a. Occupied cells