Calculate re-order level from the following:
Safety stock: 1000 units
Consumption per week: 500 units
It takes 12 weeks to reach material from the date of ordering.
(a) 1000 units
(b) 6000 units
(c) 3000 units
(d) 7000 units
Safety stock: 1000 units
Consumption per week: 500 units
It takes 12 weeks to reach material from the date of ordering.
(a) 1000 units
(b) 6000 units
(c) 3000 units
(d) 7000 units