Which of the following is not a potential for a ranking problem between two mutua lly

exclusive projects?

A. The projects have unequal lives that differ by several years.

B. The costs of the two projects differ by nearly 30%.

C. The two projects have cash flow patterns that differ dramatically.

D. One of the mutually exclusive projects involves replacement while the other

involves expansion

1 Answer

Answer :

A. The projects have unequal lives that differ by several years

Related questions

Description : Which of the following is not a potential for a ranking problem between two mutua lly exclusive projects? A. The projects have unequal lives that differ by several years. B. The ... dramatically. D. One of the mutually exclusive projects involves replacement while the other involves expansion.

Last Answer : A. The projects have unequal lives that differ by several years.

Description : Which of the following is not a potential for a ranking problem between two mutua lly exclusive projects? A. The projects have unequal lives that differ by several years B. The ... dramatically D. One of the mutually exclusive projects involves replacement while the other involves expansion

Last Answer : A. The projects have unequal lives that differ by several years

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated.

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : A project whose acceptance requires the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project B. an independent project C. a dependent project D. None of the above

Last Answer : B. an independent project

Description : A project whose acceptance precludes the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project. D. a contingent project.

Last Answer : A. a mutually exclusive project.

Description : A project whose acceptance requires the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project E. none of the above

Last Answer : A. a mutually exclusive project.

Description : A project whose acceptance precludes the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project

Last Answer : C. a dependent project

Description : A project whose acceptance requires the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project E. none of the above

Last Answer : A. a mutually exclusive project.

Description : A project whose acceptance precludes the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project

Last Answer : C. a dependent project

Description : Which of the following is least likely to be part of the calculation of the terminal- year incremental net cash flow for an energy-related expansion project? A. An initial working capital ... Disposal/reclamation costs C. Capitalized expenditures D. Salvage value of any sold or disposed assets

Last Answer : D. Salvage value of any sold or disposed assets

Description : A profitability index (PI) of .92 for a project means that . A. The project's costs (cash outlay) are (is) less than the present value of the project's benefits B. The project's NPV is ... is greater than 1 D. The project returns 92 cents in present value for each current rupee invested (cost)

Last Answer : C. The project's NPV is greater than 1

Description : Which of the following statements regarding cash flow patterns (for time periods 0, 1, 2, 3, and 4) is correct? A. The sequence of -Rs.100, Rs.50, Rs.40, Rs.60, and Rs.50 is a non-conventional cash ... -Rs.50, Rs.50, Rs.70, Rs.60, and -Rs.150 potentially has at most two internal rates of return.

Last Answer : B. The sequence of -Rs.100, Rs.600, -Rs.1,100, Rs.600, and Rs.20 potentially has a maximum of two internal rates of return.

Description : Communication management: 1. Is important only in projects involving telephone, television, radio, or newspaper production  facilities and operations  2. Is not a big problem for people with normal ... . Involves the originator, the message, the medium and the receiver  4. Preparing an agenda

Last Answer : 3. Involves the originator, the message, the medium and the receiver

Description : According to a statistical report: over 30% of all projects are cancelled before completion and over 70% of the remainder fail to deliver expected features . What must be the reason for such ... change management b) Poor requirements management c) Poor quality control d) All of the mentioned

Last Answer : b) Poor requirements management

Description : To the nearest rupee, what is the net present value of a replacement project whose cash flows are -Rs.104,000; Rs.34,444; Rs.39,877; Rs.25,000; and Rs.52,800 for years 0 through 4, respectively? The firm has decided to ... -free rate is 6%. A. Rs.15,115 B. Rs.26,798 C. Rs.33,346 D. Rs.48,121

Last Answer : C. Rs.33,346

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.

Description :  A key factor in staffing a project involves motivating people to meet the project’s  objectives, and the most effective way to do this is through the use of money and bonuses.

Last Answer : Ans: False

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A) Algorithmic model (B) Expert judgment (C) Top down (D) Analogy

Last Answer : (D) Analogy

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A)Algorithmic model (B)Expert judgment (C)Top down (D)Analogy

Last Answer : (D)Analogy

Description : A Project control system: 1. Monitors and controls the project's schedule, costs, scope, budgets etc  2. Is a mechanism which reacts to the current project status in order to endure ... 4. Is a system for controlling and executing project documentation in an uniform and timely  manner

Last Answer : 1. Monitors and controls the project's schedule, costs, scope, budgets etc

Description : Which of the following is not a capital budgeting decision? A. Expansion programme B. Merger C. Replacement of an Asset D. Inventory Level

Last Answer : D. Inventory Level

Description : How does a project differ from an ongoing work effort?  A. It is unique B. It involves more than one person C. It has a project manager D. It is not a repetitive process that follows an organization’s existing procedures  (Ans.)

Last Answer : D. It is not a repetitive process that follows an organization’s existing procedures  (Ans.)

Description : Which of the following statements is incorrect regarding a normal project? A. If the NPV of a project is greater than 0, then its PI will exceed 1. B. If the IRR of a project is 8%, its NPV, using ... the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Last Answer : D. If the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : What is called inconsistent support? a) If two literals are not negation of other b) If two literals are negation of other c) Mutually exclusive d) None of the mentioned

Last Answer : b) If two literals are negation of other

Description : The three major functions of business organizations (a) are mutually exclusive ; (b) exist independently of each other ; (c) overlap (d) function independently of each other

Last Answer :  (c) overlap

Description : The basic capital budgeting principles involved in determining relevant after-tax incremental operating cash flows require us to . A. include sunk costs, but ignore opportunity costs B. include ... C. ignore both opportunity costs and sunk costs D. include both opportunity and sunk costs

Last Answer : B. include opportunity costs, but ignore sunk costs

Description : ____ is a continuous and repetitive process involving screening, documentation,  validation, ranking and approval of viable project ideas for an organization.

Last Answer : Ans. Project identification

Description : Following is (are) the component(s) of risk management (A)Risk Assessment (B)Risk Control (C)Risk Ranking (D)All of the above

Last Answer : (D)All of the above

Description : As shown in the illustration, if 'R1' and 'R2' have unequal values, the ____________. EL-0019 A. voltage drop across 'R1' will not be equal to the voltage drop across 'R2' B. current flow ... energy dissipated in 'R2' D. current flow through 'R1' will differ from the current flow through 'R2'

Last Answer : Answer: D

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : Regarding women (not men) in the family, have you heard the phrase, "She got the beauty, I got the brains" as if the two are mutually exclusive.

Last Answer : These are all very interesting questions – I think it is a relatively new phenomenon that one of the sisters even gets ‘the smart one’ label.

Description : A and B are two mutually exclusive and exhaustive events with P(B) = 3P(A). What is the value of P (bar(B)) ? -Maths 9th

Last Answer : (c) 43 : 34Given, odds against A = 8 : 3⇒ P(not A) = \(rac{8}{8+3}\) = \(rac{8}{11}\) ⇒ P(A happens) = \(rac{3}{11}\)Odds against B = 5 : 2⇒ P(not B) = \(rac{5}{5+2}\) = \(rac{5}{7}\) ⇒ P(B happens ... {43}{77}\)odds against C = \(rac{P(not\,c)}{P(c)}\) = \(rac{rac{43}{77}}{rac{34}{77}}\) = 43 : 34.

Description : Are Two events mutually exclusive if they have no outcomes in common.?

Last Answer : Need answer

Description : Are cynicism and naïveté mutually exclusive?

Last Answer : No, only a cynic would consider someone not cynical as naive. There are a lot of people with a positive outlook on life that are not naive nor are they cynical. I am one, I am well aware of ... that most of the world is generally positive and attempting as best they can to bring light to the world.

Description : Are neurons and neurotransmitters mutually exclusive?

Last Answer : answer:I don't know why you asked this but I sure like the question. Here's what I found, according to Rebecca Seal, a neuroscientist at the University of California, San Francisco: (excerpt) ... cells-in other words, certain branches of a single neuron release glutamate, and others do not. Source

Description : Are self-improvement and being yourself mutually exclusive? Which is more important?

Last Answer : “Acting natural” is a paradox. Better to be natural, though that doesn’t prevent a person from improving themselves.

Description : What do you mean by Mutually Exclusive Events? -Maths 9th

Last Answer : The events are said to be mutually exclusive if they cannot occur simultaneously in a single draw. Events such as tossing a head or a tail with a coin, drawing a queen or a jack from a pack of cards, ... the card can be the king of spades. Similarly for B and C, the card can be king of hearts.

Description : Define Not-Mutually Exclusive events.

Last Answer : Ans: If two events A & B have some thing common in sample space S then the event will be Not-Mutually exclusive event.

Description : Define Mutually Exclusive events.

Last Answer : Ans: If two events A & B have nothing common in sample space S then the event will be mutually exclusive event.