Following is (are) the component(s) of risk management

(A)Risk Assessment

(B)Risk Control

(C)Risk Ranking

(D)All of the above

1 Answer

Answer :

(D)All of the above

Related questions

Description : The primary components of the quality management function are : 1. quality planning  2. quality control and assurance  3. quantitative measurement  4. quantitative assessment of the project

Last Answer : 5. a and b

Description : All of the following are true regarding the Qualitative Risk Analysis process except  which one?  A. Probability and impact and expert interview are used to help correct biases that occur  in the data ... of this process used to determine  which risks need near-term response plans.

Last Answer : C. Qualitative Risk Analysis is an easy method of determining risk probability and  impact that usually takes a good deal of time to perform.

Description : A risk is defined as what might happened to the ____________ of the project 1. assessment  2. detriment  3. schedule  4. cost  5. scope

Last Answer : 2. detriment

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Which of the following is the most important element of Project Management Plan that is  useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : The main purpose of the Project Management Plan is to:  a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk  of alternative options.  b ... managing the project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for  managing the project.

Description : ____ is a continuous and repetitive process involving screening, documentation,  validation, ranking and approval of viable project ideas for an organization.

Last Answer : Ans. Project identification

Description : Which of the following is not a potential for a ranking problem between two mutua lly exclusive projects? A. The projects have unequal lives that differ by several years. B. The ... dramatically. D. One of the mutually exclusive projects involves replacement while the other involves expansion.

Last Answer : A. The projects have unequal lives that differ by several years.

Description : Which of the following is not a potential for a ranking problem between two mutua lly exclusive projects? A. The projects have unequal lives that differ by several years. B. The ... dramatically. D. One of the mutually exclusive projects involves replacement while the other involves expansion

Last Answer : A. The projects have unequal lives that differ by several years

Description : Which of the following is not a potential for a ranking problem between two mutua lly exclusive projects? A. The projects have unequal lives that differ by several years B. The ... dramatically D. One of the mutually exclusive projects involves replacement while the other involves expansion

Last Answer : A. The projects have unequal lives that differ by several years

Description : Which of the following statements concerning analytical procedures is true? a. Analytical procedures are more efficient, but not more effective, than tests of details of transactions. ... usually involve comparisons of ratios developed from recorded amounts with ratios developed by management

Last Answer : Analytical procedures used as risk assessment procedures use data aggregated at a high level.

Description : The main aim of a project risk management process should be to: a. identify project risks and then manage them appropriately. b. identify all project risks and transfer them immediately. c ... are threats or opportunities on a project. d. satisfy the organization's project management process.

Last Answer : a. identify project risks and then manage them appropriately.

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : The main outcome of risk identification, in a risk management process, is to: a. identify and determine the relative importance of the project risks. b. identify and describe all risks that ... responses to the project risks. d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : Project risk management is best described as: a. managing responses to threats. b. identifying and acknowledging threats and opportunities. c. planning responses to threats. d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.

Description : What should be done by the project manager to ensure that all the work in the  project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.

Last Answer : c. Create a WBS.

Description : What is the first step in developing a risk management plan? Select one: a. Analyze the risks. b. Estimate the likelihood of the risks occurring. c. Identify potential project risks. d. Develop a risk mitigation plan. e. Estimate the potential impact of risk on the project goals.

Last Answer : c. Identify potential project risks.

Description : Which of the following is not a Configuration Management  Activity? a) Configuration item identification b) Risk management c) Release management d) Branch management

Last Answer : b) Risk management

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : Which of the following is not considered as a risk in project management? a. Specification delays b. Product competition c. Testing d. Staff turnover

Last Answer : c. Testing

Description : Risk in project management is defined as  A.An uncertain event that, if it occurs, has a positive effect on project objectives  B.An uncertain event that, if it occurs, has a negative ... effect on project  objectives  D.An uncertain event that do not have any effect on project objectives

Last Answer : C.An uncertain event that, if it occurs, has a positive or negative effect on project  objectives

Description : Each of the following statements is true regarding the risk management plan except  for which one?  A. The risk management plan is an output of the Risk Management Planning process. B. The risk ... and budgets. D. The risk management plan is an input to all the remaining risk-planning processes.

Last Answer : B. The risk management plan includes a description of the responses to risks and  triggers.

Description : The process of assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes ... Risk Analysis B. Risk Identification C. Qualitative Risk Analysis D. Risk Management Planning

Last Answer : C. Qualitative Risk Analysis

Description : Andrew has joined as the Project Manager of a project. One of the project documents  available to Andrew lists down all the risks in a hierarchical fashion. What is this document  called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : The main aim of a project risk management process should be to:  a. identifies project risks and then manage them appropriately.  b. identify all project risks and transfer them immediately.  ... are threats or opportunities on a project.  d. satisfy the organisation's project management process.

Last Answer : a. identifies project risks and then manage them appropriately.

Description : A Responsibility Assignment Matrix (RAM) can be used to:  a. define the terms of reference of the project manager.  b. define the limits of the project sponsor's responsibilities.  ... response activities to project personnel.  d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : The main outcome of risk identification, in a risk management process, is to:  a. identify and determine the relative importance of the project risks.  b. identify and describe all risks that ... to the project risks.  d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : Project risk management is best described as:  a. managing responses to threats.  b. identifying and acknowledging threats and opportunities.  c. planning responses to threats.  d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : During the planning development process, at times it is necessary to make certain assumptions to enhance the project plan when the data is not available. In regard to making those assumptions, ... upon historical data used for the project.  4. Senior management predefines the budget constraints.

Last Answer : 1. The assumptions will be considered as true, real, or certain.

Description : In project management, which of the following is NOT a method of reducing the impact of an unexpected event? (A) Risk avoidance (B) Risk sharing (C) Risk transfer (D) Risk elimination

Last Answer : D) Risk elimination

Description : Identify the incorrect statement in connection with working capital management. A. Long-term funds are more expensive than short-term funds but also riskier B. The objectives of ... fluctuating current assets E. Aggressive financing policies increase profitability at the cost of higher risk

Last Answer : A. Long-term funds are more expensive than short-term funds but also riskier

Description : In deciding the optimal level of current assets for the firm, management is confronted with  . A. a trade-off between profitability and risk B. a trade-off between liquidity and risk C. a trade-off between equity and debt D. a trade-off between short-term versus long-term borrowing

Last Answer : A. a trade-off between profitability and risk

Description : Which of the following is a basic principle of finance as it relates to the management of  working capital? A. Profitability varies inversely with risk. B. Liquidity moves together with risk. C. Profitability moves together with risk. D. Profitability moves together with liquidity.

Last Answer : C. Profitability moves together with risk.

Description : What Is A Risk In The Context Of Project Management?

Last Answer : In the context of Project Management, a risk is any factor (or threat) that may adversely affect the successful completion of the project in terms of achievement of its outcomes, delivery of its outputs or adverse effects upon resourcing, time, cost and quality.

Description : What Are The Benefits Of Risk Management In The Context Of Project Management?

Last Answer : The benefit of risk management is to increase the likelihood that the project will be completed successfully by ensuring levels of risk and uncertainty in the project is properly managed. It enables ... risks, the manner in which they can be contained and the likely cost of mitigation strategies.

Description : Is It Still Worthwhile To Do Risk Management When A Project Is Half Over?

Last Answer : Yes, there are still risks associated with a project even if it is half over. This also forms a baseline for the remainder of the project.

Description : What Is The Difference Between A Risk And An Issue In The Context Of Project Management?

Last Answer : An issue is a problem or concern that may impede the progress of the project if not addressed. A risk is any factor (or threat) that may adversely affect the successful completion of the ... of its outcomes, delivery of its outputs or adverse effects upon resourcing, time, cost and quality.

Description : Project management is the second major component of the planning phase of the  systems development life cycle (SDLC), and it includes three steps: creating the work  plan, staffing the project, and controlling and directing the project.

Last Answer : Ans: True

Description : The ____ of project closeout the assessment is to document the best practices and  lessons learned for use on future projects.

Last Answer : Ans. Primary purpose

Description : Estimates from the planning stage will need to be refined as the project progresses,  because it is virtually impossible to develop an exact assessment of the project’s schedule  before the analysis and design phases are conducted.

Last Answer : Ans: True

Description : Cost controls can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Last Answer : 4. The process of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Description : Cost budgeting can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on an on- going basis

Last Answer : 3. The process of establishing budgets, standards, and a monitoring system by which the  investment cost of the project can be measured and managed

Description : Which of the following should the auditors normally interview as part of their assessment of fraud risk? a. Senior management b. Audit committee c. Various employees whose duties financial reporting responsibilities d. All of the given choices

Last Answer : All of the given choices

Description : In the preparation of an audit program, which of the following items is not essential? a. Assessment of inherent risk b. The preparation of a budget identifying the costs of resources needed c. A review of material from prior audits d. An understanding of controls established by management

Last Answer : The preparation of a budget identifying the costs of resources needed