Jack is in charge of a project team. Due to an unexpected project 

change, some issues with the project have come up. Two key team 

members, Samantha and Felix, are arguing their solutions to the project 

problems. They cannot convince each other, and their conflict is creating a 

negative impact on the project’s progress. As a PMP, which of the following

would be the best advice for Jack to manage this conflict?

Select one:

a. Confront the problem early, and invite both Samantha and Felix to private meetings.

b. Force Felix to give up and to support Samantha.

c. Suggest that Samantha concede to Felix.

d. Let Felix and Samantha exercise their concerns through conflict resolution.

e. Delay this issue for now until it becomes a significant conflict.

1 Answer

Answer :

a. Confront the problem early, and invite both Samantha and Felix to private meetings.

Related questions

Description : Which of the following is true about management meetings? Select one: a. They are short meetings to develop a common understanding of what the short-term  priorities are for the project. ... , tracking progress of existing plans, and  making adjustments to plans in response to new information.

Last Answer : e. They are oriented toward developing plans, tracking progress of existing plans, and  making adjustments to plans in response to new information.

Description : Who owns the Project Management Plan (PMP)? a. The project team. b. The chief executive. c. The project manager. d. The project support office.

Last Answer : c. The project manager.

Description : Who owns the Project Management Plan (PMP)?  a. The project team.  b. The chief executive.  c. The project manager.  d. The project support office.

Last Answer : c. The project manager.

Description :  . Integrity in the project management field is accomplished through all of the  following except which one?  A. Training to learn how to manage relationships with others from different ... C. Applying established project management processes D. Following the PMP Code of Professional Conduct

Last Answer : A. Training to learn how to manage relationships with others from different cultures

Description : Determining the policies that are needed for the smooth execution of a project  relates to which of the following agenda items of alignment sessions? Select one: a. Developing a common ... role clarification on projects e. Agreeing on the means and methods for accomplishing the purpose

Last Answer : d. Developing role clarification on projects

Description : The most significant challenge to project managers is _____.  a. lack of project management training  b. no one really understands how to manage a complex systems development project  ... tools that can assist in controlling project progress  d. unrealistic schedule demands by project sponsors

Last Answer : d. unrealistic schedule demands by project sponsors

Description : Which one of the following is a responsibility of the project steering group/board? a. To identify potential problems for the project team to solve. b. To provide strategic direction and guidance ... project team in all daily activities. d. To receive and consider daily reports from team members.

Last Answer : b. To provide strategic direction and guidance to the sponsor.

Description : Which one of the following is a responsibility of the project steering group/board?  a. To identify potential problems for the project team to solve.  b. To provide strategic direction and ... project team in all daily activities. d. To receive and consider daily reports from team members.

Last Answer : b. To provide strategic direction and guidance to the sponsor.

Description : According to the Project Management Institute (PMI), the scope statement should  address all of the following issues EXCEPT: Select one: a. project constraints. b. project assumptions c. project ... d. code of conduct for the team members working on the project. e. project deliverables.

Last Answer : d. code of conduct for the team members working on the project.

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : Approximately what percentage of the project manager's time is spent in some form of  communication, such as: conferences, meetings, writing memos, reading and preparing reports, and talking with project  team members, upper ... other stalk holders? 1. 10-20%  2. 50-70%  3. 75-90%  4. 21-45%

Last Answer : 3. 75-90%

Description : Which one of the following statements is true? a. Business-as-usual activities cannot be improved. b. Business-as-usual activities are more difficult to manage than projects. c. Projects are ... change to business-as-usual. d. A project is always the starting point for operation refinement

Last Answer : c. Projects are transient endeavours that bring about change to business-as-usual.

Description : Which one of the following statements is true?  a. Business-as-usual activities cannot be improved.  b. Business-as-usual activities are more difficult to manage than projects.  c. Projects are ... change to business-as-usual.  d. A project is always the starting point for operation refinement.

Last Answer : c. Projects are transient endeavours that bring about change to business-as-usual

Description : Ahmed is actively initiating a project, so he plans to invite all relevant  internal and external stakeholders including sponsors, customers, project  teams, etc. for a kick-off meeting. To ensure all ... b. Scope statement c. Project charter d. Work packages e. Project funding agents

Last Answer : c. Project charter

Description : Reena's father works with a company that builds dams. Once he took her to the site where a dam was being built. Reena saw a group of people sitting there and shouting slogans against the ... the peaceful resolution of the conflict proved to boon for many citizens of the country. How? -Biology

Last Answer : (i) Because she convinced the people by explaining them the advantage of constructing dam and come with a solution of rehabilitation of displaced peoples. So the contribution to the peaceful resolution of ... (c) Low cost of production of electricity gives monetary gain which is a boon to citizens.

Description : Which of the following statements is true regarding contracts? Select one: a. They are the filters through which project members screen information that is shared. b. They do not lend ... information-rich  environment will suffer. e. Contracts promote the growth of a trusting project culture.

Last Answer : b. They do not lend themselves to create an environment of trust.

Description : Which one of the following is true for the Project Management Plan (PMP)? a. The Project Management Plan is developed by the project manager and team and owned by the  sponsor. b. A ... The Project Management Plan is developed by the project manager and team and owned by the project manager.

Last Answer : d. The Project Management Plan is developed by the project manager and team and owned by the project manager.

Description : Which one of the following is true for the Project Management Plan (PMP)?  a. The Project Management Plan is developed by the project manager and team and owned by the  sponsor. b. ... Management Plan is developed by the project manager and team and owned  by the project manager.

Last Answer : d. The Project Management Plan is developed by the project manager and team and owned  by the project manager.

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : Professional accountants may encounter problems in identifying unethical behavior or in resolving an ethical conflict. When facedwith significant ethical issues, professional accountants should do the following ... body or regulatory body to obtain an understanding of possible courses of action

Last Answer : If the problem is not resolved with the immediate superior and the professional accountant determines to go to the next higher managerial level, the immediate superior need not be notified of the decision.

Description : What is a key aspect of Project Manger leadership?  A. Great management skills  B. Negotiation  C. Creating a clear vision for the team to follow  D. Time management

Last Answer : C. Creating a clear vision for the team to follow

Description : Complete the following statement. As a project manager, Darrell is  excited that he is assigned to be in charge of the most important project  this year. After being chartered for the project, he ... c. prepare for the template to monitor project progress. d. estimate the entire project budget.

Last Answer : b. start to define and develop the stakeholder needs and requirements

Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : Which one of the following best describes project management?  a. Using APM's Body of Knowledge 6th edition as a guide to all projects.  b. Employing a project manager who has undertaken ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : Traditional Work Breakdown Structures tend to  a. focus on the design of the system as oppose to the needs of the current phase and  iteration  b. force too many levels of detail early on for large ... project and difficult to compare across projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : Why are changes to the project scope necessary? Select one: a. To understand reports b. To reflect new information c. To begin planning the project d. To teach team members what they need to know about their jobs e. To establish a trusting project culture

Last Answer : b. To reflect new information

Description : A Communications Management Plan does the following:  A. Coordinates an effort to communicate in meetings effectively B. Lays out a plan on how to communicate with your Project ... and  efficiently. D. Coordinates the communication between project leaders and uninterested project  members

Last Answer : C. Lays out the approach and method for delivering information effectively and  efficiently.

Description : In project management, which of the following is NOT a method of reducing the impact of an unexpected event? (A) Risk avoidance (B) Risk sharing (C) Risk transfer (D) Risk elimination

Last Answer : D) Risk elimination

Description : After the celebration of the successful milestone completion, a project manager  will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.

Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.

Description : According to the PMBOK guide, which of the following statements is  right in terms of using reserve analysis to determine a project budget? Select one: A. Reserve analysis always plans ... not practical. E. Contingency reserves have never been a concern when planning a project budget.

Last Answer : A. Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : )The critical element in a project's communication system is the: 1. Progress report * 2. Project directive  3. Project manager  4. Customer

Last Answer : 3. Project manager

Description : The project manager works with the project sponsor to identify the necessary resources  and team members needed to further develop the key project parameters – Cost, Scope,  Schedule, and Quality (CSSQ). (True/False)

Last Answer : Ans. True

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Resorce requirement in project becomes constant while the project is in its _____ progress stage. (A) 40 to 55% (B) 55 to 70% (C) 70 to 80% (D) 80 to 95%

Last Answer : (D) 80 to 95%

Description : Resorce requirement in project becomes constant while the  project is in its progress stage. (A) 40 to 55% (B) 55 to 70% (C) 70 to 80% (D) 80 to 95%

Last Answer : (D) 80 to 95%

Description :  A key factor in staffing a project involves motivating people to meet the project’s  objectives, and the most effective way to do this is through the use of money and bonuses.

Last Answer : Ans: False

Description : Conflict occurrence in projects is  A. Unavoidable  B. Depend on type of project  C. Avoidable  D. Depends on culture

Last Answer : A. Unavoidable

Description : Which one of the following best describes users? a. Providers of both strategic and tactical direction to the project. b. Those intended to receive benefits or operate outputs. c. Facilitators of an appropriate issue resolution procedure. d. Those providing full-time commitment to the project.

Last Answer : b. Those intended to receive benefits or operate outputs.

Description : Which one of the following best describes users?  a. Providers of both strategic and tactical direction to the project.  b. Those intended to receive benefits or operate outputs.  c. ... of an appropriate issue resolution procedure.  d. Those providing full-time commitment to the project.

Last Answer : b. Those intended to receive benefits or operate outputs.

Description : Which conflict resolution technique do project managers use most often?  A. Smoothing B. Norming C. Confronting D. Forcing

Last Answer : C. Confronting

Description : You are the project manager for a cable service provider. Your team members are  amiable with each other and are careful to make project decisions jointly. Which of the  following statements is true?  ... stage of Develop Project Team. D. They are in the forcing stage of Develop Project Team.

Last Answer : B. They are in the norming stage of Develop Project Team.