During the planning development process, at times it is necessary to make certain assumptions
to enhance the project plan when the data is not available. In regard to making those assumptions,
which one of the following is most true for project planning purposes?
1. The assumptions will be considered as true, real, or certain.
2. By making the assumption, it tends to reduce the project risk.
3. Project assumptions are based upon historical data used for the project.
4. Senior management predefines the budget constraints.