Each of the following statements is true regarding the risk management plan except 

for which one? 

A. The risk management plan is an output of the Risk Management Planning process.

B. The risk management plan includes a description of the responses to risks and 

triggers.

C. The risk management plan includes thresholds, scoring and interpretation methods, 

responsible parties, and budgets.

D. The risk management plan is an input to all the remaining risk-planning processes.

1 Answer

Answer :

B. The risk management plan includes a description of the responses to risks and 

triggers.

Related questions

Description : The process of assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes ... Risk Analysis B. Risk Identification C. Qualitative Risk Analysis D. Risk Management Planning

Last Answer : C. Qualitative Risk Analysis

Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis

Last Answer : c. Perform Qualitative risk analysis

Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis

Last Answer : c. Perform Qualitative risk analysis

Description : All of the following statements are true regarding risk events except which one?  Choose the least correct answer. A. Project risks are uncertain events.  B. If risks occur, they can ... that have more perceived rewards to the organization than the consequences of  the risk should be accepted.

Last Answer : C. Unknown risks are threats to the project objectives, and nothing can be done to  plan for them.

Description : The main outcome of risk identification, in a risk management process, is to: a. identify and determine the relative importance of the project risks. b. identify and describe all risks that ... responses to the project risks. d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : The main outcome of risk identification, in a risk management process, is to:  a. identify and determine the relative importance of the project risks.  b. identify and describe all risks that ... to the project risks.  d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description :  According to PMBOK, project management process groups are iterative, which  was originally defined by Walter Shewhart and later modified by Edward Deming.  Generally, one outcome from a previous process can serve ... -Do-Check-Act cycle c. Project phases d. PM processes e. HR process cycle

Last Answer : b. Plan-Do-Check-Act cycle

Description : The methods and regulation used to define goals, plan and monitor tasks and resources, identify and resolve issues, and control costs and budgets for a specific project is known as … a. project management. b. Process Management c. Process d. Activities

Last Answer : a. project management.

Description : All of the following are true regarding the Qualitative Risk Analysis process except  which one?  A. Probability and impact and expert interview are used to help correct biases that occur  in the data ... of this process used to determine  which risks need near-term response plans.

Last Answer : C. Qualitative Risk Analysis is an easy method of determining risk probability and  impact that usually takes a good deal of time to perform.

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description : The main purpose of the Project Management Plan is to:  a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk  of alternative options.  b ... managing the project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for  managing the project.

Description : Which one of the following statements about the project risk register is false? a. It facilitates the review and monitoring of risks. b. It facilitates the risk appetite. c. It facilitates the recording of risk responses. d. It facilitates the recording of risks.

Last Answer : b. It facilitates the risk appetite.

Description : Which one of the following statements about the project risk register is false?  a. It facilitates the review and monitoring of risks.  b. It facilitates the risk appetite.  c. It facilitates the recording of risk responses.  d. It facilitates the recording of risks

Last Answer : b. It facilitates the risk appetite

Description : Monte Carlo analysis can help predict the impact of risks on project deliverables.  This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis

Last Answer : B. Quantitative Risk Analysis

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Project risk management is best described as: a. managing responses to threats. b. identifying and acknowledging threats and opportunities. c. planning responses to threats. d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : Project risk management is best described as:  a. managing responses to threats.  b. identifying and acknowledging threats and opportunities.  c. planning responses to threats.  d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : Asking the patient questions to determine if the person understands the health teaching provided would be included during which step of the nursing process? a) Evaluation Evaluation includes observing ... ) Implementation Implementation is the step during which the teaching plan is put into action.

Last Answer : a) Evaluation Evaluation includes observing the person, asking questions, and comparing the patient’s behavioral responses with the expected outcomes.

Description : All of the following statements are true regarding risks except for which one? Choose the least correct answer.  A. Risks might be threats to the objectives of the project.  B. Risks are ... Risks might be opportunities to the objectives of the project.  D. Risks have causes and consequences.

Last Answer : B. Risks are certain events that may be threats or opportunities to the objectives of  the project

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.

Description : During the planning development process, at times it is necessary to make certain assumptions to enhance the project plan when the data is not available. In regard to making those assumptions, ... upon historical data used for the project.  4. Senior management predefines the budget constraints.

Last Answer : 1. The assumptions will be considered as true, real, or certain.

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : What is the first step in developing a risk management plan? Select one: a. Analyze the risks. b. Estimate the likelihood of the risks occurring. c. Identify potential project risks. d. Develop a risk mitigation plan. e. Estimate the potential impact of risk on the project goals.

Last Answer : c. Identify potential project risks.

Description : Andrew has joined as the Project Manager of a project. One of the project documents  available to Andrew lists down all the risks in a hierarchical fashion. What is this document  called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Which of the following is the most important element of Project Management Plan that is  useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Which of the following items should not be included in the  project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development  organisation, project responsibilities, managerial  objectives and priorities e) None of the above.

Last Answer : c) The life cycle model to be used

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Project management is the second major component of the planning phase of the  systems development life cycle (SDLC), and it includes three steps: creating the work  plan, staffing the project, and controlling and directing the project.

Last Answer : Ans: True

Description : The main aim of a project risk management process should be to: a. identify project risks and then manage them appropriately. b. identify all project risks and transfer them immediately. c ... are threats or opportunities on a project. d. satisfy the organization's project management process.

Last Answer : a. identify project risks and then manage them appropriately.

Description : The main aim of a project risk management process should be to:  a. identifies project risks and then manage them appropriately.  b. identify all project risks and transfer them immediately.  ... are threats or opportunities on a project.  d. satisfy the organisation's project management process.

Last Answer : a. identifies project risks and then manage them appropriately.

Description : Which of the following statements is true with regard to the relationship among audit risk, audit evidence, and materiality? a. The lower the inherent risk and control risk, the lower ... inherent risk. d. Aggregate materiality thresholds should not change under conditions of changing risk levels

Last Answer : Under conditions of high inherent and control risk, the auditor should place more emphasis on obtaining external evidence and should reduce reliance on internal evidence

Description : Which method is not included in seven Project Selection Methods?  A. Financial Analysis B. Strategic Alignment C. Weighted Scoring Model D. Straight line Model (Ans.)

Last Answer : D. Straight line Model (Ans.)

Description : Increasing evidence has implicated gram-negative bacterial lipopolysaccharide (LPS endotoxin) as the portion of the gram-negative bacterial cell membrane responsible for many, if not all the ... host, exerting deleterious effects on the host when excessive amounts reach the systemic circulation

Last Answer : Answer: a, b, d The LPS molecule exerts diverse effects on the mammalian host. Immunologic responses to LPS include nonspecific polyclonal B-cell proliferation, macrophage activation and ... deleterious effects on the host only after large amounts are secreted and reach the systemic circulation

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : Which of the following processes assesses the likelihood of risk occurrences and their consequences using a numerical rating? A. Qualitative Risk Analysis B. Risk Identification C. Quantitative Risk Analysis D. Risk Response Planning

Last Answer : C. Quantitative Risk Analysis

Description : Role clarification facilitates the development of all of the following, EXCEPT: Select one: a. communication planning. b. key milestones. c. work flow organization. d. approval processes. e. role boundary spanning processes.

Last Answer : b. key milestones.

Description : Contract documentation is an input to both the Close Project and Contract Closure  processes. Contract documentation might include all of the following except for which  one?  A. Supporting documents B. Contract changes C. Financial documents D. Procurement audit documents

Last Answer : D. Procurement audit documents

Description : Which of the following statements is true of Insured Asset Allocation? A. It is aimed at benefiting from short-term under pricing and over pricing of assets. B. In this strategy the risk ... . It is a strategy aimed at achieving the objectives of the investor without depending on market timing

Last Answer : E. It is a strategy aimed at achieving the objectives of the investor without depending on market timing.

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : For initial audits, additional matters the auditor may consider in the overall audit strategy and audit plan include the following except a. Major issues including the application of ... firm personnel with appropriate levels of capabilities and competence to respond to anticipated significant risks

Last Answer : Confirmation of material accounts receivable balance at the end of the year.

Description : A prerequisite of effective time management is:  1. Knowing the dictated project completion date  2. Having the most advanced software package for project planning, scheduling and control  3. ... and the  person responsible for each of them  4. Having a well staffed scheduling department

Last Answer : 1. Knowing the dictated project completion date

Description : )The total amount of risk that is calculated for a project is found by 1. Multiplying the sum of each the risk times the amount at stake 2. Calculating the cumulative sum of the probability for ... 3. Cannot be calculated since all risks are not know  4. The amount of project reserves available

Last Answer : 2. Calculating the cumulative sum of the probability for each risk and multiplying this value times the consequence of occurrence of the risk events

Description : Which one of the following best describes project management?  a. Using APM's Body of Knowledge 6th edition as a guide to all projects.  b. Employing a project manager who has undertaken ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.