As a project manager, while Kathy was trying to categorize all potential
risks for her new construction project M based on levels of probability and
impact on the project, she identified a potential risk, regarding a schedule
conflict with another project to obtain critical equipment for a short time
period. Overall, because this risk is probable and might impact her project
M, Kathy wants to record this risk; however, she is confused about where
she should document this type of risk. According to the PMBOK guide,
where should Kathy document this risk?
Select one:
a. Watch list
b. Risk management plan
c. Project management plan
d. WBS
e. Scope management plan
risks for her new construction project M based on levels of probability and
impact on the project, she identified a potential risk, regarding a schedule
conflict with another project to obtain critical equipment for a short time
period. Overall, because this risk is probable and might impact her project
M, Kathy wants to record this risk; however, she is confused about where
she should document this type of risk. According to the PMBOK guide,
where should Kathy document this risk?
Select one:
a. Watch list
b. Risk management plan
c. Project management plan
d. WBS
e. Scope management plan