The cost impact of a risk event occurring as a project proceeds through its life cycle tends

to

A. Slowly rise

B. Slowly drop

C. Drop sharply and then level out

D. Rise sharply and then level out

1 Answer

Answer :

A. Slowly rise

Related questions

Description : What is the first step in developing a risk management plan? Select one: a. Analyze the risks. b. Estimate the likelihood of the risks occurring. c. Identify potential project risks. d. Develop a risk mitigation plan. e. Estimate the potential impact of risk on the project goals.

Last Answer : c. Identify potential project risks.

Description : Risk Event Graph is having following on X axis  A.Gantt Chart  B.Work Break Down Structure  C.Project Life Cycle  D.Splitting

Last Answer : C.Project Life Cycle

Description : In project management, which of the following is NOT a method of reducing the impact of an unexpected event? (A) Risk avoidance (B) Risk sharing (C) Risk transfer (D) Risk elimination

Last Answer : D) Risk elimination

Description : During the planning development process, at times it is necessary to make certain assumptions to enhance the project plan when the data is not available. In regard to making those assumptions, ... upon historical data used for the project.  4. Senior management predefines the budget constraints.

Last Answer : 1. The assumptions will be considered as true, real, or certain.

Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.

Description : Which one of the following statements best defines an estimate?  a. An approximation of project time and cost targets, refined throughout the project life  cycle.  b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life  cycle.

Description : The Three attributes of project risk are _________, ___________ and ___________. 1. What might happen, who it happens to, and how much will it cost  2. Notification, frequency of relevant events, ... planning, total number of risk events 5. Risk event, probability occurrence, the amount at stake

Last Answer : 5. Risk event, probability occurrence, the amount at stake

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Monte Carlo analysis can help predict the impact of risks on project deliverables.  This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis

Last Answer : B. Quantitative Risk Analysis

Description : An Expected Monetary Value (EMV) of $100000 on a potential project event in the  project means which of the following? Select one: a. A number that can be ignored b. An opportunity that ... Actual investment returns on the event e. A threat that must be considered to minimize the project risk

Last Answer : b. An opportunity that must be explored

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.

Description : Risk in project management is defined as  A.An uncertain event that, if it occurs, has a positive effect on project objectives  B.An uncertain event that, if it occurs, has a negative ... effect on project  objectives  D.An uncertain event that do not have any effect on project objectives

Last Answer : C.An uncertain event that, if it occurs, has a positive or negative effect on project  objectives

Description : Political unrest, budget overruns, size and complexity of the project  Answer: B  (8)Decision trees are best used for : 1. Determining the interaction of the amount at stake and the expected ... and the associated events  4. A flow chart which determines the standard deviation of the risk event

Last Answer : 3. An illustration of how to see the interactions between decisions and the associated events

Description : An uncertain event or condition that, if it occurs, has a positive or negative effect on a project objectives is termed. A. Random Chance B. Disaster C. Risk

Last Answer : C. Risk

Description : A situation in which one of two or more risk events will follow an act, but the precise nature  of these events may not be known and the probabilities of their occurring cannot be objectively  assigned, is ... 1. certainty  2. uncertainty  3. risk  4. risk adversity  5. None of the above.

Last Answer : 2. uncertainty

Description : To the nearest rupee, what is the net present value of a replacement project whose cash flows are -Rs.104,000; Rs.34,444; Rs.39,877; Rs.25,000; and Rs.52,800 for years 0 through 4, respectively? The firm has decided to ... -free rate is 6%. A. Rs.15,115 B. Rs.26,798 C. Rs.33,346 D. Rs.48,121

Last Answer : C. Rs.33,346

Description : Bleeding complications are frequently associated with fibrinolytic therapy. Which of the following statement(s) concerning complications of fibrinolytic therapy is/are true? a. Careful monitoring of prothrombin time ... months ago can be treated with fibrinolytic therapy if head CT scan is normal

Last Answer : Answer: b Fibrinolytic therapy induces a hemostatic defect through a combination of factors. Hypofibrinogenemia and fibrin degradation products inhibit fibrin polymerization and, in combination ... is considered a major relative contraindication to either regional or systemic thrombolytic therapy

Description : What is the most critical aspect in developing a project plan that meets project  specifications within the timeframe and at the lowest costs? Select one: a. Assessing risk management b ... business partners e. Developing a project execution plan that matches the complexity level of the project

Last Answer : e. Developing a project execution plan that matches the complexity level of the project

Description : Cost controls can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Last Answer : 4. The process of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Description : Cost budgeting can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on an on- going basis

Last Answer : 3. The process of establishing budgets, standards, and a monitoring system by which the  investment cost of the project can be measured and managed

Description : The accuracy of an estimate should: a. decrease as a project progresses through its life cycle. b. increase as a project progresses through its life cycle. c. stay constant throughout the project life cycle. d. vary independently of where the project is in its life cycle.

Last Answer : b. increase as a project progresses through its life cycle.

Description : The accuracy of an estimate should:  a. decrease as a project progresses through its life cycle.  b. increase as a project progresses through its life cycle.  c. stay constant throughout the project life cycle.  d. vary independently of where the project is in its life cycle.

Last Answer : b. increase as a project progresses through its life cycle.

Description : Considers the total cost of ownership, or development plus support costs, for a project. A. Learning Curve Theory B. Life Cycle Costing C. Parametric Modeling D. Rate of Performance

Last Answer : B. Life Cycle Costing

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : )In a program or project plan, there are always revisions to account for new or missing data.  Which one of the following provides the best reason for performing a revision of the plan? 1. ... 4. Historical data on a similar project suggests that risk events are not included in the current  plan.

Last Answer : 2. Project tasks are crashed to meet their end dates

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : The main purpose of the Project Management Plan is to:  a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk  of alternative options.  b ... managing the project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for  managing the project.

Description : )A new project was initiated that involves new technology and subsequently has never been  done before. What type of contract would to owner want to issue to reduce or eliminate as much  risk as possible. 1. Firm ... 2. Cost plus fix fee  3. Cost plus incentive fee  4. Lump sum  5. A and D

Last Answer : 5. A and D

Description : A risk is defined as what might happened to the ____________ of the project 1. assessment  2. detriment  3. schedule  4. cost  5. scope

Last Answer : 2. detriment

Description : The main aim of a project risk management process should be to: a. identify project risks and then manage them appropriately. b. identify all project risks and transfer them immediately. c ... are threats or opportunities on a project. d. satisfy the organization's project management process.

Last Answer : a. identify project risks and then manage them appropriately.

Description : The main aim of a project risk management process should be to:  a. identifies project risks and then manage them appropriately.  b. identify all project risks and transfer them immediately.  ... are threats or opportunities on a project.  d. satisfy the organisation's project management process.

Last Answer : a. identifies project risks and then manage them appropriately.

Description : Which one of the following best describes a project issue? a. A major problem that requires formal escalation. b. A problem that the project manager has to deal with on a day-to-day basis. c. An uncertain event that may or may not occur. d. An opportunity that occurs through change control.

Last Answer : a. A major problem that requires formal escalation.

Description : Which one of the following best describes a project issue?  a. A major problem that requires formal escalation.  b. A problem that the project manager has to deal with on a day-to-day basis.  c. An uncertain event that may or may not occur.  d. An opportunity that occurs through change control.

Last Answer : a. A major problem that requires formal escalation.

Description : A simple way of looking at the spiral life-cycle model is as a waterfall model with each phase proceeded by a) Build-and-fix b) Freezing c) Synchronization d) Testing e) Risk analysis

Last Answer : e) Risk analysis

Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis

Last Answer : c. Perform Qualitative risk analysis

Description : All of the following are true regarding the Qualitative Risk Analysis process except  which one?  A. Probability and impact and expert interview are used to help correct biases that occur  in the data ... of this process used to determine  which risks need near-term response plans.

Last Answer : C. Qualitative Risk Analysis is an easy method of determining risk probability and  impact that usually takes a good deal of time to perform.

Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis

Last Answer : c. Perform Qualitative risk analysis

Description : The hydrologic risk of a 100-year flood occurring during the 2-year service life of a project is (a) 9.8% (b) 9.9% (c) 19.9% (d) 1.99%

Last Answer : (d) 1.99%

Description : Which of the following factors does not need to be considered when formulating  policies on the level and financing of working capital? A. The attitude to risk of a company's managers B. ... C. The availability of revenue reserves and capital reserves D. Terms of trade offered by competitors

Last Answer : C. The availability of revenue reserves and capital reserves

Description : A world-famous magician and his young assistant were observed walking slowly along in a department store when suddenly they both stopped walking and began to slowly rise from the floor. The two ... and his assistant accomplished this feat, and why didn't the onlookers express amazement? -Riddles

Last Answer : The magician and his assistant were simply using an escalator to go up to the next floor in the department store.

Description : Following are the phases of Project Management Life Cycle. Arrange them in correct order 1. Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery (A) 3-2-1-4 (B) 1-2-3-4 (C) 2-3-1-4 (D) 4-3-2-1

Last Answer : (A) 3-2-1-4

Description : The project life cycle consists of (A) Understanding the scope of the project (B) Objectives of the project (C) Formulation and planning various activities (D) All of the above

Last Answer : (D) All of the above

Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : The phases of a project life cycle are: a. starting, planning, control and closing. b. concept, definition, development, handover and closure. c. initiation, definition, planning, monitoring and operations. d. concept, definition, implementation and operations.

Last Answer : b. concept, definition, development, handover and closure.