Description : Ahmed is actively initiating a project, so he plans to invite all relevant internal and external stakeholders including sponsors, customers, project teams, etc. for a kick-off meeting. To ensure all ... b. Scope statement c. Project charter d. Work packages e. Project funding agents
Last Answer : c. Project charter
Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to make changes to the ... reliability of the project scope and describes the process for verifying and accepting completed deliverables.
Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis for future project decisions.
Description : A project charter does not include ____ of the project. (A) scope (B) objectives (C) team (D) all above are included
Last Answer : (D) all above are included
Description : ) One of the initial project documents, issued by senior management, which outlines the authority of the project manager, is called Project charter. As a seller, what other document can be used in this place: 1. Work breakdown structure 2. Project scope 3. Contract 4. Internal memo
Last Answer : 3. Contract
Description : The document that describes the project’s objectives and rules is called the project charter.
Last Answer : Ans: True
Description : Which structure shows the reporting relationships and communications channels for a project? a. Work Breakdown Structure. b. Organizational Breakdown Structure. c. Product Breakdown Structure. d. Responsibility assignment structure.
Last Answer : b. Organizational Breakdown Structure.
Description : To identify the tasks for a work plan the project manager can _____. a. control and direct the project b. estimate the size, staff the project, and remember technical skills c. establish a ... of the SDLC and the steps that occur in each e. set conservative numbers for the project software
Last Answer : d. list the four phases of the SDLC and the steps that occur in each
Description : Which structure shows the reporting relationships and communications channels for a project? a. Work Breakdown Structure. b. Organisational Breakdown Structure. c. Product Breakdown Structure. d. Responsibility assignment structure.
Last Answer : b. Organisational Breakdown Structure.
Description : An Organizational Breakdown Structure (OBS) is used to identify: a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of communication ... . d. the reporting structure and lines of communication for all individuals in the projects.
Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.
Description : An Organisational Breakdown Structure (OBS) is used to identify: a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of ... project. d. the reporting structure and lines of communication for all individuals in the projects.
Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.
Last Answer : d. Application of processes and methods throughout the project life cycle.
Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken ... on a project full time. d. Application of processes and methods throughout the project life cycle.
Description : The conceptual estimate is developed with the least amount of knowledge. When more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate
Last Answer : c. rough order of magnitude (ROM) estimate
Description : Which one of the following best describes project success criteria? a. Actively seeking some senior management support. b. Measures by which the success of the project is judged. c. Achievement of milestones. d. A motivated project team.
Last Answer : b. Measures by which the success of the project is judged.
Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.
Last Answer : b. to deliver the project objectives to enable benefits to be realised.
Description : Fill in the blank. During the _________ of a project, the project manager focuses on developing the project infrastructure needed to execute the project and developing clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection
Last Answer : b. start-up
Description : Complete the following statement. As a project manager, Darrell is excited that he is assigned to be in charge of the most important project this year. After being chartered for the project, he ... c. prepare for the template to monitor project progress. d. estimate the entire project budget.
Last Answer : b. start to define and develop the stakeholder needs and requirements
Description : After Ling finished drafting a new project charter, she sent a copy of the charter to all key project parties including the project sponsor, senior management and key stakeholders, and scheduled ... from the key project players. e. Obtain officially signed project charters from the key parties.
Last Answer : e. Obtain officially signed project charters from the key parties.
Description : According to the PMBOK Guide, the project manager is identified and assigned during which process? A. Prior to beginning the Develop Project Charter process B. At the conclusion of the ... . Prior to beginning the Planning processes D. Prior to beginning the Preliminary Scope Statement process
Last Answer : C. Prior to beginning the Planning processes
Description : Which of the following is true regarding the project charter? A. The project charter should be published under the name of a manager external to the project. B. The project charter should be ... project manager. D. The project charter should be published under the name of the project champion.
Last Answer : A. The project charter should be published under the name of a manager external to the project.
Description : The Project charter is created by: 1. The project manager 2. Upper management 3. The Vice President over a functional management group 4. The customer
Last Answer : 2. Upper management
Description : Project reporting can best be defined as: a. informing stakeholders about the project. b. storing and archiving of project information. c. gathering stakeholder feedback. d. collecting project information.
Last Answer : a. informing stakeholders about the project.
Description : In tracking, reporting and controlling, the process engage whether the project results are in accordance with a. project plans b. performance specification c. both a, b d. none of the above
Last Answer : c. both a, b
Last Answer : a. informing stakeholders about the project
Description : Cost controls can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities, uncertainties, and inflation that could ... of gathering, accumulating, analyzing, reporting, and managing the costs on an on-going basis.
Last Answer : 4. The process of gathering, accumulating, analyzing, reporting, and managing the costs on an on-going basis.
Description : Cost budgeting can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities, uncertainties, and inflation that could ... of gathering, accumulating, analyzing, reporting, and managing the costs on an on- going basis
Last Answer : 3. The process of establishing budgets, standards, and a monitoring system by which the investment cost of the project can be measured and managed
Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder
Last Answer : B. Project Team Members responsible for the work package
Description : After the celebration of the successful milestone completion, a project manager will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.
Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.
Description : .Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder
Description : A project planning methodology is any structured approach used to guide the project team during development of the project plan. What is an example of this methodology? 1. Standard forms or templates. 2. Upper management involvement 3. Functional work authorizations 4. Stakeholders skills
Last Answer : 1. Standard forms or templates.
Description : From HR perspective, the project manager's responsibility in the planning role includes: 1. Hiring the team 2. Developing work schedules 3. Forecasting 4. Feedback sessions 5. Both b and c
Last Answer : 5. Both b and c
Description : In a ____, the employees work for different projects in a team-like structure.
Last Answer : Ans. Project-type organisational structure
Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of activities ... endeavor undertaken to achieve a desired outcome. d. A project is a method of planning work.
Last Answer : c. A unique transient endeavor undertaken to achieve a desired outcome.
Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of ... endeavour undertaken to achieve a desired outcome. d. A project is a method of planning work.
Last Answer : c. A unique transient endeavour undertaken to achieve a desired outcome.
Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.
Last Answer : a. It utilizes resources as and when required under direction of a project manager.
Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity
Last Answer : C. Text description of roles, responsibilities, authorities
Description : Sergei, the project manager, is worried about completing the project on time. To increase the productivity of his 15-person team he should create subteams with no more than 10 people on a sub team.
Description : Adding people to a project team in order to speed up total development time _____. a. is a standard task in timeboxing b. is a useful way to meet a tight deadline c. may actually increase total development time d. simplifies communication within the team e. none of the above
Last Answer : c. may actually increase total development time
Description : People participated in or affected by project activities are known as (A) staff (B) stakeholders (C) project team (D) project managers
Last Answer : (B) stakeholders
Description : Who are project team members primarily accountable to? a. External stakeholders. b. The end users. c. The finance director. d. The project manager.
Last Answer : d. The project manager.
Description : Which one of the following is true for the Project Management Plan (PMP)? a. The Project Management Plan is developed by the project manager and team and owned by the sponsor. b. A ... The Project Management Plan is developed by the project manager and team and owned by the project manager.
Last Answer : d. The Project Management Plan is developed by the project manager and team and owned by the project manager.
Description : Which one of the following is a responsibility of the project steering group/board? a. To identify potential problems for the project team to solve. b. To provide strategic direction and guidance ... project team in all daily activities. d. To receive and consider daily reports from team members.
Last Answer : b. To provide strategic direction and guidance to the sponsor.
Description : Who owns the Project Management Plan (PMP)? a. The project team. b. The chief executive. c. The project manager. d. The project support office.
Last Answer : c. The project manager.
Description : A communication management plan identifies the relevant information that should be communicated to: a. the project team. b. the project stakeholders. c. the project board. d. the project sponsor.
Last Answer : b. the project stakeholders.
Description : Which of these is not one of the constraints of a project? a. Scope b. Resources c. Team d. Budget
Last Answer : c. Team
Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager
Last Answer : b) project