Which one of the following best describes project management? 

a. Using APM’s Body of Knowledge 6th edition as a guide to all projects. 

b. Employing a project manager who has undertaken similar projects. 

c. Utilising team members who can work on a project full time.

d. Application of processes and methods throughout the project life cycle.

1 Answer

Answer :

d. Application of processes and methods throughout the project life cycle.

Related questions

Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.

Last Answer : a. It utilizes resources as and when required under direction of a project manager.

Description : Determining the policies that are needed for the smooth execution of a project  relates to which of the following agenda items of alignment sessions? Select one: a. Developing a common ... role clarification on projects e. Agreeing on the means and methods for accomplishing the purpose

Last Answer : d. Developing role clarification on projects

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : According to the PMBOK Guide, the project manager is identified and assigned  during which process?  A. Prior to beginning the Develop Project Charter process B. At the conclusion of the ... . Prior to beginning the Planning processes D. Prior to beginning the Preliminary Scope Statement process

Last Answer : C. Prior to beginning the Planning processes

Description : One of the reasons a project life cycle is split into phases is to: a. facilitate formal go/no-go decision making during the project. b. balance the costs of work in each phase of ... the major deployments of resources throughout the project. d. chunk work into time periods of similar durations.

Last Answer : a. facilitate formal go/no-go decision making during the project.

Description : One of the reasons a project life cycle is split into phases is to:  a. facilitate formal go/no-go decision making during the project.  b. balance the costs of work in each phase ... the major deployments of resources throughout the project.  d. chunk work into time periods of similar durations.

Last Answer : a. facilitate formal go/no-go decision making during the project.

Description : A project management information system consists of: 1. A project management software package operating on appropriate computer facilities  2. Hardware, software, documents, and procedures  3. Automated and ... of  pertinent information for members of a project team  4. All of the above

Last Answer : 4. All of the above

Description : The most successful project manager usually: 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience with formal ... . Has considerable experience as a functional manager before moving into the project  management arena.

Last Answer : 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : A project planning methodology is any structured approach used to guide the project team  during development of the project plan. What is an example of this methodology? 1. Standard forms or templates.  2. Upper management involvement  3. Functional work authorizations 4. Stakeholders skills

Last Answer : 1. Standard forms or templates.

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : .Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time.  b. to deliver the project objectives to ... benefits.  d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : Who are project team members primarily accountable to? a. External stakeholders. b. The end users. c. The finance director. d. The project manager.

Last Answer : d. The project manager.

Description : . A project leader or manager is expected to be completely accountable for his team  members and meeting the team’s targets. (True/False)

Last Answer : Ans. True

Description : The project manager works with the project sponsor to identify the necessary resources  and team members needed to further develop the key project parameters – Cost, Scope,  Schedule, and Quality (CSSQ). (True/False)

Last Answer : Ans. True

Description : Daniel has just been assigned as the project manager. To motivate his team properly,  Daniel’s first step is to award bonuses to team members

Last Answer : Ans: False

Description : You are the project manager for a cable service provider. Your team members are  amiable with each other and are careful to make project decisions jointly. Which of the  following statements is true?  ... stage of Develop Project Team. D. They are in the forcing stage of Develop Project Team.

Last Answer : B. They are in the norming stage of Develop Project Team.

Description : Who are project team members primarily accountable to?  a. External stakeholders.  b. The end users.  c. The finance director.  d. The project manager.

Last Answer : d. The project manager.

Description :  According to PMBOK, project management process groups are iterative, which  was originally defined by Walter Shewhart and later modified by Edward Deming.  Generally, one outcome from a previous process can serve ... -Do-Check-Act cycle c. Project phases d. PM processes e. HR process cycle

Last Answer : b. Plan-Do-Check-Act cycle

Description : The process each manager follows during the life of a project is known as a) Project Management b) Manager life cycle c) Project Management Life Cycle d) All of the mentioned

Last Answer : c) Project Management Life Cycle

Description :  The process each manager follows during the life of a project is known as a) Project Management b) Manager life cycle c) Project Management Life Cycle d) All of the mentioned

Last Answer : c) Project Management Life Cycle

Description : The process each manager follows during the life of a project is known as (A)Project Management (B) Manager life cycle (C) Project Management Life Cycle (D)All of the mentioned

Last Answer : (C) Project Management Life Cycle

Description : Which one of the following is true for the Project Management Plan (PMP)? a. The Project Management Plan is developed by the project manager and team and owned by the  sponsor. b. A ... The Project Management Plan is developed by the project manager and team and owned by the project manager.

Last Answer : d. The Project Management Plan is developed by the project manager and team and owned by the project manager.

Description : Which one of the following is true for the Project Management Plan (PMP)?  a. The Project Management Plan is developed by the project manager and team and owned by the  sponsor. b. ... Management Plan is developed by the project manager and team and owned  by the project manager.

Last Answer : d. The Project Management Plan is developed by the project manager and team and owned  by the project manager.

Description : Who owns the Project Management Plan (PMP)? a. The project team. b. The chief executive. c. The project manager. d. The project support office.

Last Answer : c. The project manager.

Description : Who owns the Project Management Plan (PMP)?  a. The project team.  b. The chief executive.  c. The project manager.  d. The project support office.

Last Answer : c. The project manager.

Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.

Description : Which one of the following statements best defines an estimate?  a. An approximation of project time and cost targets, refined throughout the project life  cycle.  b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life  cycle.

Description : The process of assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes ... Risk Analysis B. Risk Identification C. Qualitative Risk Analysis D. Risk Management Planning

Last Answer : C. Qualitative Risk Analysis

Description : Which one of the following best describes project success criteria? a. Actively seeking some senior management support. b. Measures by which the success of the project is judged. c. Achievement of milestones. d. A motivated project team.

Last Answer : b. Measures by which the success of the project is judged.

Description : Which one of the following best describes project success criteria?  a. Actively seeking some senior management support.  b. Measures by which the success of the project is judged.  c. Achievement of milestones.  d. A motivated project team.

Last Answer : b. Measures by which the success of the project is judged.

Description : Which of the following is true about a project manager? Select one: a. Project managers analyze work processes and explore opportunities to make  improvements. b. Project managers are focused ... . d. Project managers are goal oriented. e. Project managers standardize the work processes.

Last Answer : d. Project managers are goal oriented.

Description : Approximately what percentage of the project manager's time is spent in some form of  communication, such as: conferences, meetings, writing memos, reading and preparing reports, and talking with project  team members, upper ... other stalk holders? 1. 10-20%  2. 50-70%  3. 75-90%  4. 21-45%

Last Answer : 3. 75-90%

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : According to the Project Management Institute (PMI), the scope statement should  address all of the following issues EXCEPT: Select one: a. project constraints. b. project assumptions c. project ... d. code of conduct for the team members working on the project. e. project deliverables.

Last Answer : d. code of conduct for the team members working on the project.

Description : Project management provides the project managers and team members with the  principles they require to effectively meet the needs of the customer. (True/False)

Last Answer : Ans. True

Description : Configuration Management can be administered in several ways. These include a) A single configuration management team for the whole  organization b) A separate configuration management team for ... c) Configuration Management distributed among the project  members d) All of the mentioned

Last Answer : a) A single configuration management team for the whole  organization

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : )The critical element in a project's communication system is the: 1. Progress report * 2. Project directive  3. Project manager  4. Customer

Last Answer : 3. Project manager

Description : What is a project phase? A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)  B. A singular activity that completes a ... that has very similar parts D. A consistent period of time that is used throughout a project

Last Answer : A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)

Description : The accuracy of an estimate should: a. decrease as a project progresses through its life cycle. b. increase as a project progresses through its life cycle. c. stay constant throughout the project life cycle. d. vary independently of where the project is in its life cycle.

Last Answer : b. increase as a project progresses through its life cycle.

Description : The accuracy of an estimate should:  a. decrease as a project progresses through its life cycle.  b. increase as a project progresses through its life cycle.  c. stay constant throughout the project life cycle.  d. vary independently of where the project is in its life cycle.

Last Answer : b. increase as a project progresses through its life cycle.