Ahmed is actively initiating a project, so he plans to invite all relevant 

internal and external stakeholders including sponsors, customers, project 

teams, etc. for a kick-off meeting. To ensure all of them are covered in the 

stakeholder register, which document is the most helpful for Ahmed to 

look at?

Select one:

a. Project team activities

b. Scope statement

c. Project charter

d. Work packages

e. Project funding agents

1 Answer

Answer :

c. Project charter

Related questions

Description : Complete the following statement. As a project manager, Darrell is  excited that he is assigned to be in charge of the most important project  this year. After being chartered for the project, he ... c. prepare for the template to monitor project progress. d. estimate the entire project budget.

Last Answer : b. start to define and develop the stakeholder needs and requirements

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description : Which one of the following statements is true?  a. Independent reviews and quality audits form part of quality assurance to ensure the project  manager delivers on time and to budget. ... planning enables the project manager to manage the trade-off between customer  expectations and budget.

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for  purpose and meet stakeholder expectations.

Description : Complete the following statement. In a weak matrix environment, the  project manager, Eric, has to constantly make an effort to influence his  project team and stakeholders to ensure project success. ... managers. d. there are no functional managers. e. Eric has flexibility on authority.

Last Answer : b. Eric has no or little authority.

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : A Responsibility Assignment Matrix (RAM) can be used to:  a. define the terms of reference of the project manager.  b. define the limits of the project sponsor's responsibilities.  ... response activities to project personnel.  d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : ) One of the initial project documents, issued by senior management, which outlines the  authority of the project manager, is called Project charter. As a seller, what other document can  be used in this place: 1. Work breakdown structure  2. Project scope  3. Contract  4. Internal memo

Last Answer : 3. Contract

Description : Which of the following is true regarding the project charter? A. The project charter should be published under the name of a manager external to the project. B. The project charter should be ... project manager. D. The project charter should be published under the name of the project champion.

Last Answer : A. The project charter should be published under the name of a manager external to the project.

Description : The PM distributed a document to the stakeholders, which described the software to be  developed, the functionality, the users it would serve and the installation timeline. The document  was an example of: ... scope  4. It was not complete enough to be either a product or a project scope document

Last Answer : 4. It was not complete enough to be either a product or a project scope document

Description : A communication management plan identifies the relevant information that should be communicated to: a. the project team. b. the project stakeholders. c. the project board. d. the project sponsor.

Last Answer : b. the project stakeholders.

Description : A communication management plan identifies the relevant information that should be  communicated to:  a. the project team.  b. the project stakeholders.  c. the project board. d. the project sponsor.

Last Answer : b. the project stakeholders.

Description : What should be done by the project manager to ensure that all the work in the  project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.

Last Answer : c. Create a WBS.

Description : Project reporting can best be defined as: a. informing stakeholders about the project. b. storing and archiving of project information. c. gathering stakeholder feedback. d. collecting project information.

Last Answer : a. informing stakeholders about the project.

Description : Project reporting can best be defined as:  a. informing stakeholders about the project.  b. storing and archiving of project information. c. gathering stakeholder feedback.  d. collecting project information.

Last Answer : a. informing stakeholders about the project

Description : A project charter does not include ____ of the project. (A) scope (B) objectives (C) team (D) all above are included

Last Answer : (D) all above are included

Description : Fill in the blank. During the _________ of a project, the project manager focuses on  developing the project infrastructure needed to execute the project and developing  clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection

Last Answer : b. start-up

Description : Fill in the blank. During the _________ of a project, the project manager  focuses on developing the project infrastructure needed to execute the  project and developing clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection

Last Answer : b. start-up

Description :  The scope of the work is defined in which phase of the project management? (A) Initiating (B) Planning (C) Executing (D) Closing

Last Answer : (A) Initiating

Description : People participated in or affected by project activities are known as (A) staff (B) stakeholders (C) project team (D) project managers

Last Answer : (B) stakeholders

Description : Determining the policies that are needed for the smooth execution of a project  relates to which of the following agenda items of alignment sessions? Select one: a. Developing a common ... role clarification on projects e. Agreeing on the means and methods for accomplishing the purpose

Last Answer : d. Developing role clarification on projects

Description : Marco is an investor, and Jon is a project team member. Both have  intensive technical background for the project that you are managing.  However, recently they have disagreed on the next step to take ... b. Stakeholders c. The project team d. Investors e. The board of trustees of this company

Last Answer : c. The project team

Description : Who are project team members primarily accountable to? a. External stakeholders. b. The end users. c. The finance director. d. The project manager.

Last Answer : d. The project manager.

Description : Who are project team members primarily accountable to?  a. External stakeholders.  b. The end users.  c. The finance director.  d. The project manager.

Last Answer : d. The project manager.

Description : . A project leader or manager is expected to be completely accountable for his team  members and meeting the team’s targets. (True/False)

Last Answer : Ans. True

Description : According to the Project Management Institute (PMI), the scope statement should  address all of the following issues EXCEPT: Select one: a. project constraints. b. project assumptions c. project ... d. code of conduct for the team members working on the project. e. project deliverables.

Last Answer : d. code of conduct for the team members working on the project.

Description : )The engineer of the project in the planning phase and makes a significant contribution to the  technical scope. This is an example of what type of skill and knowledge? 1. Inherent  2. Stakeholder  3. Technical evaluation  4. Convergent thinking

Last Answer : 2. Stakeholder

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description : According to the PMBOK Guide, the project manager is identified and assigned  during which process?  A. Prior to beginning the Develop Project Charter process B. At the conclusion of the ... . Prior to beginning the Planning processes D. Prior to beginning the Preliminary Scope Statement process

Last Answer : C. Prior to beginning the Planning processes

Description : The conceptual estimate is developed with the least amount of knowledge. When  more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate

Last Answer : c. rough order of magnitude (ROM) estimate

Description : Fill in the blank. A __ represents the sequence of the activities needed to  complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change

Last Answer : c. project logic diagram

Description : According to the PMBOK guide, which of the following statements is  right in terms of using reserve analysis to determine a project budget? Select one: A. Reserve analysis always plans ... not practical. E. Contingency reserves have never been a concern when planning a project budget.

Last Answer : A. Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : A(n) _ is a review of the quality plan, procedures, data collection, and analysis by  an outside group. Select one: a. scope document b. project appraisal c. cost performance index d. analogous estimate e. quality audit

Last Answer : e. quality audit

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : .Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : Why are changes to the project scope necessary? Select one: a. To understand reports b. To reflect new information c. To begin planning the project d. To teach team members what they need to know about their jobs e. To establish a trusting project culture

Last Answer : b. To reflect new information

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : Which of the following is/are considered stakeholder in the process? a. Customers b. End-users c. Project managers d. All of the above.

Last Answer : d. All of the above.

Description : When a project manager starts to plan a new project budget, the cost  of which project management process group is expected to be lowest? Select one: a. Initiating b. Executing c. Monitoring and controlling d. Closing e. Planning

Last Answer : d. Closing

Description : A project planning methodology is any structured approach used to guide the project team  during development of the project plan. What is an example of this methodology? 1. Standard forms or templates.  2. Upper management involvement  3. Functional work authorizations 4. Stakeholders skills

Last Answer : 1. Standard forms or templates.

Description : ___ should be made of all cost factors so as to reflect on all relevant investment and  operational costs of the project including contingencies.

Last Answer : Ans. Realistic estimates

Description : Which of the following is true about management meetings? Select one: a. They are short meetings to develop a common understanding of what the short-term  priorities are for the project. ... , tracking progress of existing plans, and  making adjustments to plans in response to new information.

Last Answer : e. They are oriented toward developing plans, tracking progress of existing plans, and  making adjustments to plans in response to new information.

Description : Which one of the following best describes project success criteria? a. Actively seeking some senior management support. b. Measures by which the success of the project is judged. c. Achievement of milestones. d. A motivated project team.

Last Answer : b. Measures by which the success of the project is judged.