.Activity Definition is typically performed by which of the following:

A. Project Manager who created the WBS

B. Project Team Members responsible for the work package

C. Project Officer

D. Project Stakeholder

1 Answer

Answer :

B. Project Team Members responsible for the work package

Related questions

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : A prerequisite of effective time management is:  1. Knowing the dictated project completion date  2. Having the most advanced software package for project planning, scheduling and control  3. ... and the  person responsible for each of them  4. Having a well staffed scheduling department

Last Answer : 1. Knowing the dictated project completion date

Description : The basic approach to Earned Value is to A. Sum up the Work Package Earned Values to calculate the Earned Value of the Control  Account and ultimately the Project  B. Multiply the percent complete by ... that package  C. Estimate a percent complete for each WBS Work Package  D. All of the above

Last Answer : D. All of the above

Description : What should be done by the project manager to ensure that all the work in the  project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.

Last Answer : c. Create a WBS.

Description : Unlike traditional Work Breakdown Structures (WBS), evolutionary WBSs are  a. organized in a standard manner across all projects  b. created in an iterative and incremental manner  c. designed so one can compare the current project to past projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : Ahmed is actively initiating a project, so he plans to invite all relevant  internal and external stakeholders including sponsors, customers, project  teams, etc. for a kick-off meeting. To ensure all ... b. Scope statement c. Project charter d. Work packages e. Project funding agents

Last Answer : c. Project charter

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description : Complete the following statement. As a project manager, Darrell is  excited that he is assigned to be in charge of the most important project  this year. After being chartered for the project, he ... c. prepare for the template to monitor project progress. d. estimate the entire project budget.

Last Answer : b. start to define and develop the stakeholder needs and requirements

Description : Which one of the following statements is true?  a. Independent reviews and quality audits form part of quality assurance to ensure the project  manager delivers on time and to budget. ... planning enables the project manager to manage the trade-off between customer  expectations and budget.

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for  purpose and meet stakeholder expectations.

Description : To successfully manage a project, the PM must play both a manager and leadership role. In the manager role the PM will do all but which of the following: 1. Develop procedures  2. Align people  3. Produce results for stakeholder  4. Focus on the organization and its structure 5. Both b and d

Last Answer : 2. Align people

Description : Which one of the following statements is true? a. The business case is owned by the sponsor and is created during the concept phase of the project life  cycle. b. The business case is ... is owned by the project manager and is created during the definition phase of the  project life cycle.

Last Answer : a. The business case is owned by the sponsor and is created during the concept phase of the project life  cycle.

Description : Which one of the following statements is true? a. The business case is owned by the sponsor and is created during the concept phase of the  project life cycle.  b. The business case is ... is owned by the project manager and is created during the definition phase of the project life cycle.

Last Answer : a. The business case is owned by the sponsor and is created during the concept phase of the  project life cycle.

Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : Which one of the following best describes project management?  a. Using APM's Body of Knowledge 6th edition as a guide to all projects.  b. Employing a project manager who has undertaken ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : A project management information system consists of: 1. A project management software package operating on appropriate computer facilities  2. Hardware, software, documents, and procedures  3. Automated and ... of  pertinent information for members of a project team  4. All of the above

Last Answer : 4. All of the above

Description : Who are project team members primarily accountable to? a. External stakeholders. b. The end users. c. The finance director. d. The project manager.

Last Answer : d. The project manager.

Description : . A project leader or manager is expected to be completely accountable for his team  members and meeting the team’s targets. (True/False)

Last Answer : Ans. True

Description : The project manager works with the project sponsor to identify the necessary resources  and team members needed to further develop the key project parameters – Cost, Scope,  Schedule, and Quality (CSSQ). (True/False)

Last Answer : Ans. True

Description : Daniel has just been assigned as the project manager. To motivate his team properly,  Daniel’s first step is to award bonuses to team members

Last Answer : Ans: False

Description : You are the project manager for a cable service provider. Your team members are  amiable with each other and are careful to make project decisions jointly. Which of the  following statements is true?  ... stage of Develop Project Team. D. They are in the forcing stage of Develop Project Team.

Last Answer : B. They are in the norming stage of Develop Project Team.

Description : Who are project team members primarily accountable to?  a. External stakeholders.  b. The end users.  c. The finance director.  d. The project manager.

Last Answer : d. The project manager.

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : Alice is a Project Manager. She is coordinating a bidder conference to allow vendors to get clarification on the work that needs to be performed. Which phase of Project Management is in progress. A. Conduct Procurements B. Plan Procurements C. Control Procurements D. Close Procurements

Last Answer : A. Conduct Procurements

Description : Alice is a Project Manager. She is coordinating a bidder conference to allow vendors to get  clarification on the work that needs to be performed. Which phase of Project Management is in  progress. A. Conduct Procurements B. Plan Procurements C. Control Procurements D. Close Procurements

Last Answer : A. Conduct Procurements

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A) Technical key resources (B) Work key structure (C) Work Breakdown Structure (WBS). (D) None of the above

Last Answer : (C) Work Breakdown Structure (WBS).

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work  with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram

Last Answer : a. layered description

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A)Technical key resources (B)Work key structure (C)Work Breakdown Structure (WBS). (D)None of the above

Last Answer : (C)Work Breakdown Structure (WBS).

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  a. The life cycle phases.  b. The logical order of tasks.  c. The scope of the project.  d. Project costs

Last Answer : c. The scope of the project.

Description : After the celebration of the successful milestone completion, a project manager  will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.

Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.

Description : Which of the following makes up the project scope baseline?  A. The project scope statement B. The scope management plan and WBS C. The WBS, project scope statement, and WBS dictionary D. The scope management plan, the WBS, and the WBS dictionary

Last Answer : C. The WBS, project scope statement, and WBS dictionary

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : A Responsibility Assignment Matrix (RAM) can be used to:  a. define the terms of reference of the project manager.  b. define the limits of the project sponsor's responsibilities.  ... response activities to project personnel.  d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : Which one of the following best defines a benefit? a. A positive result of stakeholder management. b. The successful management of a project. c. An improvement resulting from project deliverables. d. The successful delivery of project reports and updates.

Last Answer : c. An improvement resulting from project deliverables.

Description : Which one of the following best describes a project stakeholder? a. A party who is concerned about the project going ahead. b. A party with an interest or role in the project or is impacted by ... of the project. d. A party who has a financial stake in the organization managing the project.

Last Answer : b. A party with an interest or role in the project or is impacted by the project.

Description : Project reporting can best be defined as: a. informing stakeholders about the project. b. storing and archiving of project information. c. gathering stakeholder feedback. d. collecting project information.

Last Answer : a. informing stakeholders about the project.

Description : Which of the following is/are considered stakeholder in the process? a. Customers b. End-users c. Project managers d. All of the above.

Last Answer : d. All of the above.

Description : Which one of the following best defines a benefit?  a. A positive result of stakeholder management.  b. The successful management of a project.  c. An improvement resulting from project deliverables. d. The successful delivery of project reports and updates.

Last Answer : c. An improvement resulting from project deliverables.

Description : Which one of the following best describes a project stakeholder?  a. A party who is concerned about the project going ahead.  b. A party with an interest or role in the project or is impacted by ... of the project.  d. A party who has a financial stake in the organisation managing the project.

Last Answer : b. A party with an interest or role in the project or is impacted by the project.

Description : Project reporting can best be defined as:  a. informing stakeholders about the project.  b. storing and archiving of project information. c. gathering stakeholder feedback.  d. collecting project information.

Last Answer : a. informing stakeholders about the project

Description : )The engineer of the project in the planning phase and makes a significant contribution to the  technical scope. This is an example of what type of skill and knowledge? 1. Inherent  2. Stakeholder  3. Technical evaluation  4. Convergent thinking

Last Answer : 2. Stakeholder