Description : Which technique is applicable when other projects in the same analogy application domain have been completed? a) Algorithmic cost modelling b) Expert judgement c) Estimation by analogy d) Parkinson’s Law
Last Answer : c) Estimation by analogy
Description : A is developed using historical cost information that relates some metric to the project cost. a) Algorithmic cost modelling b) Expert judgement c) Estimation by analogy d) Parkinson’s Law
Last Answer : a) Algorithmic cost modelling
Description : . Which of the following is empirical estimation technique? (i) expert judgement (ii) Delphi estimation (iii) COCOMO (iv) Critical path Method A. only i, ii & iii B. only i & ii C. only i, iii & iv D. All of the above
Last Answer : B. only i & ii
Description : Which of the following items should not be included in the project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development organisation, project responsibilities, managerial objectives and priorities e) None of the above.
Last Answer : c) The life cycle model to be used
Description : Integrated CASE tools are used to support tasks that happen throughout the SDLC.
Last Answer : Ans: True
Description : Lower CASE tools are used to create integrated diagrams of the system and store information about system components during the analysis phase.
Last Answer : Ans: False
Description : Upper CASE tools are used to create diagrams and generate code for database tables system functionality during the design phase.
Description : All of the following are true regarding the Qualitative Risk Analysis process except which one? A. Probability and impact and expert interview are used to help correct biases that occur in the data ... of this process used to determine which risks need near-term response plans.
Last Answer : C. Qualitative Risk Analysis is an easy method of determining risk probability and impact that usually takes a good deal of time to perform.
Description : Each component of the software product is separately estimated and the results aggregated to produce an estimate for the overall job. (A) Algorithmic model (B) Expert judgment (C) Bottom-up (D) Top down
Last Answer : (C) Bottom-up
Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A) Algorithmic model (B) Expert judgment (C) Top down (D) Analogy
Last Answer : (D) Analogy
Description : Each component of the product is separately estimated and the results aggregated to produce an estimate for the overall job. (A)Algorithmic model (B)Expert judgment (C)Bottom-up (D)Top down
Last Answer : (C)Bottom-up
Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A)Algorithmic model (B)Expert judgment (C)Top down (D)Analogy
Last Answer : (D)Analogy
Description : Mathematical models using linear, dynamic, integer, or algorithm models are considered A. Project selection criteria B. A form of expert judgment C. Project selection methods D. A form of historical information
Last Answer : C. Project selection methods
Description : The most successful project manager usually: 1. works their way up from assistants in the project office to full-fledged project managers, supplementing that experience with formal ... . Has considerable experience as a functional manager before moving into the project management arena.
Last Answer : 1. works their way up from assistants in the project office to full-fledged project managers, supplementing that experience
Description : )Which form of power is the LEAST effective from the project manager's viewpoint in terms of influencing functional managers? 1. Formal power 2. Expert power 3. Penalty power 4. Referent power
Last Answer : 3. Penalty power
Description : Expert power is the power that comes from the amount of knowledge a person has obtained in a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of expertise and also manage the project
Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of expertise and also manage the project
Description : Which of the following statements is true of Insured Asset Allocation? A. It is aimed at benefiting from short-term under pricing and over pricing of assets. B. In this strategy the risk ... . It is a strategy aimed at achieving the objectives of the investor without depending on market timing
Last Answer : E. It is a strategy aimed at achieving the objectives of the investor without depending on market timing.
Description : What is Digital Forensic? A. Process of using scientific knowledge in analysis and presentation of evidence in court B. The application of computer science and investigative procedures for a legal ... technology in the investigation and establishment of the facts or evidence in a court of law
Last Answer : B. The application of computer science and investigative procedures for a legal purpose involving the analysis of digital evidence after proper search authority, chain of custody, validation with mathematics, use of validated tools, repeatability, reporting, and possible expert presentation
Description : What is Digital Forensic? a. Process of using scientific knowledge in analysis and presentation of evidence in court b. The application of computer science and investigative procedures for a legal ... technology in the investigation and establishment of the facts or evidence in a court of law
Last Answer : b. The application of computer science and investigative procedures for a legal purpose involving the analysis of digital evidence after proper search authority, chain of custody, validation with mathematics, use of validated tools, repeatability, reporting, and possible expert presentation
Description : What is Digital Forensic? (A) Process of using scientific knowledge in analysis and presentation of evidence in court (B) The application of computer science and investigative procedures for a ... or technology in the investigation and establishment of the facts or evidence in a court of law
Last Answer : (B) The application of computer science and investigative procedures for a legal purpose involving the analysis of digital evidence after proper search authority, chain of custody, validation with mathematics, use of validated tools, repeatability, reporting, and possible expert presentation
Description : Fill in the blank. A __ represents the sequence of the activities needed to complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change
Last Answer : c. project logic diagram
Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram
Last Answer : a. layered description
Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of activities ... endeavor undertaken to achieve a desired outcome. d. A project is a method of planning work.
Last Answer : c. A unique transient endeavor undertaken to achieve a desired outcome.
Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of ... endeavour undertaken to achieve a desired outcome. d. A project is a method of planning work.
Last Answer : c. A unique transient endeavour undertaken to achieve a desired outcome.
Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited
Last Answer : d. compressed
Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against the potential benefit of the project’s success in order to decide if the project should be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation
Last Answer : e. initiation
Description : Fill in the blank. During the _________ of a project, the project manager focuses on developing the project infrastructure needed to execute the project and developing clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection
Last Answer : b. start-up
Description : Fill in the blank. Risk represents the likelihood that an event will happen during the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack
Last Answer : b. achievement
Description : Fill in the blanks. It is during the ______________ phase that the decision should be made regarding whether the project should continue. During this phase, ____________ must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk
Last Answer : e. initiation, risk
Description : Fill in the blank. The _____ is the difference between the additional money spent on prevention and the corresponding reduction in the cost of failure. Select one: a. cost-benefit analysis b. implicit cost c. cost of quality d. variable cost e. cost-utility analysis
Last Answer : c. cost of quality
Description : Fill in the blank. There is _______ correlation between project complexity and project risk. Select one: a. an unknown b. a positive c. no d. a negative e. a general
Last Answer : b. a positive
Description : According to the Project Management Institute (PMI), project management is defined as the application of knowledge, _____, _____, and techniques to project activities to meet the project requirements . Select ... b. tools, analysis c. analysis, theories d. skills, tools e. skills, theories
Last Answer : d. skills, tools
Description : Which model is used to compute the effort required to integrate reusable components or program code that is automatically generated by design or program translation tools? a) An application-composition model b) A post-architecture model c) A reuse model d) An early design model
Last Answer : c) A reuse model
Description : What combines procedures and tools to manage different versions of configuration objects that are created during the process? a) Change control b) Version control c) SCIs d) None of the mentioned
Last Answer : b) Version control
Description : Project management includes the tools, techniques, and essential to deal with the growth of products a. Knowledge b. Skill c. Attitude d. Confidence
Last Answer : a. Knowledge
Description : The most significant challenge to project managers is _____. a. lack of project management training b. no one really understands how to manage a complex systems development project ... tools that can assist in controlling project progress d. unrealistic schedule demands by project sponsors
Last Answer : d. unrealistic schedule demands by project sponsors
Description : Monte Carlo analysis can help predict the impact of risks on project deliverables. This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis
Last Answer : B. Quantitative Risk Analysis
Description : What Are The Tools Needed For A Project Management System?
Last Answer : A work definition policy and format, a scheduling procedure, a resource budgeting methodology and format, a real time data collection/reporting system, a material control and accountability subsystem, a ... control subsystem, and a monthly formal status review format to be used by senior management.
Description : What Are The Different Project Management Tools?
Last Answer : The different Project Management tools are MS Project, Templates, eBooks, flowcharts Compliant with PMBOK 4th Edition, EPOs (Electronic Project Offices) etc.
Description : Parkinson's Second Law?
Last Answer : Parkinson's Law, named for Cyril Northcote Parkinson, states that, ''Work expands so as to fill the time available for its completion.''. Of more concern in Personal Finance, however, is Parkinson's ... you will find that you took on new bills or financial obligations at the time of a pay increase.
Description : If a historian wanted to determine whether iron tools can be found in the ruins of an ancient African city which of expert should he consult?
Last Answer : An archaeologist.
Description : Suicide Hackers are those _________ a) who break a system for some specific purpose with or without keeping in mind that they may suffer long term imprisonment due to their malicious activity ... digital footprints d) who are employed in an organization to do malicious activities on other firms
Last Answer : a) who break a system for some specific purpose with or without keeping in mind that they may suffer long term imprisonment due to their malicious activity
Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms
Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.
Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.
Description : CASE tool is a popular graphic depiction of the work plan that lists project tasks along a y-axis, time along an x-axis, and uses shaded boxes to represent tasks.
Description : Ryan, a newly hired systems analyst/consultant, is about to begin a systems project. Where will Ryan look first to locate the identifiable tasks he will record in his work plan? a. ... . the project planning software available at the local bookstore e. the website of his old college professor
Last Answer : c. the company training materials for the company methodology