Which of the following states that work expands to fill the time 

available.

a) CASE tools

b) Pricing to win

c) Parkinson’s Law

d) Expert judgement

1 Answer

Answer :

c) Parkinson’s Law

Related questions

Description : Which technique is applicable when other projects in the same analogy application domain have been completed? a) Algorithmic cost modelling b) Expert judgement c) Estimation by analogy d) Parkinson’s Law

Last Answer : c) Estimation by analogy

Description : A is developed using historical cost information that relates  some metric to the project cost. a) Algorithmic cost modelling b) Expert judgement c) Estimation by analogy d) Parkinson’s Law

Last Answer : a) Algorithmic cost modelling

Description : . Which of the following is empirical estimation technique? (i) expert judgement (ii) Delphi estimation (iii) COCOMO (iv) Critical path Method A. only i, ii & iii B. only i & ii C. only i, iii & iv D. All of the above

Last Answer : B. only i & ii

Description : Which of the following items should not be included in the  project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development  organisation, project responsibilities, managerial  objectives and priorities e) None of the above.

Last Answer : c) The life cycle model to be used

Description : Integrated CASE tools are used to support tasks that happen throughout the SDLC.

Last Answer : Ans: True

Description : Lower CASE tools are used to create integrated diagrams of the system and store  information about system components during the analysis phase.

Last Answer : Ans: False

Description : Upper CASE tools are used to create diagrams and generate code for database tables  system functionality during the design phase.

Last Answer : Ans: False

Description : All of the following are true regarding the Qualitative Risk Analysis process except  which one?  A. Probability and impact and expert interview are used to help correct biases that occur  in the data ... of this process used to determine  which risks need near-term response plans.

Last Answer : C. Qualitative Risk Analysis is an easy method of determining risk probability and  impact that usually takes a good deal of time to perform.

Description : Each component of the software product is separately estimated and the results aggregated to produce an estimate for the overall job. (A) Algorithmic model (B) Expert judgment (C) Bottom-up (D) Top down

Last Answer : (C) Bottom-up

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A) Algorithmic model (B) Expert judgment (C) Top down (D) Analogy

Last Answer : (D) Analogy

Description : Each component of the product is separately estimated and the results aggregated to produce an estimate for the overall job. (A)Algorithmic model (B)Expert judgment (C)Bottom-up (D)Top down

Last Answer : (C)Bottom-up

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A)Algorithmic model (B)Expert judgment (C)Top down (D)Analogy

Last Answer : (D)Analogy

Description : Mathematical models using linear, dynamic, integer, or algorithm models are  considered  A. Project selection criteria B. A form of expert judgment C. Project selection methods D. A form of historical information

Last Answer : C. Project selection methods

Description : The most successful project manager usually: 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience with formal ... . Has considerable experience as a functional manager before moving into the project  management arena.

Last Answer : 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience

Description : )Which form of power is the LEAST effective from the project manager's viewpoint in terms of influencing functional managers? 1. Formal power  2. Expert power  3. Penalty power  4. Referent power

Last Answer : 3. Penalty power

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : Which of the following statements is true of Insured Asset Allocation? A. It is aimed at benefiting from short-term under pricing and over pricing of assets. B. In this strategy the risk ... . It is a strategy aimed at achieving the objectives of the investor without depending on market timing

Last Answer : E. It is a strategy aimed at achieving the objectives of the investor without depending on market timing.

Description : What is Digital Forensic? A. Process of using scientific knowledge in analysis and presentation of evidence in court B. The application of computer science and investigative procedures for a legal ... technology in the investigation and establishment of the facts or evidence in a court of law

Last Answer : B. The application of computer science and investigative procedures for a legal purpose involving the analysis of digital evidence after proper search authority, chain of custody, validation with mathematics, use of validated tools, repeatability, reporting, and possible expert presentation

Description : What is Digital Forensic? a. Process of using scientific knowledge in analysis and presentation of evidence in court b. The application of computer science and investigative procedures for a legal ... technology in the investigation and establishment of the facts or evidence in a court of law

Last Answer : b. The application of computer science and investigative procedures for a legal purpose involving the analysis of digital evidence after proper search authority, chain of custody, validation with mathematics, use of validated tools, repeatability, reporting, and possible expert presentation

Description : What is Digital Forensic? (A) Process of using scientific knowledge in analysis and presentation of evidence in court (B) The application of computer science and investigative procedures for a ... or technology in the investigation and establishment of the facts or evidence in a court of law

Last Answer : (B) The application of computer science and investigative procedures for a legal purpose involving the analysis of digital evidence after proper search authority, chain of custody, validation with mathematics, use of validated tools, repeatability, reporting, and possible expert presentation

Description : What is Digital Forensic? A. Process of using scientific knowledge in analysis and presentation of evidence in court B. The application of computer science and investigative procedures for a legal ... technology in the investigation and establishment of the facts or evidence in a court of law

Last Answer : B. The application of computer science and investigative procedures for a legal purpose involving the analysis of digital evidence after proper search authority, chain of custody, validation with mathematics, use of validated tools, repeatability, reporting, and possible expert presentation

Description : Fill in the blank. A __ represents the sequence of the activities needed to  complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change

Last Answer : c. project logic diagram

Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work  with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram

Last Answer : a. layered description

Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of activities ... endeavor undertaken to achieve a desired outcome. d. A project is a method of planning work.

Last Answer : c. A unique transient endeavor undertaken to achieve a desired outcome.

Description : Which one of the following statements best describes a project?  a. A project is a set of tools and techniques often used when delivering organisational change.  b. A project is the sum of ... endeavour undertaken to achieve a desired outcome.  d. A project is a method of planning work.

Last Answer : c. A unique transient endeavour undertaken to achieve a desired outcome.

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : Fill in the blank. During the _________ of a project, the project manager focuses on  developing the project infrastructure needed to execute the project and developing  clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection

Last Answer : b. start-up

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : Fill in the blank. The _____ is the difference between the additional money spent on  prevention and the corresponding reduction in the cost of failure. Select one: a. cost-benefit analysis b. implicit cost c. cost of quality d. variable cost e. cost-utility analysis

Last Answer : c. cost of quality

Description : Fill in the blank. There is _______ correlation between project complexity  and project risk. Select one: a. an unknown b. a positive c. no d. a negative e. a general

Last Answer : b. a positive

Description : Fill in the blank. During the _________ of a project, the project manager  focuses on developing the project infrastructure needed to execute the  project and developing clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection

Last Answer : b. start-up

Description : According to the Project Management Institute (PMI), project  management is defined as the application of knowledge, _____, _____, and  techniques to project activities to meet the project requirements . Select ... b. tools, analysis c. analysis, theories d. skills, tools e. skills, theories

Last Answer : d. skills, tools

Description : Which model is used to compute the effort required to  integrate reusable components or program code that is  automatically generated by design or program translation  tools? a) An application-composition model b) A post-architecture model c) A reuse model d) An early design model

Last Answer : c) A reuse model

Description : What combines procedures and tools to manage different versions of configuration objects that are created during the process? a) Change control b) Version control c) SCIs d) None of the mentioned

Last Answer : b) Version control

Description : Project management includes the tools, techniques, and essential to  deal with the growth of products a. Knowledge b. Skill c. Attitude d. Confidence

Last Answer : a. Knowledge

Description : The most significant challenge to project managers is _____.  a. lack of project management training  b. no one really understands how to manage a complex systems development project  ... tools that can assist in controlling project progress  d. unrealistic schedule demands by project sponsors

Last Answer : d. unrealistic schedule demands by project sponsors

Description : Monte Carlo analysis can help predict the impact of risks on project deliverables.  This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis

Last Answer : B. Quantitative Risk Analysis

Description : What Are The Tools Needed For A Project Management System?

Last Answer : A work definition policy and format, a scheduling procedure, a resource budgeting methodology and format, a real time data collection/reporting system, a material control and accountability subsystem, a ... control subsystem, and a monthly formal status review format to be used by senior management.

Description : What Are The Different Project Management Tools?

Last Answer : The different Project Management tools are MS Project, Templates, eBooks, flowcharts Compliant with PMBOK 4th Edition, EPOs (Electronic Project Offices) etc.

Description : Parkinson's Second Law?

Last Answer : Parkinson's Law, named for Cyril Northcote Parkinson, states that, ''Work expands so as to fill the time available for its completion.''. Of more concern in Personal Finance, however, is Parkinson's ... you will find that you took on new bills or financial obligations at the time of a pay increase.

Description : If a historian wanted to determine whether iron tools can be found in the ruins of an ancient African city which of expert should he consult?

Last Answer : An archaeologist.

Description : If a historian wanted to determine whether iron tools can be found in the ruins of an ancient African city which of expert should he consult?

Last Answer : An archaeologist.

Description : Suicide Hackers are those _________ a) who break a system for some specific purpose with or without keeping in mind that they may suffer long term imprisonment due to their malicious activity ... digital footprints d) who are employed in an organization to do malicious activities on other firms

Last Answer : a) who break a system for some specific purpose with or without keeping in mind that they may suffer long term imprisonment due to their malicious activity

Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.

Description : Which one of the following statements best defines an estimate?  a. An approximation of project time and cost targets, refined throughout the project life  cycle.  b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life  cycle.

Description : CASE tool is a popular graphic depiction of the work plan that lists project tasks along a y-axis, time along an x-axis, and uses shaded boxes to represent tasks.

Last Answer : Ans: False

Description : Ryan, a newly hired systems analyst/consultant, is about to begin a systems project.  Where will Ryan look first to locate the identifiable tasks he will record in his work plan?  a. ... . the project planning software available at the local bookstore  e. the website of his old college professor

Last Answer : c. the company training materials for the company methodology

Description : Did a legal expert say that the Trump win against the16 opponents is not a real win?