Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work 

with increasing detail in each layer.

Select one:

a. layered description

b. step change

c. ballpark estimate

d. project execution plan

e. project logic diagram

1 Answer

Answer :

a. layered description

Related questions

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description : Fill in the blank. A __ represents the sequence of the activities needed to  complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change

Last Answer : c. project logic diagram

Description : The conceptual estimate is developed with the least amount of knowledge. When  more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate

Last Answer : c. rough order of magnitude (ROM) estimate

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : Fill in the blank. During the _________ of a project, the project manager focuses on  developing the project infrastructure needed to execute the project and developing  clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection

Last Answer : b. start-up

Description : Fill in the blank. During the _________ of a project, the project manager  focuses on developing the project infrastructure needed to execute the  project and developing clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection

Last Answer : b. start-up

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A) Technical key resources (B) Work key structure (C) Work Breakdown Structure (WBS). (D) None of the above

Last Answer : (C) Work Breakdown Structure (WBS).

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A)Technical key resources (B)Work key structure (C)Work Breakdown Structure (WBS). (D)None of the above

Last Answer : (C)Work Breakdown Structure (WBS).

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  a. The life cycle phases.  b. The logical order of tasks.  c. The scope of the project.  d. Project costs

Last Answer : c. The scope of the project.

Description : The basic approach to Earned Value is to A. Sum up the Work Package Earned Values to calculate the Earned Value of the Control  Account and ultimately the Project  B. Multiply the percent complete by ... that package  C. Estimate a percent complete for each WBS Work Package  D. All of the above

Last Answer : D. All of the above

Description : What should be done by the project manager to ensure that all the work in the  project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.

Last Answer : c. Create a WBS.

Description : Unlike traditional Work Breakdown Structures (WBS), evolutionary WBSs are  a. organized in a standard manner across all projects  b. created in an iterative and incremental manner  c. designed so one can compare the current project to past projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : What is the first step in developing a risk management plan? Select one: a. Analyze the risks. b. Estimate the likelihood of the risks occurring. c. Identify potential project risks. d. Develop a risk mitigation plan. e. Estimate the potential impact of risk on the project goals.

Last Answer : c. Identify potential project risks.

Description : A Cost Breakdown Structure (CBS) shows costs assigned to: a. individual work packages using the Work Breakdown Structure (WBS). b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM). d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description :  A Cost Breakdown Structure (CBS) shows costs assigned to:  a. individual work packages using the Work Breakdown Structure (WBS).  b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM).  d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description : What Is A Work Breakdown Structure (wbs)?

Last Answer : The work breakdown structure defines the total project. A work breakdown structure is a product oriented, family tree composed of hardware elements, software elements, and service elements. The work ... the end product. The work breakdown structure is not an organization chart of company personnel.

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : Andrew has joined as the Project Manager of a project. One of the project documents  available to Andrew lists down all the risks in a hierarchical fashion. What is this document  called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : WBS is produced by identifying the key elements, breaking each element down into  component parts and continuing to breakdown until manageable work packages have been identified. (True/False)

Last Answer : Ans. True

Description : To identify the tasks for a work plan the project manager can _____.  a. control and direct the project  b. estimate the size, staff the project, and remember technical skills  c. establish a ... of the SDLC and the steps that occur in each  e. set conservative numbers for the project software

Last Answer : d. list the four phases of the SDLC and the steps that occur in each

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement

Description : Fill in the blank. There is _______ correlation between project complexity  and project risk. Select one: a. an unknown b. a positive c. no d. a negative e. a general

Last Answer : b. a positive

Description : To assist in budget control, it is suggested that the estimate occur at the _____ ____ ______  level of the WBS 1. Highest  2. Lowest  3. Major work effort  4. Third

Last Answer : 2. Lowest

Description : What is the most critical aspect in developing a project plan that meets project  specifications within the timeframe and at the lowest costs? Select one: a. Assessing risk management b ... business partners e. Developing a project execution plan that matches the complexity level of the project

Last Answer : e. Developing a project execution plan that matches the complexity level of the project

Description : The Scope Management Plan is included in which of the following documents. 1. Project Plan  2. The Work Breakdown Structure  3. The Scope Statement  4. Project Specifications

Last Answer : 3. The Scope Statement

Description : Traditional Work Breakdown Structures tend to  a. focus on the design of the system as oppose to the needs of the current phase and  iteration  b. force too many levels of detail early on for large ... project and difficult to compare across projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : A(n) _ is a review of the quality plan, procedures, data collection, and analysis by  an outside group. Select one: a. scope document b. project appraisal c. cost performance index d. analogous estimate e. quality audit

Last Answer : e. quality audit

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Which of the following makes up the project scope baseline?  A. The project scope statement B. The scope management plan and WBS C. The WBS, project scope statement, and WBS dictionary D. The scope management plan, the WBS, and the WBS dictionary

Last Answer : C. The WBS, project scope statement, and WBS dictionary

Description :  According to PMBOK, project management process groups are iterative, which  was originally defined by Walter Shewhart and later modified by Edward Deming.  Generally, one outcome from a previous process can serve ... -Do-Check-Act cycle c. Project phases d. PM processes e. HR process cycle

Last Answer : b. Plan-Do-Check-Act cycle

Description : The justification for the investment to be made in a project is documented in the: a. Cost Breakdown Structure. b. procurement strategy. c. business case. d. Project Management Plan.

Last Answer : c. business case.

Description : The justification for the investment to be made in a project is documented in the:  a. Cost Breakdown Structure.  b. procurement strategy.  c. business case.  d. Project Management Plan

Last Answer : c. business case.

Description : Fill in the blank. The _____ is the difference between the additional money spent on  prevention and the corresponding reduction in the cost of failure. Select one: a. cost-benefit analysis b. implicit cost c. cost of quality d. variable cost e. cost-utility analysis

Last Answer : c. cost of quality

Description : Each item of the Work Breakdown Structure is assigned a unique identifier. What is the name  of this identifier? 1. Product ID number  2. Code of accounts  3. Quality inspection identifier  4. Project activity code

Last Answer : 2. Code of accounts

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : A prerequisite of effective time management is:  1. Knowing the dictated project completion date  2. Having the most advanced software package for project planning, scheduling and control  3. ... and the  person responsible for each of them  4. Having a well staffed scheduling department

Last Answer : 1. Knowing the dictated project completion date

Description :  A project budget estimate that is developed with the least amount of  knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate

Last Answer : c. Conceptual estimate

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package