All of the following are true regarding the Qualitative Risk Analysis process except 

which one? 

A. Probability and impact and expert interview are used to help correct biases that occur 

in the data you’ve gathered during this process.

B. The probability and impact matrix is used during this process to assign red, yellow, and

green conditions to risks.

C. Qualitative Risk Analysis is an easy method of determining risk probability and 
impact that usually takes a good deal of time to perform.
D. Risk urgency assessment is a tool and technique of this process used to determine 
which risks need near-term response plans.

1 Answer

Answer :

C. Qualitative Risk Analysis is an easy method of determining risk probability and 

impact that usually takes a good deal of time to perform.

Related questions

Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis

Last Answer : c. Perform Qualitative risk analysis

Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis

Last Answer : c. Perform Qualitative risk analysis

Description : Monte Carlo analysis can help predict the impact of risks on project deliverables.  This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis

Last Answer : B. Quantitative Risk Analysis

Description : The process of assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes ... Risk Analysis B. Risk Identification C. Qualitative Risk Analysis D. Risk Management Planning

Last Answer : C. Qualitative Risk Analysis

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : Each of the following statements is true regarding the risk management plan except  for which one?  A. The risk management plan is an output of the Risk Management Planning process. B. The risk ... and budgets. D. The risk management plan is an input to all the remaining risk-planning processes.

Last Answer : B. The risk management plan includes a description of the responses to risks and  triggers.

Description : All of the following statements are true regarding risk events except which one?  Choose the least correct answer. A. Project risks are uncertain events.  B. If risks occur, they can ... that have more perceived rewards to the organization than the consequences of  the risk should be accepted.

Last Answer : C. Unknown risks are threats to the project objectives, and nothing can be done to  plan for them.

Description : Which of the following processes assesses the likelihood of risk occurrences and their consequences using a numerical rating? A. Qualitative Risk Analysis B. Risk Identification C. Quantitative Risk Analysis D. Risk Response Planning

Last Answer : C. Quantitative Risk Analysis

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Which of the following is not the part of Risk Control  A. Execution of the risk response strategy  B. Monitoring of triggering events  C. Initiating contingency plans  D. Not watching for new risks

Last Answer : D. Not watching for new risks

Description : Which of the following is true about management meetings? Select one: a. They are short meetings to develop a common understanding of what the short-term  priorities are for the project. ... , tracking progress of existing plans, and  making adjustments to plans in response to new information.

Last Answer : e. They are oriented toward developing plans, tracking progress of existing plans, and  making adjustments to plans in response to new information.

Description : All of the following statements are true regarding risks except for which one? Choose the least correct answer.  A. Risks might be threats to the objectives of the project.  B. Risks are ... Risks might be opportunities to the objectives of the project.  D. Risks have causes and consequences.

Last Answer : B. Risks are certain events that may be threats or opportunities to the objectives of  the project

Description : The main outcome of risk identification, in a risk management process, is to: a. identify and determine the relative importance of the project risks. b. identify and describe all risks that ... responses to the project risks. d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : The main outcome of risk identification, in a risk management process, is to:  a. identify and determine the relative importance of the project risks.  b. identify and describe all risks that ... to the project risks.  d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : Asking the patient questions to determine if the person understands the health teaching provided would be included during which step of the nursing process? a) Evaluation Evaluation includes observing ... ) Implementation Implementation is the step during which the teaching plan is put into action.

Last Answer : a) Evaluation Evaluation includes observing the person, asking questions, and comparing the patient’s behavioral responses with the expected outcomes.

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : )The total amount of risk that is calculated for a project is found by 1. Multiplying the sum of each the risk times the amount at stake 2. Calculating the cumulative sum of the probability for ... 3. Cannot be calculated since all risks are not know  4. The amount of project reserves available

Last Answer : 2. Calculating the cumulative sum of the probability for each risk and multiplying this value times the consequence of occurrence of the risk events

Description : What is the first step in developing a risk management plan? Select one: a. Analyze the risks. b. Estimate the likelihood of the risks occurring. c. Identify potential project risks. d. Develop a risk mitigation plan. e. Estimate the potential impact of risk on the project goals.

Last Answer : c. Identify potential project risks.

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : A Responsibility Assignment Matrix (RAM) can be used to:  a. define the terms of reference of the project manager.  b. define the limits of the project sponsor's responsibilities.  ... response activities to project personnel.  d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : The process of identifying the probability of occurrence of a natural hazard of a given intensity at a specific location based on an analysis of natural processes and site conditions is termed as- (a) Disaster calculation (b) Hazard Assessment (c) Hazard calculation (d) None of the above

Last Answer : (b) Hazard Assessment

Description : The term ‘phenomenology’ is associated with the process of (A) Qualitative Research (B) Analysis of Variance (C) Correlational Study (D) Probability Sampling

Last Answer : (A) Qualitative Research

Description : Which of the following is most likely to be a response to the auditor's assessment that the risk of material misstatement due to fraud for the existence of inventory is high? a. Observe test counts ... be counted on different dates so as to allow the same auditor to be present at every count

Last Answer : Observe test counts of inventory at certain locations on an unannounced basis.

Description : According to the PMBOK guide which of the following statements is right in terms  of using reserve analysis to determine a project budget ? a. Reserve analysis always plans contingency reserves ... not practical. e. Contingency reserves have never been a concern when planning a project budget.

Last Answer : . Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : According to the PMBOK guide, which of the following statements is  right in terms of using reserve analysis to determine a project budget? Select one: A. Reserve analysis always plans ... not practical. E. Contingency reserves have never been a concern when planning a project budget.

Last Answer : A. Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : The main aim of a project risk management process should be to: a. identify project risks and then manage them appropriately. b. identify all project risks and transfer them immediately. c ... are threats or opportunities on a project. d. satisfy the organization's project management process.

Last Answer : a. identify project risks and then manage them appropriately.

Description : The main aim of a project risk management process should be to:  a. identifies project risks and then manage them appropriately.  b. identify all project risks and transfer them immediately.  ... are threats or opportunities on a project.  d. satisfy the organisation's project management process.

Last Answer : a. identifies project risks and then manage them appropriately.

Description : Which skill needed by the nurse to think critically involves identification of patient problems indicated by data? a) Analysis Analysis is used to identify patient problems indicated by data. b) ... or interventions used to address patient problems and to help a patient move toward desired outcomes.

Last Answer : a) Analysis Analysis is used to identify patient problems indicated by data.

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.

Description : Which of the following statements is true of Insured Asset Allocation? A. It is aimed at benefiting from short-term under pricing and over pricing of assets. B. In this strategy the risk ... . It is a strategy aimed at achieving the objectives of the investor without depending on market timing

Last Answer : E. It is a strategy aimed at achieving the objectives of the investor without depending on market timing.

Description : Estimates from the planning stage will need to be refined as the project progresses,  because it is virtually impossible to develop an exact assessment of the project’s schedule  before the analysis and design phases are conducted.

Last Answer : Ans: True

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A) Algorithmic model (B) Expert judgment (C) Top down (D) Analogy

Last Answer : (D) Analogy

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A)Algorithmic model (B)Expert judgment (C)Top down (D)Analogy

Last Answer : (D)Analogy

Description : Qualitative research is often exploratory and has all of the following characteristics except: a. It is typically used when a great deal is already known about the topic of interest b. It ... hypotheses and develop theory about phenomena in the world d. It uses the inductive scientific method

Last Answer : a. It is typically used when a great deal is already known about the topic of interest

Description : Which technique is applicable when other projects in the same analogy application domain have been completed? a) Algorithmic cost modelling b) Expert judgement c) Estimation by analogy d) Parkinson’s Law

Last Answer : c) Estimation by analogy

Description : In project management, which of the following is NOT a method of reducing the impact of an unexpected event? (A) Risk avoidance (B) Risk sharing (C) Risk transfer (D) Risk elimination

Last Answer : D) Risk elimination

Description : Following is (are) the component(s) of risk management (A)Risk Assessment (B)Risk Control (C)Risk Ranking (D)All of the above

Last Answer : (D)All of the above

Description : A risk is defined as what might happened to the ____________ of the project 1. assessment  2. detriment  3. schedule  4. cost  5. scope

Last Answer : 2. detriment

Description : The process of assigning values for the time and effort needed to perform a system  project is called _____.  a. analysis  b. estimation  c. identifying  d. planning

Last Answer : b. estimation

Description : An example of the risk involved in development is a) Key personnel may resign before the product is complete b) The manufacturer of critical components (e.g. the hardware  associated with a ... a fully functional lower-cost  equivalent package e) All of these are risks involved in development.

Last Answer : e) All of these are risks involved in development.

Description : )Which of the following fit the category of external risks? 1. Project delays, budget under-runs, movement of city utilities  2. Regulatory, currency changes, taxation  3. Natural disasters, ... , design, social impact  5. Political unrest, budget overruns, size and complexity of the project

Last Answer : 2. Regulatory, currency changes, taxation

Description : Which one of the following statements best describes the use of an issue log? a. A summary of all possible alternative resolutions of an issue. b. A summary of all the project issues, their ... for capturing all issues. d. A tool to ensure that the issue management process is adhered to.

Last Answer : b. A summary of all the project issues, their analysis and status.

Description : Which one of the following statements best describes the use of an issue log?  a. A summary of all possible alternative resolutions of an issue.  b. A summary of all the project issues, their ... for capturing all issues.  d. A tool to ensure that the issue management process is adhered to.

Last Answer : b. A summary of all the project issues, their analysis and status.

Description : Which of the following is the task of a Test Lead / Leader: i. Interaction with the Test Tool Vendor to identify best ways to leverage test tool on the project. ii. Write Test Summary Reports based on the ... is true and ii,iii,iv are false d) iii and iv is correct and i and ii are incorrect

Last Answer : a) i, ii, iii is true and iv is false

Description : Which one of the following statements about the project risk register is false? a. It facilitates the review and monitoring of risks. b. It facilitates the risk appetite. c. It facilitates the recording of risk responses. d. It facilitates the recording of risks.

Last Answer : b. It facilitates the risk appetite.

Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : Andrew has joined as the Project Manager of a project. One of the project documents  available to Andrew lists down all the risks in a hierarchical fashion. What is this document  called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : Which one of the following statements about the project risk register is false?  a. It facilitates the review and monitoring of risks.  b. It facilitates the risk appetite.  c. It facilitates the recording of risk responses.  d. It facilitates the recording of risks

Last Answer : b. It facilitates the risk appetite