Which one of the following statements is true?

a. Business-as-usual activities cannot be improved.

b. Business-as-usual activities are more difficult to manage than projects.

c. Projects are transient endeavours that bring about change to business-as-usual.

d. A project is always the starting point for operation refinement

1 Answer

Answer :

c. Projects are transient endeavours that bring about change to business-as-usual.

Related questions

Description : Which one of the following statements is true?  a. Business-as-usual activities cannot be improved.  b. Business-as-usual activities are more difficult to manage than projects.  c. Projects are ... change to business-as-usual.  d. A project is always the starting point for operation refinement.

Last Answer : c. Projects are transient endeavours that bring about change to business-as-usual

Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of activities ... endeavor undertaken to achieve a desired outcome. d. A project is a method of planning work.

Last Answer : c. A unique transient endeavor undertaken to achieve a desired outcome.

Description : Which one of the following statements best describes a project?  a. A project is a set of tools and techniques often used when delivering organisational change.  b. A project is the sum of ... endeavour undertaken to achieve a desired outcome.  d. A project is a method of planning work.

Last Answer : c. A unique transient endeavour undertaken to achieve a desired outcome.

Description : Which of the following statements is true regarding contracts? Select one: a. They are the filters through which project members screen information that is shared. b. They do not lend ... information-rich  environment will suffer. e. Contracts promote the growth of a trusting project culture.

Last Answer : b. They do not lend themselves to create an environment of trust.

Description : Traditional Work Breakdown Structures tend to  a. focus on the design of the system as oppose to the needs of the current phase and  iteration  b. force too many levels of detail early on for large ... project and difficult to compare across projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : Which one of the following is a responsibility of the project steering group/board? a. To identify potential problems for the project team to solve. b. To provide strategic direction and guidance ... project team in all daily activities. d. To receive and consider daily reports from team members.

Last Answer : b. To provide strategic direction and guidance to the sponsor.

Description : Which one of the following is a responsibility of the project steering group/board?  a. To identify potential problems for the project team to solve.  b. To provide strategic direction and ... project team in all daily activities. d. To receive and consider daily reports from team members.

Last Answer : b. To provide strategic direction and guidance to the sponsor.

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description : Which one of the following statements is true?  a. Independent reviews and quality audits form part of quality assurance to ensure the project  manager delivers on time and to budget. ... planning enables the project manager to manage the trade-off between customer  expectations and budget.

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for  purpose and meet stakeholder expectations.

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : A ____ of activities that are used to achieve the project’s goals or objectives is known as  the project life cycle.

Last Answer : Ans. Rational order

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.

Description : Identify, from among the following, the correct statement. a) One of the main challenges Engineering facing today is the requirement of most systems to work with a multitude of  homogenous systems ... of component based assembly, we find  that onlyless than 20% of today's is still custom built

Last Answer : c) does not wear-out in the traditional sense of the term, but  does tend to deteriorate as it evolves

Description : Which of the following statements is incorrect regarding a normal project? A. If the NPV of a project is greater than 0, then its PI will exceed 1. B. If the IRR of a project is 8%, its NPV, using ... the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Last Answer : D. If the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated.

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : Something is always................each time the activities of a project are repeated. a. Different b. Same c. Various d. None of the above

Last Answer : a. Different

Description : Which one of the following statements best defines procurement? a. A technique to establish the best approach for obtaining the resources for the project. b. A group of interrelated resources and ... product. d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : Which one of the following statements best defines procurement?  a. A technique to establish the best approach for obtaining the resources for the project.  b. A group of interrelated resources and ... product.  d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : Which one of the following statements is true? a. The business case is owned by the sponsor and is created during the concept phase of the project life  cycle. b. The business case is ... is owned by the project manager and is created during the definition phase of the  project life cycle.

Last Answer : a. The business case is owned by the sponsor and is created during the concept phase of the project life  cycle.

Description : Which one of the following statements is true? a. The business case is owned by the sponsor and is created during the concept phase of the  project life cycle.  b. The business case is ... is owned by the project manager and is created during the definition phase of the project life cycle.

Last Answer : a. The business case is owned by the sponsor and is created during the concept phase of the  project life cycle.

Description : It is often difficult to estimate size at an early stage in a project  when only a specification is available a) True b) False

Last Answer : a) True

Description : A profitability index (PI) of .92 for a project means that . A. The project's costs (cash outlay) are (is) less than the present value of the project's benefits B. The project's NPV is ... is greater than 1 D. The project returns 92 cents in present value for each current rupee invested (cost)

Last Answer : C. The project's NPV is greater than 1

Description : The main aim of a project risk management process should be to: a. identify project risks and then manage them appropriately. b. identify all project risks and transfer them immediately. c ... are threats or opportunities on a project. d. satisfy the organization's project management process.

Last Answer : a. identify project risks and then manage them appropriately.

Description : A ____ needs to possess excellent analytical and organizational skills to manage a project team

Last Answer : Ans. Project Manager

Description : A critical success factor for project management is to _____.  a. create a work plan  b. follow the three steps of project management  c. identify most project tasks  d. manage the hundreds of tasks

Last Answer : e. start with a realistic assessment of the work

Description : The most significant challenge to project managers is _____.  a. lack of project management training  b. no one really understands how to manage a complex systems development project  ... tools that can assist in controlling project progress  d. unrealistic schedule demands by project sponsors

Last Answer : d. unrealistic schedule demands by project sponsors

Description :  . Integrity in the project management field is accomplished through all of the  following except which one?  A. Training to learn how to manage relationships with others from different ... C. Applying established project management processes D. Following the PMP Code of Professional Conduct

Last Answer : A. Training to learn how to manage relationships with others from different cultures

Description : The main aim of a project risk management process should be to:  a. identifies project risks and then manage them appropriately.  b. identify all project risks and transfer them immediately.  ... are threats or opportunities on a project.  d. satisfy the organisation's project management process.

Last Answer : a. identifies project risks and then manage them appropriately.

Description : To successfully manage a project, the PM must play both a manager and leadership role. In the manager role the PM will do all but which of the following: 1. Develop procedures  2. Align people  3. Produce results for stakeholder  4. Focus on the organization and its structure 5. Both b and d

Last Answer : 2. Align people

Description : Which of the following is true about management meetings? Select one: a. They are short meetings to develop a common understanding of what the short-term  priorities are for the project. ... , tracking progress of existing plans, and  making adjustments to plans in response to new information.

Last Answer : e. They are oriented toward developing plans, tracking progress of existing plans, and  making adjustments to plans in response to new information.

Description : The hurricane model implies that project estimates become more accurate as the  project's product becomes better understood.

Last Answer : Ans: True

Description : A project whose acceptance requires the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project B. an independent project C. a dependent project D. None of the above

Last Answer : B. an independent project

Description : A project whose acceptance precludes the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project. D. a contingent project.

Last Answer : A. a mutually exclusive project.

Description : A project whose acceptance requires the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project E. none of the above

Last Answer : A. a mutually exclusive project.

Description : A project whose acceptance precludes the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project

Last Answer : C. a dependent project

Description : A project whose acceptance requires the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project E. none of the above

Last Answer : A. a mutually exclusive project.

Description : A project whose acceptance precludes the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project

Last Answer : C. a dependent project

Description : Fill in the blank. A __ represents the sequence of the activities needed to  complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change

Last Answer : c. project logic diagram

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A) Algorithmic model (B) Expert judgment (C) Top down (D) Analogy

Last Answer : (D) Analogy

Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : An Organizational Breakdown Structure (OBS) is used to identify: a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of communication ... . d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.