In a project schedule, the sequence of activities which cannot be delayed during the 

course of the project without extending the project end date is referred to as the: 

A. Action plan

B. Critical path

C. Schedule baseline

D. Slack line

1 Answer

Answer :

B. Critical path

Related questions

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : Which of the following is displayed as an S curve?  A. Gantt B. Cost baseline C. Critical path D. Schedule baseline

Last Answer : B. Cost baseline

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : Which of the following project baselines provides the basis for measurement of  the expected cash flow against requirements over time and is often displayed as an  S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline

Last Answer : b. Cost performance baseline

Description : The Scope Baseline is: 1. the original description of the project's end results  2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data 3. the original project budget and schedule  4. a and c

Last Answer : 2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.  B. ... approach that combines the scope and cost baseline into a project performance and  progress measurement tool.

Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : The network diagram is the best tool for demonstrating:  A. Schedule variances B. Resource requirements C. The sequence of project activities  D. Schedule performance over time

Last Answer : C. The sequence of project activities

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : Which of the following makes up the project scope baseline?  A. The project scope statement B. The scope management plan and WBS C. The WBS, project scope statement, and WBS dictionary D. The scope management plan, the WBS, and the WBS dictionary

Last Answer : C. The WBS, project scope statement, and WBS dictionary

Description : To crash a schedule you should: 1. Increase the time allowed on those tasks that have float.  2. Try to increase expenditures of time only those tasks that are behind schedule.  3. Replace those ... to par with the busy.  4. Increase work efforts on those tasks that are on the critical path.

Last Answer : 4. Increase work efforts on those tasks that are on the critical path.

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : All activities lying on critical path have slack time equal to (A) 0 (B) 1 (C) 2 (D) None of above

Last Answer : (A) 0

Description :  The project team has just determined that the deadline for completion will not be met.  In order to deliver a high quality system on schedule, the team has requested that the  features be ... that a fixed deadline be imposed for the project. This technique  is referred to as SDLC methodology.

Last Answer : Ans: False

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : ............................ is the sequence of activities which determines the total project duration. a. Critical path b. Network c. Non-critical activities d. None of these

Last Answer : a. Critical path

Description : Work that continues throughout the project and does not relate to  any specific phase of development is termed a(n) a) Milestone b) Project function c) Activity d) Task e) Baseline.

Last Answer : b) Project function

Description :  A time-phased budget that project managers use to measure and monitor cost performance. A. Cost Baseline B. Cost Budgeting C. Cost Estimating D. Cost Variance

Last Answer : A. Cost Baseline

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : While assessing your project processes, you have identified some  uncontrolled process variations. Which of the following would be the  appropriate chart you may use for this purpose? Select one: a. Pareto diagram b. PERT chart c. Control chart d. HR personnel chart e. Critical path

Last Answer : c. Control chart

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description : . An important aim of a post-project review is to: a. validate overall progress to date against the budget and schedule. b. capture learning and document it for future usage. c. ... of all permanent documentation, signed by the sponsor. d. establish that project benefits have been identified.

Last Answer : b. capture learning and document it for future usage.

Description : You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D ... .  A. Crashing B. fast tracking C. resource leveling D. adjusting the resource calendar

Last Answer : A. Crashing

Description : An important aim of a post-project review is to:  a. validate overall progress to date against the budget and schedule.  b. capture learning and document it for future usage.  c. ... of all permanent documentation, signed by the sponsor.  d. establish that project benefits have been identified

Last Answer : b. capture learning and document it for future usage.

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities

Description : The critical path  A. Is a path that operates from the starting node to the end node  B. Is a mixture of all paths.  C.Is the longest path  D.Is the shortest path

Last Answer : C.Is the longest path

Description : Which of the following does NOT generate changes to the Project documents: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations

Last Answer : A. Define Activities

Description : Fill in the blank. A __ represents the sequence of the activities needed to  complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change

Last Answer : c. project logic diagram

Description : A project includes a number of activities that must be completed in some ………… a. particular order b. sequence c. both d. all the above

Last Answer : d. all the above

Description : A project is a sequence of a. Unique b. Complex c. connected activities d. all the above

Last Answer : d. all the above

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description : The project schedule is used to determine all of the following except which one?  A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

Last Answer : A. Cost estimates

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : What is the most critical aspect in developing a project plan that meets project  specifications within the timeframe and at the lowest costs? Select one: a. Assessing risk management b ... business partners e. Developing a project execution plan that matches the complexity level of the project

Last Answer : e. Developing a project execution plan that matches the complexity level of the project

Description : A critical success factor for project management is to _____.  a. create a work plan  b. follow the three steps of project management  c. identify most project tasks  d. manage the hundreds of tasks

Last Answer : e. start with a realistic assessment of the work

Description : According to Olivier Mesly, the 4 P’s critical for the success of a project are: (A) plan, processes, people, policy (B) plan, processes, people, power (C) plan, processes, potential, policy (D) plan, processes, potential, power

Last Answer : (B) plan, processes, people, power

Description : Your upcoming project includes project team members from a foreign country. To  make certain that cultural differences don't interfere with team performance, thereby  affecting the success of the project ... exercises.  D. Inform the team members of the organization's rules and standards.

Last Answer : A. Provide diversity training to all the team members.

Description :  A project budget estimate that is developed with the least amount of  knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate

Last Answer : c. Conceptual estimate

Description : Which one of the following statements is true? a. Business-as-usual activities cannot be improved. b. Business-as-usual activities are more difficult to manage than projects. c. Projects are ... change to business-as-usual. d. A project is always the starting point for operation refinement

Last Answer : c. Projects are transient endeavours that bring about change to business-as-usual.