Traditional Work Breakdown Structures tend to 

a. focus on the design of the system as oppose to the needs of the current phase and 

iteration 

b. force too many levels of detail early on for large project and they tend to 

allow too few level of detail for small projects 

c. be too specific for the project and difficult to compare across projects 

d. all of the above 

e. none of the above

1 Answer

Answer :

d. all of the above

Related questions

Description : Unlike traditional Work Breakdown Structures (WBS), evolutionary WBSs are  a. organized in a standard manner across all projects  b. created in an iterative and incremental manner  c. designed so one can compare the current project to past projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : The traditional Work Breakdown Structure makes it easy to compare the current  project with past projects.

Last Answer : Ans: False

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Identify, from among the following, the correct statement. a) One of the main challenges Engineering facing today is the requirement of most systems to work with a multitude of  homogenous systems ... of component based assembly, we find  that onlyless than 20% of today's is still custom built

Last Answer : c) does not wear-out in the traditional sense of the term, but  does tend to deteriorate as it evolves

Description : An Organizational Breakdown Structure (OBS) is used to identify: a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of communication ... . d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : An Organisational Breakdown Structure (OBS) is used to identify:  a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of ... project. d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work  with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram

Last Answer : a. layered description

Description : The evolutionary Work Breakdown Structure makes it easy to compare the current  project with past project

Last Answer : Ans: True

Description : Alice is a Project Manager. She is coordinating a bidder conference to allow vendors to get clarification on the work that needs to be performed. Which phase of Project Management is in progress. A. Conduct Procurements B. Plan Procurements C. Control Procurements D. Close Procurements

Last Answer : A. Conduct Procurements

Description : Alice is a Project Manager. She is coordinating a bidder conference to allow vendors to get  clarification on the work that needs to be performed. Which phase of Project Management is in  progress. A. Conduct Procurements B. Plan Procurements C. Control Procurements D. Close Procurements

Last Answer : A. Conduct Procurements

Description : A Project control system: 1. Monitors and controls the project's schedule, costs, scope, budgets etc  2. Is a mechanism which reacts to the current project status in order to endure ... 4. Is a system for controlling and executing project documentation in an uniform and timely  manner

Last Answer : 1. Monitors and controls the project's schedule, costs, scope, budgets etc

Description : Which one of the following statements is true? a. Business-as-usual activities cannot be improved. b. Business-as-usual activities are more difficult to manage than projects. c. Projects are ... change to business-as-usual. d. A project is always the starting point for operation refinement

Last Answer : c. Projects are transient endeavours that bring about change to business-as-usual.

Description : Which one of the following statements is true?  a. Business-as-usual activities cannot be improved.  b. Business-as-usual activities are more difficult to manage than projects.  c. Projects are ... change to business-as-usual.  d. A project is always the starting point for operation refinement.

Last Answer : c. Projects are transient endeavours that bring about change to business-as-usual

Description : The traditional Work Breakdown Structure approach is very useful when the  requirements of the system are not well understood.

Last Answer : Ans: False

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : Estimates from the planning stage will need to be refined as the project progresses,  because it is virtually impossible to develop an exact assessment of the project’s schedule  before the analysis and design phases are conducted.

Last Answer : Ans: True

Description : A mean for monitoring and controlling organization's strategic projects is A. Project Monitoring process B. Project Portfolio Process C. Project Portfolio Plan D. Project Portfolio Phase

Last Answer : B. Project Portfolio Process

Description : It is often difficult to estimate size at an early stage in a project  when only a specification is available a) True b) False

Last Answer : a) True

Description : . It is not wise to identify tasks for a current project using existing methodology,  because methodologies that have been used by an organization for other projects probably will not work for this project without extensive changes.

Last Answer : Ans: False

Description : The most successful project manager usually: 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience with formal ... . Has considerable experience as a functional manager before moving into the project  management arena.

Last Answer : 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience

Description : The answer is: (A) related projects The leadership style where focus is on relationships and community rather than exercising of  power, is termed as (A) laissez-faire (B) interactional leadership (C) servant leadership (D) oligarchy

Last Answer : (C) servant leadership

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : The conceptual estimate is developed with the least amount of knowledge. When  more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate

Last Answer : c. rough order of magnitude (ROM) estimate

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description : One of the greatest weaknesses of systems consulting firms is that they try to apply  estimates and methodologies that they have developed over time and applied to other  projects, most of which are very different from the current project.

Last Answer : Ans: False

Description : "How will conflicts over resources/facility usage between this and other projects be settled?", is critically settled at level A. Main program B. Project formation C. Project Buildup D. Project Buildup

Last Answer : B. Project formation

Description : How will conflicts over resources/facility usage between this and other projects be settled?", is critically settled at level A. Main program B. Project formation C. Project Buildup D. Project Buildup

Last Answer : B. Project formation

Description : ____ structures are typically used in businesses that primarily sell and produce standard  products and seldom conduct external projects.

Last Answer : Ans. Functional-type organisation

Description : Work that continues throughout the project and does not relate to  any specific phase of development is termed a(n) a) Milestone b) Project function c) Activity d) Task e) Baseline.

Last Answer : b) Project function

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : A profitability index (PI) of .92 for a project means that . A. The project's costs (cash outlay) are (is) less than the present value of the project's benefits B. The project's NPV is ... is greater than 1 D. The project returns 92 cents in present value for each current rupee invested (cost)

Last Answer : C. The project's NPV is greater than 1

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A) Technical key resources (B) Work key structure (C) Work Breakdown Structure (WBS). (D) None of the above

Last Answer : (C) Work Breakdown Structure (WBS).

Description : Which structure shows the reporting relationships and communications channels for a project? a. Work Breakdown Structure. b. Organizational Breakdown Structure. c. Product Breakdown Structure. d. Responsibility assignment structure.

Last Answer : b. Organizational Breakdown Structure.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : Which one of the following statements best defines the purpose of a Product Breakdown Structure (PBS)? a. To define the hierarchy of deliverables that are required to be produced on the project. ... . d. To identify the health and safety strategies and procedures to be used on the project

Last Answer : a. To define the hierarchy of deliverables that are required to be produced on the project.

Description : The entire process of a project may be considered to be made upon a number of sub- processes placed in different stages called the Work Breakdown Structure. (True/False)

Last Answer : Ans. True

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A)Technical key resources (B)Work key structure (C)Work Breakdown Structure (WBS). (D)None of the above

Last Answer : (C)Work Breakdown Structure (WBS).

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : Which structure shows the reporting relationships and communications channels for a  project?  a. Work Breakdown Structure.  b. Organisational Breakdown Structure.  c. Product Breakdown Structure.  d. Responsibility assignment structure.

Last Answer : b. Organisational Breakdown Structure.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  a. The life cycle phases.  b. The logical order of tasks.  c. The scope of the project.  d. Project costs

Last Answer : c. The scope of the project.

Description : Which one of the following statements best defines the purpose of a Product Breakdown  Structure(PBS)?  a. To define the hierarchy of deliverables that are required to be produced on the project.  b. ... .  d. To identify the health and safety strategies and procedures to be used on the project.

Last Answer : a. To define the hierarchy of deliverables that are required to be produced on the project.

Description : Each item of the Work Breakdown Structure is assigned a unique identifier. What is the name  of this identifier? 1. Product ID number  2. Code of accounts  3. Quality inspection identifier  4. Project activity code

Last Answer : 2. Code of accounts

Description : The Scope Management Plan is included in which of the following documents. 1. Project Plan  2. The Work Breakdown Structure  3. The Scope Statement  4. Project Specifications

Last Answer : 3. The Scope Statement

Description : ) One of the initial project documents, issued by senior management, which outlines the  authority of the project manager, is called Project charter. As a seller, what other document can  be used in this place: 1. Work breakdown structure  2. Project scope  3. Contract  4. Internal memo

Last Answer : 3. Contract