Number of taps on platform as per norms for recommended level of facilities
(a) One for every coach
(b) One for alternate coach*
(c) One every 200 metres distance
(d) At the discretion of DRM

1 Answer

Answer :

(b) One for alternate coach*

Related questions

Description : Number of taps to be provided on ‘A’ category stations on each platform as per norms of minimum essential facilities are (a) 20 taps (b) 15 taps (c) 12 taps* (d) One taps for each bogie

Last Answer : (c) 12 taps*

Description : Urinals & Latrines for A & B stations as norms for recommended level of facilities for railway station (a) Ndb/500 (b) Ndb/300 (c) Ndb/200* (d) None of the above

Last Answer : (c) Ndb/200*

Description : Numbers of taps on each platform of ‘C’ category station as per norms of minimum essential facility criteria are (a) 6* (b) 8 (c) 12 (d) 15

Last Answer : (a) 6*

Description : Numbers of taps on each platform of ‘B’ category station as per norms of minimum essential facility criteria are (a) 6 (b) 8 (c) 12* (d) 15

Last Answer : (c) 12*

Description : Numbers of taps on each platform of ‘A’ category station as per norms of minimum essential facility criteria are (a) 6 (b) 8 (c) 12 (d) 15*

Last Answer : d) 15*

Description : Number of urinals & latrines to be provided on ‘A’ category stations as per norms on main essential facilities are (a) 15 (b) 10* (c) 8 (d) 6

Last Answer : (b) 10*

Description : Norms for No. of seats at recommended level at Cat. E stn. is (a) 0.4 Ndb (b) 0.4 Nds* (c) 0.4 Nmax (d) 100 on each P.F.

Last Answer : (b) 0.4 Nds*

Description : Norms for No. of seats at recommended level at Cat. D stn. is (a) 0.4 Ndb (b) 0.4 Nds* (c) 0.4 Nmax (d) 100 on each P.F.

Last Answer : (b) 0.4 Nds*

Description : Norms for No. of seats at recommended level at Cat. C stn. is (a) 0.4 Ndb (b) 0.4 Nds* (c) 0.4 Nmax (d) 100 on each P.F.

Last Answer : (b) 0.4 Nds*

Description : Norms for No. of seats at recommended level at Cat. B stn. is (a) 0.4 Ndb * (b) 0.4 Nds (c) 0.4 Nmax (d) 100 on each P.F.

Last Answer : (a) 0.4 Ndb

Description : Norms for No. of seats at recommended level at Cat. A stn. is (a) 0.4 Ndb* (b) 0.4 Nds (c) 0.4 Nmax (d) 100 on each P.F.

Last Answer : (a) 0.4 Ndb*

Description : As per international norms, the maximum permissible value of noise level in the industrial environment is __________ decibels as measured at a distance of 1.5 metres from the source of noise. (A) 110 (B) 85 (C) 60 (D) 45

Last Answer : (B) 85

Description : A model stations on railways should have (a) Minimum essential facilities (b) Desirable facilities* (c) Recommended facilities (d) All the above

Last Answer : b) Desirable facilities*

Description : Where Enquiries are ordered by DRM the enquiry report should be submitted to DRM within (a) 5 days (b) 7 days* (c) 10 days (d) 12 days

Last Answer : (b) 7 days

Description : As per norms for desirable amenity as given to model station, the retiring rooms should be provided on stations classified as --- (a) A & B* (b) A,B & C (c) A,B,C & D (d) A, B,C, D & E (e) A

Last Answer : a) A & B*

Description : As per norms for desirable amenity as given to model station, the clock rooms should be provided on stations classified as --- (a) A & B * (b) A,B & C (c) A,B,C & D (d) A, B,C, D & E (e) A

Last Answer : (a) A & B *

Description : As per norms for desirable amenity as given to model station, the water coolers should be provided on stations classified as --- (a) A & B (b) A,B & C (c) A,B,C & D* (d) A, B,C, D & E (e) A

Last Answer : (c) A,B,C & D*

Description : As per norms for desirable amenity as given to model station, the parking facility/circulating area should be provided on stations classified as --- (a) A & B (b) A,B & C (c) A,B,C & D* (d) A, B,C, D & E

Last Answer : (c) A,B,C & D*

Description : As per norms for desirable amenity as given to model station, the public address system should be provided on stations classified as --- (a) A & B (b) A,B & C* (c) A,B,C & D (d) A, B,C, D & E (e) A

Last Answer : (b) A,B & C*

Description : As per norms for desirable amenity as given to model station, the book stalls should be provided on stations classified as --- (a) A & B (b) A,B & C* (c) A,B,C & D (d) A, B,C, D & E (e) A

Last Answer : (b) A,B & C*

Description : As per norms for desirable amenity as given to model station, the refreshment rooms should be provided on stations classified as --- (a) A & B* (b) A,B & C (c) A,B,C & D (d) A, B,C, D & E (e) A

Last Answer : (a) A & B*

Description : Numbers of latrines on ‘D’ category of stations as per norms for essential amenities is (a) 2 (b) 4* (c) 6 (d) 10

Last Answer : (b) 4*

Description : Numbers of latrines on ‘C’ category of stations as per norms for essential amenities is (a) 2 * (b) 4 (c) 6 (d) 10

Last Answer : (a) 2 *

Description : Numbers of latrines on ‘B’ category of stations as per norms for essential amenities is (a) 2 (b) 4 (c) 6 * (d) 10

Last Answer : (c) 6

Description : Numbers of latrines on ‘A’ category of stations as per norms for essential amenities is (a) 2 (b) 4 (c) 6 (d) 10*

Last Answer : d) 10*

Description : For ‘B’ category stations as per minimum essential facility it is necessary to provide (a) High level platform (b) Medium level platform* (c) Rail level platform (d) All the above

Last Answer : (b) Medium level platform*

Description : Speed breaker has to be provided on road approaches of level crossing at maximum feasible distance within Railway boundary but not exceeding a) 10 meters b) 15 meters c) 20 meters* d) 200 meters

Last Answer : c) 20 meters*

Description : eFor design of sewers for sullage, minimum velocity of ---- metres per second is taken. (a) 1.0 m sec* (b) 1.5 m/sec (c) 2.0 m/sec (d) 2.5 m/sec

Last Answer : (a) 1.0 m sec*

Description : Requirement of water for platform washing is a)5 litre per square metre per day * b)10 litre per square meter per day c) 15 litre per square metre per day d)20 litre per square metre per day

Last Answer : a)5 litre per square metre per day *

Description : Height of Low level platform for passengers for BG is --- high (a) 0.455 m* (b) 0.560 m (c) 0.650 m (d) 0.760 m

Last Answer : (a) 0.455 m*

Description : Height of high level platform for passengers for BG is --- high (a) 0.455 m (b) 0.560 m (c) 0.650 m (d) 0.760 m*

Last Answer : (d) 0.760 m*

Description : Height of platform of a flag station in cutting above rail level is (a) Same height as Rail level (b) 305 mm above rail level (c) 455 mm above rail level (d) 840mm above rail level*

Last Answer : (d) 840mm above rail level*

Description : For ‘A’ category stations it is necessary to provide (a) High level platform* (b) Medium level platform (c) Rail level platform (d) All the above

Last Answer : (a) High level platform*

Description : The maximum height above rail level for B.G. goods platform is ……. Mm (a) 1000mm (b) 1050mm (c) 1065mm* (d) 1075mm

Last Answer : (c) 1065mm*

Description : What is maximum height above rail level for low-level passenger platform for BG? (a) 300mm (b) 455mm* (c) 525mm (d) 550mm

Last Answer : (b) 455mm

Description : Maximum height above rail level of high passenger Platform a. 860 mm b. 900 mm c. 840 mm&* d. 875 mm

Last Answer : c. 840 mm&*

Description : Noise level heard at a distance of about 100 metres from a jet engine with after burner is about __________ decibels. (A) 120 (B) 140 (C) 170 (D) 200

Last Answer : (C) 170

Description : Pick out the wrong statement pertaining to the turbine agitator. (A) Recommended peripheral speed for the turbine agitator is 200-250 metres/minute (B) Pitched blade turbine agitator gives only radial flow with ... l/4th of agitator diameter (with central disc, it is l/8th of the agitator diameter)

Last Answer : (B) Pitched blade turbine agitator gives only radial flow with complete absence of the axial flow

Description : Maximum distance apart of trolley refuges on bridges with main spans of 100metre or more is i. 50 mtr j. 100 mtr k. 200 mtr l. a refuge over each pair*

Last Answer : l. a refuge over each pair*

Description : Which of the facilities do not exist at halt station? (a) Facilities for stopping the train (b) Facilities for a small waiting (c) Facilities for crossing of train* (d) Facilities for book of passengers

Last Answer : (c) Facilities for crossing of train*

Description : For rolling mark 60 kg/Sail/X/2010 the first testing in the field after initial testing of rails in rail manufacturing plant, will be done. (i) After test free period of 25%. (ii) After passage of every 40 ... period.* (iii) After passage of 200 GMT. (iv) On the basis of annual GMT of the section.

Last Answer : (ii) After passage of every 40 GMT traffic during test free period.*

Description : An important bridge is one which has total waterway of equal to or more than a) 1000 sq.metres.* b) 800 sq. metres c) 500 sq. metres d) 300 sq. metres

Last Answer : a) 1000 sq.metres.*

Description : While taking sample of water from well, sample is collected a)About 2 metre above the bottom of wel b) About 1 metre above the bottom of well * c)About 1 metres below the bottom of well d) none of the above

Last Answer : b) About 1 metre above the bottom of well *

Description : Facia boards of platform shelters shall have a minimum horizontal clearance of ……. from C.L. of track at a minimum height of 4.61m above RL. a) 2360 mm b) 3660 mm c) 3000 mm d) 1600 mm*

Last Answer : d) 1600 mm*

Description : One of the following works does not require CRS sanction a) Regirdering/ Rebuilding b) Erection of new FOB c) Erection of platform shelter* d) Pipe line crossing

Last Answer : c) Erection of platform shelter*

Description : The horizontal clearance of edge of foot over bridge structure from face of platform is a) 6525 mm b) 3660 mm* c) 5330 mm d) 5300 mm

Last Answer : b) 3660 mm*

Description : The gradient of a platform is generally (a) 1 in 1000 (b) 1 in 750 (c) 1 in 500* (d) 1 in 250

Last Answer : (c) 1 in 500*

Description : The minimum horizontal distances form centre of track to face of passenger platform coping for B.G. is ……. Mm (A) 1650 MM. (B) 1670 MM* (C)1676 MM (D) 1685 MM

Last Answer : (B) 1670 MM*

Description : Lubrication of ERC and inserts in corrosion prone areas and platform line is done:- (a) Once in a month. (b) Once in a fortnight. (c) Once in a week. (d) Once in a year.*

Last Answer : (d) Once in a year.*