When going to a new automation level
a. there is a 1 year lag.
b. there is a lag dependent on the amount the automation level has been changed. c. there is no lag.
d. the lag is dependent on the cost.
e. none of the above.

1 Answer

Answer :

a. there is a 1 year lag.

Related questions

Description : There is ______ lag in buying new Capacity and ______ lag in changing Automation. a. 0; 0 b. 1 year; 0 c. 0; 1 year d. 1 year; 1 year e. ½ year; ½ year

Last Answer : d. 1 year; 1 year

Description : Which is false about production in Capsim? a. Teams cannot produce beyond 100% capacity. b. Teams should match their production schedule to the teams sales forecast. c. There is a one year lag ... year lag between purchase and use of additional production automation. e. All of the above are true.

Last Answer : a. Teams cannot produce beyond 100% capacity.

Description : What does not drive length of R&D project? a. The product's automation level on the Production line. b. The amount of money You are willing to spend on it. c. The number of R&D projects underway ... of the product's new location to an existing product in your company's line. e. The labor strike.

Last Answer : The labor strike.

Description : If you sell off a production line (capacity and automation), the amount of cash that the company will receive will be a. 65% of the original cost. b. average cost of production for the previous year (market ... . 50% of the book value. d. 50% of the acquisition cost. e. 65% of the book value.

Last Answer : a. 65% of the original cost.

Description : The cost to increase automation to 8.0 is equal to a. First Shift Capacity X [$8 X (4 - Automation Level). b. First Shift Capacity X [$8 X (4 + Automation Level). c. First Shift Capacity X [$4 X ... Capacity X [$4 X (8 + Automation Level). e. First Shift Capacity X [$4 X (4 - Automation Level)

Last Answer : c. First Shift Capacity X [$4 X (8 – Automation Level).

Description : In the Capstone® simulation, what are the components of a product's material cost? a. Cost of Inventory on hand and the cost to store it b. Reliability component cost and positioning component ... , shipping and handling d. Level of automation and product reliability e. None of the above

Last Answer : b. Reliability component cost and positioning component cost

Description : .As a manager you need to change the automation level of your segment from 2 to 5. The line has a capacity of $2 million. How much would it cost? a. $12 million b. $24 million c. $10 million d. $6 million e. none of the above

Last Answer : b. $24 million

Description : .If you are currently producing 100,000 units at an automation level of 5, how much would it cost to maximize automation? a. $500,000 b. $50,000 c. $2,000,000 d. $5,000,000 e. none of the above

Last Answer : c. $2,000,000

Description : .If you are currently producing 100,000 units and your automation level is 10, how much will it cost you to double your capacity? a. $1,000,000 b. $4,600,000 c. $100,000 d. $10,000 e. none of the above

Last Answer : b. $4,600,000

Description : What is the total cost in dollars for adding 1.0 million units of capacity to a production line with an automation level of 1.0 and floor space costs per unit of $6? Assume automation costs per unit of $4. a. $26 million b. $10 million c. $2.6 million d. $1 million e. none of the above

Last Answer : b. $10 million

Description : If a line has a capacity of 100,000 units, the cost of changing the automation level 1 unit either up or down is a. $60,000. b. $40,000. c. $400,000. d. $600,000. e. none of the above.

Last Answer : c. $400,000.

Description : Lowering the automation level will result in a. receiving a cash payment of $4 per unit of capacity. b. a tax credit. c. a charge. d. immediate changes to production lines. e. none of the above.

Last Answer : c. a charge.

Description : At the start of the simulation, all assembly lines have an automation level between: a. 2.0 and 4.0. b. 3.0 and 5.0. c. 4.0 and 6.0. d. 5.0 and 7.0. e. 6.0 and 8.0.

Last Answer : b. 3.0 and 5.0.

Description : Adding one additional unit of capacity costs a. $4 x Change (difference) in Automation Level b. $6 + ($4 x Current Automation Level). c. $6 x Change (difference) in Automation Level. d. $4 + ($6 x Current Automation Level). e. none of these.

Last Answer : b. $6 + ($4 x Current Automation Level).

Description : The automation level a. causes you to require more manpower with higher ratings. b. causes you to require more manpower with lower ratings. c. causes you to require less manpower with higher ratings. d. causes you to require less manpower with lower ratings. e. both b and c.

Last Answer : e. both b and c.

Description : .If your current capacity is 10,000 units and your automation level is 5.0, what is the difference of the investment between doubling your capacity and doubling your automation level? a. $60,000 b. $20,000 c. $10,000 d. $520,000 e. $260,000

Last Answer : a. $60,000

Description : A new unit of capacity costs $6 for the floor space plus $4 times a. hourly wage. b. automation rating. c. unit cost. d. MTBF. e. $0.65.

Last Answer : b. automation rating.

Description : Which three factors drive labor cost? a. Production capacity b. Wage and benefit rates c. Automation levels d. Second shift/Overtime costs e. b, c, d

Last Answer : e. b, c, d

Description : If you want to add 500,000 units of capacity to an assembly line with an automation rating of 5, how much will it cost? a. 1,200,000 b. 1,300,000 c. 13,000,000 d. 24,000,000 e. 26,000,000

Last Answer : c. 13,000,000

Description : If you increase automation from 2.0 to 5.0, the cost is: a. $12 per unit of capacity. b. $15 per unit of capacity. c. $9 per unit of capacity. d. $6 per unit of capacity. e. Cannot determine with this information.

Last Answer : a. $12 per unit of capacity.

Description : The relative cost of a product’s material cost increases as: a. size is increased. b. performance is decreased. c. MTBF is raised. d. automation stays the same. e. all of the above.

Last Answer : c. MTBF is raised.

Description : When purchasing increased Capacity and Automation, the new capacity becomes available a. immediately. b. in 1 year. c. in 6 months. d. in 2 years. e. none of these.

Last Answer : b. in 1 year.

Description : Repositioning moves a product on the Perceptual Map from its old location to a new one. When does the new location become active? a. The day the R&D project completes b. The following year ... R&D project completes d. The day capacity and automation is purchased e. The day capacity is purchased

Last Answer : a. The day the R&D project completes

Description : Which of the following is true about the Accounts Receivable Lag and its implications on demand? a. If you offer no credit, demand falls to about 60% of normal. b. At 30 days, demand is 90%. c. At 45 days, demand is 95%. d. At 60 days, demand is 98.5%. e. At 90 days, demand is 100%.

Last Answer : d. At 60 days, demand is 98.5%.

Description : If you reduce automation in the production component of Marketing, you will: a. slow down R&D designs. b. incur a retooling cost. c. lose the game. d. none of the above.

Last Answer : b. incur a retooling cost.

Description : Account Receivables lag impacts sales. At no credit terms, the appeal falls to about ______ %, at 30 days, appeal is _____ %, at 60 days, appeal is ______%. a. 98.5, 92, 65 b. 65, 92, 98.5 c. 70, 85, 99 d. none of the above, there is no impact

Last Answer : b. 65, 92, 98.5

Description : If you purchase production capacity and automation: a. it is available immediately. b. it is available in 6 months. c. it is available in the next year. d. it is available when you need it. e. none of the above.

Last Answer : c. it is available in the next year.

Description : If a product's Automation rating is substantially increased, it will: a. take longer to move the product across the Perceptual Map. b. take a shorter time to move the product across the Perceptual Map. ... Perceptual Map. d. have no effect on the product moving across the Perceptual Map. e. other.

Last Answer : a. take longer to move the product across the Perceptual Map.

Description : What happens to a company when it increases the A/P lag? a. It improves its cash position. b. It deteriorates its cash position. c. It loses credibility. d. Its suppliers withhold material for production. e. a, d.

Last Answer : e. a, d.

Description : If your team decides to introduce a new product, when should capacity and automation be purchased? a. Two rounds prior to product release b. One round prior to product release c. The ... round after product release e. Purchase of capacity and automation is not necessary for new product release

Last Answer : b. One round prior to product release

Description : Which statement is true? a. Increasing in capacity and changes in automation can take less than a year to implement if the product already exists. Sales of capacity take a full year to implement ... automation and sales of capacity take less than a year to implement if the product already exists.

Last Answer : b. Increases in capacity and changes in automation take a full year to implement. Sales of capacity are immediate.

Description : Higher automation leads to lower production costs and has what effect on repositioning a product on the perceptual map? a. makes it more difficult and expensive b. makes it easier and cheaper c. no effect d. eliminates repositioning

Last Answer : a. makes it more difficult and expensive

Description : The A/R lag is a. a marketing spreadsheet definition. b. the accounts receivable lag (in days). c. the time between customers receiving products and when they are expected to pay for them. d. a, b, and c.

Last Answer : d. a, b, and c.

Description : As a general rule, stock issues are used to: a. Protect you from getting a loan from Big Al. b. Fund the purchase of more market share. c. Fund long term investments in capacity and automation. d. Fund yearly sales and promotional budgets. e. All of the above.

Last Answer : c. Fund long term investments in capacity and automation.

Description : Automation levels are given on a scale of _____ to _____. a. 0.0; 5.0 b. 1.0; 5.0 c. 0.0; 10.0 d. 1.0; 10.0 e. 5.0; 10.0

Last Answer : d. 1.0; 10.0

Description : Labor costs are driven by three factors: a. wage and benefit rates, automation levels, and MTBF. b. wage and benefit rates, positioning, and second shift. c. wage and benefit rates, second ... , automation levels, and second shift. e. wage and benefit rates, second shift, and material costs.

Last Answer : d. wage and benefit rates, automation levels, and second shift.

Description : What is the right formula for capacity investment? a. Investment = Capacity x ($4 x Automation) b. Investment = Capacity x [$10 + ($4 x Automation)] c. Investment = Capacity x [$4 + ($6 x Automation)] d. Investment = Capacity x [$6 + ($4 x Automation)] e. Investment = Capacity x Automation

Last Answer : d. Investment = Capacity x [$6 + ($4 x Automation)]

Description : How can the R&D cycle time be reduced? a. Increasing automation levels b. Budgeting money to quality initiatives c. Increasing R&D budget d. Decreasing product portfolio e. Decreasing capacity

Last Answer : b. Budgeting money to quality initiatives

Description : What is one drawback of increasing automation? a. The product requires increased time/expense for subsequent short-move repositioning. b. Operating second shift becomes more expensive. c. ... d. Automation slows production capability. e. It requires more employees for the production line.

Last Answer : a. The product requires increased time/expense for subsequent short-move repositioning.

Description : Which Automation rating requires the longest time to reposition a product? a. 1 b. 3 c. 7 d. 9 e. 10

Last Answer : e. 10

Description : R&D completion time depends on a. number of projects in R&D. b. automation rating. c. similarity to existing products. d. size of the product. e. a, b, and c.

Last Answer : e. a, b, and c.

Description : Which of the following are not considered in the Fine Cut? a. Positioning b. Automation c. Age d. Reliability e. Price

Last Answer : b. Automation

Description : Rapid movement of an existing product on the Perceptual Map requires a. reliability adjustment. b. low automation levels. c. high automation levels. d. none of the above.

Last Answer : b. low automation levels.

Description : For each point of change in automation, your company is charged ______ per unit of capacity. a. $6.00 c. $4.00 b. $5.00 d. $7.00

Last Answer : c. $4.00

Description : What is one way to lower material costs? a. decrease MTBF b. increase capacity c. increase automation d. none of the above

Last Answer : a. decrease MTBF

Description : If the previous year you reached 100% customer awareness in your company, this year what will you need to do to maintain this level? a. There is nothing to do. I have already reached as much awareness ... half of the money spent the previous year to reach 75% of the population. e. None of these.

Last Answer : c. I would only need to create 33% new awareness to maintain 100% this year

Description : What is the minimum amount of time that it takes to create a new product? a. 3 months b. 6 months c. 1 year d. 2 years e. 5 years

Last Answer : c. 1 year

Description : Maximum issue is a. the upper limit in thousands of dollars that teams can issue in stock this year. b. amount in thousands of dollars that teams wish to issue in stock. c. upper limit of stock that can be ... thousands of dollars. d. amount of stock, if any, to buy back. e. none of the above.

Last Answer : a. the upper limit in thousands of dollars that teams can issue in stock this year.

Description : Looking at the production, if the potential bar is higher than the actual one, a. the company should spend more budget in sales. b. the company over produced and missed sales ... company under produced and missed sales opportunities. e. the company should spend more budget in marketing.

Last Answer : d. the company under produced and missed sales opportunities.

Description : What is working capital? a. The funds needed for the day to day running of the company b. The cash on hand at the end of the day c. Profits less current liabilities d. The amount of funds a company needs to run indefinitely e. Total sales less total expenses