The assignment problem
a. Requires that only one activity be assigned to each resource
b. Is a special case of transportation problem
c. Can be used to maximize resources
d. All of the above

1 Answer

Answer :

d. All of the above

Related questions

Description : The assignment problem is: a. Requires that only one activity be assigned to each resource b. Is a special case of transportation problem c. Can be used to maximise resource d. All the above

Last Answer : d. All the above

Description : While solving an assignment problem, an activity is assigned to a resource through a square with zero opportunity cost because the objective is to a. Minimize total cost of assignment b. Reduce the cost of ... to zero c. Reduce the cost of that particular assignment to zero d. All of the above

Last Answer : c. Reduce the cost of that particular assignment to zero

Description : An assignment problem is a special case of transportation problem, where a. Number of rows equals number of columns b. All rim conditions are 1 c. Values of each decision variable is either 0 or 1

Last Answer : D.variable is either 0 or 1

Description : An assignment problem is considered as a particular case of a transportation problem because a. The number of rows equals columns b. All xij = 0 or 1 c. All rim conditions are 1 d. All of the above

Last Answer : d. All of the above

Description : For maximization in assignment problem, the objective is to maximize the a. Profit b. Optimization c. Cost d. None of the above

Last Answer : a. Profit

Description : If no. of rows are not equal to number of columns and the matrix elements are profit elements then the problem is: a. Balanced and Maximization Transportation problem b. ... Transportation problem c. Balanced and Maximization Assignment problem d. Unbalanced and Maximization Assignment problem

Last Answer : a. Balanced and Maximization Transportation problem

Description : If no. of rows are equal to number of columns and the matrix elements are Time elements then the problem is: a. Balanced and Minimization Transportation problem b. ... Transportation problem c. Balanced and Minimization Assignment problem d. Unbalanced and Minimization Assignment problem

Last Answer : c. Balanced and Minimization Assignment problem

Description : ___ is one of the fundamental combinatorial optimization problems a. Assignment problem b. Transportation problem c. Optimization problem d. None of the above

Last Answer : a. Assignment problem

Description : The purpose of a dummy row or column in an assignment problem is to a. Obtain balance between total activities and total resources b. Prevent a solution from becoming degenerate c. Provide a means of representing a dummy problem d. None of the above

Last Answer : a. Obtain balance between total activities and total resources

Description : If the number of jobs is not equal to the number of resources, then the problem is term as _____ assignment problem a. Balanced b. Unbalanced c. Equal d. Unequal

Last Answer : b. Unbalanced

Description : If the number of jobs is equal to the number of resources, then the problem is term as _____ assignment problem a. Balanced b. Unbalanced c. Equal d. Unequal

Last Answer : a. Balanced

Description : ________ technique is related to Quality control a. Assignment b. Transportation c. CPM d. SQC

Last Answer : d. SQC

Description : ______ are technique applied in project management a. CPM b. Assignment c. Transportation d. Decision theory

Last Answer : a. CPM

Description : An optimal solution of an assignment problem can be obtained only if a. Each row & column has only one zero element b. Each row & columns has at least one zero element c. The data is arrangement in a square matrix d. None of the above

Last Answer : d. None of the above

Description : An optimal assignment requires that the maximum number of lines that can be drawn through squares with zero opportunity cost be equal to the number of a. Rows or columns b. Rows & columns c. Rows + columns -1 d. None of the above

Last Answer : b. Rows & columns

Description : LPP is exactly used in solving what kind of resource allocation problems? a. Production planning and scheduling b. Transportation c. Sales and advertising d. All of the above

Last Answer : d. All of the above

Description : Maximization assignment problem is transformed into a minimization problem by a. Adding each entry in a column from the maximization value in that column b. Subtracting each entry in a column from the maximum ... entry in a column from the maximum value in that table d. Any one of the above

Last Answer : c. Subtracting each entry in a column from the maximum value in that table

Description : What is the mathematical constant of "e" mean?

Last Answer : answer:Good question! I have wondered this myself, and even after professors explaining it to me, it seems that there's not one meaning for it; it's just useful. Examples: 1) The exponential function (eΛx ... logarithm, so eΛ(lnx)=x. I'd love to hear what other Jellies have to say about this.

Description : Trying to understand the magical number of e?

Last Answer : The derivative of a^x (where a is a constant) is (a^x)ln(a). So for 2^x at x=0, your derivative is (2^0)ln(2) = .693.

Description : Who is queen Elizabeth?

Last Answer : queen of england http://en.wikipedia.org/wiki/Elizabeth_II_of_the_United_Kingdom

Description : Pickle girl.

Last Answer : What is a good nickname for my pregnant wife, who eats a gallon of pickles every two days?

Description : Knapsack hand compression sprayer develops pressure b. 1.5-3.5kg/cm2. c. 2-3.5kg/cm2. d. None of above

Last Answer : Ans- a. 3 to 12kg/cm2.

Description : For solving an assignment problem, which method is used? a. British b. American c. German d. None of the above

Last Answer : B. american

Description : . The method used for solving an assignment problem is called a. Reduced matrix method b. MODI method c. Hungarian method d. None of the above

Last Answer : . c. Hungarian method

Description : If in an assignment problem, number of rows is not equal to number of columns then a. Maximization problem b. Problem is unbalanced c. Problem is degenerate d. Optimum solution is not possible

Last Answer : c. Problem is degenerate

Description : When a particular assignment in the given problem is not possible or restricted as a condition, it is called a __ problem a. Infeasible b. Degenerate c. Unbalanced d. Prohibited

Last Answer : d. Prohibited

Description : The extra row or column which is added to balance an assignment problem is called _____ a. Regret b. Epsilon c. Dummy d. extra

Last Answer : c. Dummy

Description : ________ which is a subclass of a linear programming problem(LPP) a. Programming problem b. Transportation problem c. Computer problem d. All of the above

Last Answer : b. Transportation problem

Description : 37. Which of the following is not a characteristics of the LP a. Resources must be limited b. Only one objective function c. Parameters value remains constant during the planning period d. The problem must be of minimization type

Last Answer : d. The problem must be of minimization type

Description : 56. Constraints in LP problem are called active if they a. Represent optimal solutions b. At optimality do not consume all the available resources c. Both a & b d. None of the above

Last Answer : a. Represent optimal solutions

Description : 50. Which of the following statements is true with respect to the optimal solution of an LP problem? a. Every LP problem has an optimal solution b. Optimal solution of an LP problem always occurs ... completely used d. If an optimal solution exists, there will always be at least one at a corner

Last Answer : d. If an optimal solution exists, there will always be at least one at a corner

Description : _________ technique helps to make a choice from numerous available alternatives a. PERT b. CPM c. Linear Programming d. Transportation

Last Answer : d. Transportation

Description : _____ technique is related to Inventory management a. EOQ b. SQC c. CPM d. transportation

Last Answer : a. EOQ

Description : 42. _____ assumption means the prior knowledge of all the coefficients in the objective function , the coefficients of the constraints and the resource values a. Proportionality b. Certainty c. Finite choices d. Continuity

Last Answer : b. Certainty

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by using only one time factor per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : 53. While plotting constraints on a graph paper, terminal points on both the axes are connected by straight line because a. The resources are limited in supply b. The objective function as a linear function c. The constraints are linear equations or inequalities d. All of the above

Last Answer : c. The constraints are linear equations or inequalities

Description : . Non-negativity condition in an LP model implies a. A positive coefficient of variables in objective function b. A positive coefficient of variables in any constraint c. Non-negative value of resources d. None of the above

Last Answer : d. None of the Above

Description : 35. Which of the following is not a characteristic of the L P model a. Alternative courses of actions b. An objective function of maximization type c. Limited amount of resources d. Non-negativity condition on the value of decision variable

Last Answer : b. An objective function of maximization type

Description : 2. Non-Negativity condition is an important component of L P model because a. Variables value should remain under the control of the decision-maker b. Value of variables make sense & correspond to real-world problems c. Variables are interrelated in terms of limited resources d. None of the above

Last Answer : b. Value of variables make sense & correspond to real-world problems

Description : 29. A constraint in an LP model restricts a. Value of objective function b. Value of a decision variable c. Use of the available resources d. All of the above

Last Answer : d. All of the above

Description : 28. Linear programming is a a. Constrained optimization technique b. Technique for economic allocation of limited resources c. Mathematical technique d. All of the above

Last Answer : b. Technique for economic allocation of limited resource

Description :  A Cost Breakdown Structure (CBS) shows costs assigned to:  a. individual work packages using the Work Breakdown Structure (WBS).  b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM).  d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description : Floats for critical activities will be always _____ a. One b. Zero c. Highest d. Same as duration of the activity

Last Answer : b. Zero

Description : An activity whose start or end cannot be delay without affecting total project completion time is called ______ activity a. Dummy b. Non-critical c. Critical d. Important

Last Answer : c. Critical

Description : Pick up the incorrect statement from the following a. The activity which consumes maximum time, is called a node b. The activity is the time consuming part of a project c. The beginning ... of a job, are called events d. Logically and sequentially connected activities and events form a network

Last Answer : a. The activity which consumes maximum time, is called a node

Description : In a PERT network, the earliest(activity) start time is the a. Earliest time that an activity can be finished without delaying the entire project b. Latest time that an activity can ... of precedence requirements d. Latest time that an activity can be finished without delaying the entire project

Last Answer : c. Earliest time that an activity can be started without violation of precedence requirements

Description : At the completion of the forward and backward passes, the slack for an activity is given by the a. Difference between early start and early finish b. Difference between early start and ... c. Difference between latest start and early finish d. Difference between latest start and latest finish

Last Answer : c. Difference between latest start and early finish

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by employing three time estimates per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : 49. A feasible solution to an LP problem a. Must satisfy all of the problem’s constraints simultaneously b. Need not satisfy all of the constraints, only some of them c. Must be a corner point of the feasible solution d. Must optimize the value of the objective function

Last Answer : a. Must satisfy all of the problem’s constraints simultaneously

Description : Match the following. i) Mutual exclusion a) A process may hold allocated resources while waiting assignment. ii) Hold and wait b) No resource can be forcibly removed from a process holding it. iii) No preemption c) Only one process may use ... , ii-c, iii-b C) i-b, ii-c, iii-a D) i-c, ii-a, iii-b

Last Answer : D) i-c, ii-a, iii-b