At the completion of the forward and backward passes, the slack for an activity is given by the
a. Difference between early start and early finish
b. Difference between early start and latest finish
c. Difference between latest start and early finish
d. Difference between latest start and latest finish

1 Answer

Answer :

c. Difference between latest start and early finish

Related questions

Description : An activity whose start or end cannot be delay without affecting total project completion time is called ______ activity a. Dummy b. Non-critical c. Critical d. Important

Last Answer : c. Critical

Description : Backward pass calculations are done to find ________ occurrence times of events a. Tentative b. Definite c. Latest d. Earliest

Last Answer : c. Latest

Description : In a PERT network, the earliest(activity) start time is the a. Earliest time that an activity can be finished without delaying the entire project b. Latest time that an activity can ... of precedence requirements d. Latest time that an activity can be finished without delaying the entire project

Last Answer : c. Earliest time that an activity can be started without violation of precedence requirements

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : Forward pass calculations are done to find _____ occurrence times of events a. Exact b. Earliest c. Latest d. Approximate

Last Answer : b. Earliest

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : To calculate early start (ES) and early finish (EF) perform a:  A. Backward pass B. Forward pass  C. Lateral pass D. Critical pass

Last Answer : B. Forward pass

Description : . In simplex algorithm, which method is used to deal with the situation where an infeasible starting basic solution is given? a. Slack variable b. Simplex method c. Big M Method d. None of the above

Last Answer : b. Simplex method

Description : In simplex method, if there is tie between a decision variable and a slack (or surplus) variable, ______ should be selected a. Slack variable b. Surplus variable c. Decision variable d. None of the above

Last Answer : c. Decision variable

Description : In simplex method, we add _______ variables in the case of “=” a. Slack variable b. Surplus variable c. Artificial variable d. None of the above

Last Answer : c. Artificial variable

Description : 66. Which method is an iterative procedure for solving LPP in a finite number of steps? a. Simplex algorithm b. Slack variable c. Big M method d. Simplex method

Last Answer : d. Simplex method

Description : Select the incorrect statement. (A) Earliest start of an activity is the early event time of the node it leaves. (B) Latest finish of an activity is the late event time of the node it enters. (C) Latest start of an activity is its latest finish minus its duration. (D) None of the above

Last Answer : (D) None of the above

Description : What is the benefit of using PERT/CPM network as integral component of project management? a. They furnish a consistent framework for planning, scheduling, monitoring and controlling project b. They illustrate ... that the project will be completed by a specific date d. All of the above

Last Answer : d. All of the above

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : Total float for any activity is defined as the difference between (A) Its latest finish time and earliest start time for its successor activity (B) Its latest start time and earliest start ... earliest finish time (D) Its earliest finish time and earliest start time for its successor activity

Last Answer : (B) Its latest start time and earliest start time

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : The EST + activity duration = .............................. a. Earliest Finish Time b. Latest Start Time c. Latest Finish Time d. None of these

Last Answer : a. Earliest Finish Time

Description : Pick up the correct statement from the following: (A) Forward pass is used for calculating earliest expected time (B) Backward pass is used for calculating the latest occurrence time (C) Maximum value of earliest ... time is used if there is more than one value of any event (D) All the above

Last Answer : (D) All the above

Description : Floats for critical activities will be always _____ a. One b. Zero c. Highest d. Same as duration of the activity

Last Answer : b. Zero

Description : Pick up the incorrect statement from the following a. The activity which consumes maximum time, is called a node b. The activity is the time consuming part of a project c. The beginning ... of a job, are called events d. Logically and sequentially connected activities and events form a network

Last Answer : a. The activity which consumes maximum time, is called a node

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by employing three time estimates per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by using only one time factor per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : The assignment problem a. Requires that only one activity be assigned to each resource b. Is a special case of transportation problem c. Can be used to maximize resources d. All of the above

Last Answer : d. All of the above

Description : While solving an assignment problem, an activity is assigned to a resource through a square with zero opportunity cost because the objective is to a. Minimize total cost of assignment b. Reduce the cost of ... to zero c. Reduce the cost of that particular assignment to zero d. All of the above

Last Answer : c. Reduce the cost of that particular assignment to zero

Description : ........................... is the latest time by which an activity can be finished without delaying the completion of the project. a. LST b. LFT c. EFT d. EST

Last Answer : b. LFT

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : The latest finish time for an activity: A. Equals the min. of LFT − t for al immediate successors B. Equals the max. of LFT − t for al immediate predecessors. C. Equals the max. of EST + t for all immediate predecessors. D. Equals the min. of EST + t for all immediate successors

Last Answer : A. Equals the min. of LFT − t for al immediate successors

Description : Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer. (A) A is correct but R is not correct (B) R is correct but A is not correct (C) Both A and R is correct (D) Both A and R is incorrect

Last Answer : (A) A is correct but R is not correct

Description : When a particular assignment in the given problem is not possible or restricted as a condition, it is called a __ problem a. Infeasible b. Degenerate c. Unbalanced d. Prohibited

Last Answer : d. Prohibited

Description : If profit, sales, production, etc is given then it is _________ a. Balanced problem b. Unbalanced problem c. Maximization problem d. Minimization problem

Last Answer : c. Maximization problem

Description : If cost, time, etc is given, then it is ________ a. Balanced problem b. Unbalanced problem c. Maximization problem d. Minimization problem

Last Answer : d. Minimization problem

Description : _____ is another method to solve a given LPP involving some artificial variable? a. Big M method b. Method of penalties c. Two-phase simplex method d. None of the above

Last Answer : a. Big M method

Description : The basic difference between PERT and CPM is that a. PERT deals with events and CPM with activities b. Critical Path is determined in PERT only c. Costs are considered on CPM only d. Guessed times are used in PERT and evaluated times in CPM.

Last Answer : a. PERT deals with events and CPM with activities

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good (A) EF = ES + D (B) LS = LF - D (C) LF = LS + D (D) All the above

Last Answer : (D) All the above

Description : Which of the following statements is correct regarding float' for anactivity? a) Time between its earliest start time and earliest finish time b) Time between its latest start time and latest ... start time and earliest finish time d) Time between earliest finish time and latest finish time

Last Answer : d) Time between earliest finish time and latest finish time

Description : Every combination of strategies determines an outcome known as _____ a. Regret b. Payoff c. Saddle point d. Profit matrix

Last Answer : b. Payoff

Description : The choice of the strategy is made by both the _________ simultaneously a. Decision maker b. Manager c. Competitor d. Player

Last Answer : Player

Description : A ______ occurs when each player selects one of his strategies a. Profit b. Decision c. Play d. Game

Last Answer : c. Play

Description : A ______ is the one in which the player selects more than one strategy with fixed probabilities before playing the game. a. Mixed strategy b. Pure strategy c. Complete strategy d. Impure strategy

Last Answer : d. Impure strategy

Description : A _______ provides a complete definition of how a player will play a game a. Mixed strategy b. Pure strategy c. Complete strategy d. Impure strategy

Last Answer : c. Complete strategy

Description : The various alternatives or courses of actions available to each player in a game are called as ____ a. Saddle points b. Strategies c. Pay-off d. Gains

Last Answer : b. Strategies

Description : A situation in a game where, in the payoff matrix, maximin of row is equal to minimax of column is called___ a. Centre point b. Main point c. Saddle point d. Equal point

Last Answer : c. Saddle point

Description : In a game, the alternatives or courses of action available to each player are called _____ a. Options b. Choices c. Actions d. strategies

Last Answer : d. strategies

Description : The participants in a game are called ______ a. Clients b. Members c. Customers d. Players

Last Answer : d. Players