In a PERT network, the earliest(activity) start time is the
a. Earliest time that an activity can be finished without delaying the entire project
b. Latest time that an activity can be started without delaying the entire project
c. Earliest time that an activity can be started without violation of precedence requirements
d. Latest time that an activity can be finished without delaying the entire project

1 Answer

Answer :

c. Earliest time that an activity can be started without violation of precedence requirements

Related questions

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : ........................... is the latest time by which an activity can be finished without delaying the completion of the project. a. LST b. LFT c. EFT d. EST

Last Answer : b. LFT

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : What is the benefit of using PERT/CPM network as integral component of project management? a. They furnish a consistent framework for planning, scheduling, monitoring and controlling project b. They illustrate ... that the project will be completed by a specific date d. All of the above

Last Answer : d. All of the above

Description : For a project manager to have an effective means of identifying and communicating the planned activities and their interrelationships, he must use a network technique. One of the network ... evaluation review technique c. Path evaluation review technique d. Project execution review technique

Last Answer : b. Program evaluation review technique

Description : Backward pass calculations are done to find ________ occurrence times of events a. Tentative b. Definite c. Latest d. Earliest

Last Answer : c. Latest

Description : Forward pass calculations are done to find _____ occurrence times of events a. Exact b. Earliest c. Latest d. Approximate

Last Answer : b. Earliest

Description : dummy activity is used in PERT network to describe the (A) Precedence relationship (B) Resource idleness (C) Resource restriction (D) Necessary time delay

Last Answer : Option A

Description : At the completion of the forward and backward passes, the slack for an activity is given by the a. Difference between early start and early finish b. Difference between early start and ... c. Difference between latest start and early finish d. Difference between latest start and latest finish

Last Answer : c. Difference between latest start and early finish

Description : An activity whose start or end cannot be delay without affecting total project completion time is called ______ activity a. Dummy b. Non-critical c. Critical d. Important

Last Answer : c. Critical

Description : Pick up the incorrect statement from the following a. The activity which consumes maximum time, is called a node b. The activity is the time consuming part of a project c. The beginning ... of a job, are called events d. Logically and sequentially connected activities and events form a network

Last Answer : a. The activity which consumes maximum time, is called a node

Description : The basic difference between PERT and CPM is that a. PERT deals with events and CPM with activities b. Critical Path is determined in PERT only c. Costs are considered on CPM only d. Guessed times are used in PERT and evaluated times in CPM.

Last Answer : a. PERT deals with events and CPM with activities

Description : . In what year was PERT developed? a. 1957 b. 1959 c. 1960 d. 1958

Last Answer : . 1957

Description : _________ technique helps to make a choice from numerous available alternatives a. PERT b. CPM c. Linear Programming d. Transportation

Last Answer : d. Transportation

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by employing three time estimates per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by using only one time factor per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : Select the incorrect statement. (A) Earliest start of an activity is the early event time of the node it leaves. (B) Latest finish of an activity is the late event time of the node it enters. (C) Latest start of an activity is its latest finish minus its duration. (D) None of the above

Last Answer : (D) None of the above

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : Total float for any activity is defined as the difference between (A) Its latest finish time and earliest start time for its successor activity (B) Its latest start time and earliest start ... earliest finish time (D) Its earliest finish time and earliest start time for its successor activity

Last Answer : (B) Its latest start time and earliest start time

Description : The EST + activity duration = .............................. a. Earliest Finish Time b. Latest Start Time c. Latest Finish Time d. None of these

Last Answer : a. Earliest Finish Time

Description : 31. Constraints in an LP model represents a. Limitations b. Requirements c. Balancing limitations & requirements d. All of the above

Last Answer : d. All of the above

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : Which among the below stated datagram discard code fields in ICMP is/are generated if a router fails to forward a packet due to administrative filtering? a. Source Route Failed b. Communication Administratively Prohibited c. Host Precedence Violation d. Precedence Cut-off in Effect

Last Answer : b. Communication Administratively Prohibited

Description : Floats for critical activities will be always _____ a. One b. Zero c. Highest d. Same as duration of the activity

Last Answer : b. Zero

Description : The assignment problem a. Requires that only one activity be assigned to each resource b. Is a special case of transportation problem c. Can be used to maximize resources d. All of the above

Last Answer : d. All of the above

Description : While solving an assignment problem, an activity is assigned to a resource through a square with zero opportunity cost because the objective is to a. Minimize total cost of assignment b. Reduce the cost of ... to zero c. Reduce the cost of that particular assignment to zero d. All of the above

Last Answer : c. Reduce the cost of that particular assignment to zero

Description : In project crashing, as we systematically, crash the project, direct cost of project ______ a. Increases b. Decreases c. Remain same d. None of the above

Last Answer : a. Increases

Description : ______ are technique applied in project management a. CPM b. Assignment c. Transportation d. Decision theory

Last Answer : a. CPM

Description : The second longest path in the network diagram is called a. Alternate b. Feasible c. Sub-critical d. Critical

Last Answer : c. Sub-critical

Description : Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer. (A) A is correct but R is not correct (B) R is correct but A is not correct (C) Both A and R is correct (D) Both A and R is incorrect

Last Answer : (A) A is correct but R is not correct

Description : A project activity has several components as indicated below; S.  No. Activity Preceded by Duration (in  Weeks) 1 A - 8 2 B A 6 3 C A 12 4 D B 4 5 E D 5 6 F B 12 7 G E& F ... H 5 10 J I & G 6 d. Prepare a PERT chart, estimate the duration of the project and identify the  critical path.

Last Answer : PERT Diagram based on Activity on Arrow  .  E  D 5 G B 5 9 J, 6 A 6 F,12 I ,5 8 c 12 H 8 OR  PERT Diagram based on Activity on Node …………………….6 marks a. Critical Path: A-B-F-G-J …………………….1 mark  b. Estimated Project Duration: 41 weeks

Description : ......................... is activity oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : a. CPM

Description : Complete the following statement. As a project manager, Darrell is  excited that he is assigned to be in charge of the most important project  this year. After being chartered for the project, he ... c. prepare for the template to monitor project progress. d. estimate the entire project budget.

Last Answer : b. start to define and develop the stakeholder needs and requirements

Description : If in a LPP, the solution of a variable can be infinity large without violating the constraints, the solution is ___ a. Infeasible b. Unbounded c. Alternative d. None of the above

Last Answer : b. Unbounded

Description : 5. Operations Research was known as an ability to win a war without really going into a _____ a. Battle Field b. Fighting c. War d. Both a & b

Last Answer : d. Both a & b

Description : If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good (A) EF = ES + D (B) LS = LF - D (C) LF = LS + D (D) All the above

Last Answer : (D) All the above

Description : Which of the following statements is correct regarding float' for anactivity? a) Time between its earliest start time and earliest finish time b) Time between its latest start time and latest ... start time and earliest finish time d) Time between earliest finish time and latest finish time

Last Answer : d) Time between earliest finish time and latest finish time

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : If no. of rows are equal to number of columns and the matrix elements are Time elements then the problem is: a. Balanced and Minimization Transportation problem b. ... Transportation problem c. Balanced and Minimization Assignment problem d. Unbalanced and Minimization Assignment problem

Last Answer : c. Balanced and Minimization Assignment problem

Description : If cost, time, etc is given, then it is ________ a. Balanced problem b. Unbalanced problem c. Maximization problem d. Minimization problem

Last Answer : d. Minimization problem

Description : 40. Which of the following is a limitation associated with an LP model a. The relationship among decision variables is linear b. No guarantee to get integer valued solutions c. No considerations of effect of time & uncertainty on LP model d. All of the above

Last Answer : d. All of the above

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities

Description : Every combination of strategies determines an outcome known as _____ a. Regret b. Payoff c. Saddle point d. Profit matrix

Last Answer : b. Payoff

Description : The choice of the strategy is made by both the _________ simultaneously a. Decision maker b. Manager c. Competitor d. Player

Last Answer : Player

Description : A ______ occurs when each player selects one of his strategies a. Profit b. Decision c. Play d. Game

Last Answer : c. Play

Description : A ______ is the one in which the player selects more than one strategy with fixed probabilities before playing the game. a. Mixed strategy b. Pure strategy c. Complete strategy d. Impure strategy

Last Answer : d. Impure strategy