Pick up the incorrect statement from the following
a. The activity which consumes maximum time, is called a node
b. The activity is the time consuming part of a project
c. The beginning and end of a job, are called events
d. Logically and sequentially connected activities and events form a network
a. The activity which consumes maximum time, is called a node
b. The activity is the time consuming part of a project
c. The beginning and end of a job, are called events
d. Logically and sequentially connected activities and events form a network