Which one of the following is true for the Project Management Plan (PMP)?
a. The Project Management Plan is developed by the project manager and team and owned by the
sponsor.
b. A draft of the Project Management Plan is developed by the sponsor at the same time as the
business case.
c. The Project Management Plan is developed by the sponsor and owned by the project manager.
d. The Project Management Plan is developed by the project manager and team and owned
by the project manager.