The advantage of following the IEEE Standard for drawing up a
Project Management Plan (SPMP) – see IEEE Standard 1059.1 1987
– is
a) It is drawn up by representatives from major
development organisations
b) It is designed for all types of products
c) It is a framework that can be used irrespective of
process model or specific techniques
d) It can be tailored for each organisation for a
particular applicationarea, development team or
technique.
e) All of the above.