Explain the procedure of internal plastering a newly built brick wall.

1 Answer

Answer :

Procedure : The mix ratio of mortar in case of cement plastering depends upon the nature of the work to be plastered. For rich plastering work at sensitive places (e.g. in side bathrooms, W.C. etc.), 1:3 cement plaster mix is used. For general plastering of walls 1:4 to 1:8 cement mortar is used.

Preparing the surface

• Before applying the plaster, the surface of wall shall be cleaned, free from loose particles/dust and wet in advance.

• The joints of masonry are properly raked to a depth of 10 to 15 mm to provide key and bonding between wall and plaster.

• All the cavities and holes in the wall should be properly filled up in advance.

• When the surface is ready, plaster is applied.

Applying the plaster

• Cement plastering may be applied in one or two coats.

• In case plastering is to be done in two coats the first coat is applied as described below:

• The mortars screed or bands and patches (dots) of plaster of required thickness shall be made on the surface vertically and horizontally at center to center distance of 2 M and evenness of plastered surface shall be checked by plumb bob and plain wooden rule.

• The mortar is dashed against the prepared surface into a uniform thickness with the help of trowel.

• Surplus mortar is removed with the help of mason’s straight edge and then the mortar is pressed well with a wooden float so that mortar may fill in the joints of the masonry.

• The thickness of this coat should not be more than 16 mm.

• Before applying the second coat, the first coat is allowed to set but it should not become dry and it is also roughened with a scratching tool to provide key to the second coat.

• The second coat is then applied in a thin layer not exceeding 3 mm in thickness within48 hours.

• It is then well trowelled and rubbed perfectly smooth with the help of a steel float. It is then allowed to set for 2 days and cured for more than 8 to 10 days.

Related questions

Description : Describe the procedure for carrying out the ‘Plastering’ in cement mortar in two coats.

Last Answer : The mix ratio of mortar in case of cement plastering depends upon the nature of the work to be plastered.  For rich plastering work at sensitive places (e.g. in side bathrooms, W.C. etc.), 1:3 ... help of a steel float. It is then allowed to set for 2 days and cured for more than 7 days.

Description : Explain four defects in plastering with neat sketch.

Last Answer : Following are the defects in plastering: 1) Blistering of plastered surface: it is the defect in which small patches of plaster are swelled out from the plastered surface. 2 ... defect in which there is complete dislocation of some portion of plastered surface which forms the patches. 

Description : Describe the procedure of laying a floor finish on a newly constructed slab.

Last Answer : 1. Slab is cleared off from loose mortar deposited during plaster work and level the surface. 2. Chalk out the marking on wall @ 0.6 m above the slab surface in one level. 3. Construct mortar dots at four ... and lay the tile in line and level. 8. Repeat point no 7 procedure up to door corner.

Description : State any four precautions to be taken while plastering.

Last Answer : i. Before application of the plastering, the surface must be clean and free of dirt, oil, or other elements which may interfere with bonding. ii. Smooth or non-absorbent surfaces should be prepared. iii. ... or vertical line at the end of the day or if work requires to be suspended for any reason.

Description : Pick up the correct statement from the following: (A) A mortar joint having a concave finishing in brick masonry, is called keyed joint (B) A mortar joint projecting beyond the face of a masonry wall, is ... (C) A mortar joint having a recess in it, is called ruled joint (D) All the above

Last Answer : Option D

Description : Draw a neat labeled sectional view showing different components of building from foundation to parapet, for a load bearing brick masonry wall.

Last Answer : Draw a neat labeled sectional view showing different components of building from foundation to parapet, for a load bearing brick masonry wall.

Description : Explain the procedure of preparation of surface along with the method of application of color wash paint on the wall.

Last Answer : The correct preparation of surface plays an important role in preserving the properties and life of the paint. For these the procedure is as follows: 1.If the receiving surface is rough, it should be made smooth ... of color wash paint on the wall. 1.By Brushing. 2.By Spraying. 3. By Rollers.

Description : The position of a brick when laid on its side 9 cm × 9 cm with its frog in the vertical plane, is called (A) Brick on edge (B) Brick on end (C) Brick on bed (D) Brick held vertically

Last Answer : Option B

Description : Differentiate between brick masonry and stone masonry

Last Answer : Sr. no. Brick masonry Stone masonry 1 It is cheaper than stone masonry It is stronger than Brick masonry 2 It is cheaper in places where clay is available It is ... easy to apply any finishing to Brick surface. It is difficult to apply any finishing to stone surface

Description : As a ‘Supervisor’, state precautionary measures you will observe while constructing brick masonry, along with their reasons.

Last Answer : Following Precautionary measures are to be observe as a supervisor while constructing brick masonry: 1. Bricks should be as per the specification. The bricks should be well burnt, reddish in colour, sound and hard ... is used and for a period of about one to two weeks, if cement mortar is used.

Description : Compare stone masonry construction with brick masonry construction.

Last Answer : STONE MASONRY  BRICK MASONRY 1. Stone masonry is stronger and more durable than brick masonry 1. Brick masonry is less stronger and less durable than stone masonry. 2. ... other hand is considered unsuitable in the construction of piers, docks, dams and other marine structure.

Description : Compare brick masonry and stone masonry used in building construction.

Last Answer : Sr. No. Brick Masonry Stone Masonry 1 It is less stronger than stone masonry. It is stronger than brick masonry. 2 It is cheaper in places where clay is available ... is used Double scaffolding is used 12 Plastering is required  Plastering is not required

Description : Describe the procedure of water proofing used in slabs stating its importance in building construction.

Last Answer : Following is the stepwise procedure effectively applied in treatment of brick bat coba.  1 All existing treatment or coating on roof slab top is initially removed and surface is cleaned by hard wire brush ... surface is marked with 300 mm false squares The curing is done on next day. 

Description : Describe the procedure for layout of load bearing structure by center – line method.

Last Answer : 1. From the plan (fig 1), the center line of the walls are calculated. Then the center lines of the rooms are set out by setting perpendiculars in the ratio 3:4:5. Suppose the corner points ... lime or by with furrow with spade. 6. A theodolite should be used for accurate center line marking. 

Description : A wall constructed to resist the pressure of an earth filling, is called (A) Retaining wall (B) Breast wall (C) Buttress (D) Parapet wall

Last Answer : Option A

Description : The type of pointing in which upper side of mortar joints is kept about 12 mm inside the face of the masonry and bottom is kept flushed with face of wall, is (A) Truck pointing (B) Recessed pointing (C) Struck pointing (D) Grooved pointing

Last Answer : Option C

Description : A wall constructed with stones to protect slopes of cuttings in natural ground from the action of weathering agents, is called (A) Retaining wall (B) Breast wall (C) Buttress (D) Parapet wall

Last Answer : Option B

Description : Suggest commonly adopted sizes of door for: 1) Internal door of residential bldg. 2) Door of garage for car park

Last Answer :  1) Internal door of residential bldg. - 900 X 2100 mm 2) Door of garage for car park. – 2250 X 2250 mm

Description : For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is (A) 0.200 m3 (B) 0.247 m3 (C) 0.274 m3 (D) 0.295 m

Last Answer : (C) 0.274 m3

Description : For plastering the exposed brick walls, the cement sand mortar should be (A) 1 : 2 (B) 1 : 3 (C) 1 : 4 (D) 1 : 6

Last Answer : Answer: Option C

Description : Explain the requirements of good formwork with names and materials proposed for beam of size 300 X 450 mm with neat labeled sketch.  

Last Answer : Requirements of good formwork:- 1. It should be adequately strong to withstand an extensive variety of dead and live loads. For instance, self-weight, weight of reinforcement, weight of wet concrete, loads of ... of concreting. 8. It should be lightweight. 9. It should be easy to remove.

Description : Explain raft foundation with neat sketch and explain its suitability. 

Last Answer : Raft Footing: It is suitable where ground is soft. Clayey or marshy having low bearing capacity, and where sub soil water conditions are uncertain. The raft foundation is also used to reduce settlement below highly compressible soils

Description : Define shoring. Enlist types of shoring. Explain any one type with neat sketch.

Last Answer : Shoring:- Shoring is the construction of a temporary structure to support temporarily an unsafe structure. These support walls laterally. Shoring can be used when walls bulge out, when walls crack due to ... of the structure above and transfer same to the ground on firm foundation below. 

Description : Explain the types of probable cause of non-structural cracks observed in building construction along with preventive measures for any one of crack. 

Last Answer : Cause of cracks:   Cause # 1. Movement Due To Creep: Creep of a material is defined as the property due to which the material continues to deform with time under sustained stress. ... contraction and slip joints at appropriate location. Painting top roof with reflective finish such as white wash.

Description : Explain the requirement of good formwork.

Last Answer : Requirements of good formwork : 1. It should be strong enough to resist the pressure or the weight of the fresh concrete and the superimposed loads due to equipment, men etc., if any. This requires ... be less. 11. It should be easily possible to give the required geometrical shape to the form.

Description : Explain timbering and strutting with a neat sketch.

Last Answer : A method of giving the temporary support to the side of deep trench or when subsoil is loose or very soft is known as timbering (i.e. shoring) and strutting. It consists of timber planks and strut to give ... . 2. Box sheeting 3. Vertical sheeting 4. Runner system 5. Sheet piling  

Description : Explain the causes of non – structural cracks in building construction and remedial measures.

Last Answer : The important causes responsible for cracks in building are : 1. Due to movement of ground. 2. Due to temperature variation. 3. Due to moisture changes. 4. Due to effect of ... be good workmanship. 6. Uneven settlement of foundation should be avoided by resting foundation on hard strata.

Description : Explain the necessity of ‘Scaffolding and Shoring’.

Last Answer : Necessity of scaffolding: 1. To provide a working platform so that the worker can stand on the platform and do the work easily & safely 2. To provide a platform for placing material & logistics( ... have been made stable, or which might become unstable by reason of work carried out on or near them

Description : Explain in brief Guniting and Grouting.

Last Answer : Guniting-Process of applying cement and sand (1:3) mixture under pressure (20 -30N/cm2)on concrete surface in order to repair concrete work. It is a process of repairing concrete work or ... masonry. The process of placing a grout material into cavities of concrete or masonry is called grouting.

Description : Enlist different types of staircase. Explain any one type with a neat sketch.

Last Answer : Types of Staircase: 1. Straight Stair 2. Dog legged Stair 3. Quarter turn Stair 4. Open well Stair 5. Three quarter turn Stair 6. Bifurcated Stair 7. Geometrical Stair 8. Circular ... . This well may be rectangular or of any geometrical shape and it can be used for fixing lift.

Description : Explain timbering and strutting in excavation with neat sketch.

Last Answer : A method of giving the temporary support to the side of deep trench or when subsoil is loose or very soft is known as timbering (i.e. shoring) and strutting. It consists of timber planks and strut to give ... sheeting 3. Vertical sheeting 4. Runner system  5. Sheet Piling 

Description : Explain the foundation layout of load bearing structure by centre-line method.

Last Answer : Foundation layout of load bearing structure by centre line method: 1.One corner of the foundation plan is fixed by measuring the distance from the border of the plot and wooden peg with a nail on ... are marked with nail / cross line on plaster for further reference to establish centre line.

Description : Raft foundation are generally preferred to when the area required for individual footing, is more than (A) 25% to total area (B) 30% of total area (C) 40% to total area (D) 50% of total area

Last Answer : Option D

Description : Pick up the correct statement from the following: (A) Isolated footing is provided under column to transfer the load safely to soil bed (B) Column footings may have steps or projections in the ... ) Heavily loaded column base must be provided steel reinforcement in both directions (D) All the above

Last Answer : Option D

Description : The pile provided with one or more bulles in its vertical shaft, is generally known as (A) Under-ream pile (B) Friction pile (C) Bearing pile (D) Sheet pile

Last Answer : Option A

Description : The Auger borings are not common (A) In soils that require lateral support (B) In cohesive soils (C) In soft soils (D) None of the above

Last Answer : Option A

Description : Pitched and sloping roofs are suitable for (A) Coastal regions (B) Plain regions (C) Covering large areas (D) All of the above

Last Answer : Option A

Description : Pick up the correct statement from the following: (A) The pile driven in sand is called sand pile (B) The drilled hole filled with sand is called sand pile (C) The sand piles are used for bearing purposes (D) None of these

Last Answer : Option A

Description : The foundation which consists of a thick reinforced cement slab covering whole area to support heavy concentrated structural loads, is known as (A) Combined footing (B) Strap footing (C) Raft footing (D) None of these

Last Answer : Option C

Description : For different layers of cement concrete floor. Pick up the incorrect statement from the following: (A) The lowest layer consists of consolidated ground (B) A 10 cm thick clean sand is laid on consolidated ground (C) ... sand (D) A 10 cm thick cement concrete (1 : 2 : 4) is laid on top layer

Last Answer : Option D

Description : Higher pitch of the roof (i) Results in stronger roof (ii) Results in weaker roof (iii) Requires more covering material (iv) Requires less covering material The correct answer is (A) (i) and (iii) (B) (i) and (iv) (C) (ii) and (iii) (D) (ii) and (iv)

Last Answer : Option A

Description : Pick up the correct statement from the following: (A) D.P.C. should be continuous (B) D.P.C. should be of good impervious material (C) D.P.C. may be horizontal or vertical (D) All the above

Last Answer : Option D

Description : The inclined surface of an abutment to receive the arch, is known as (A) Skew back (B) Soffit (C) Spandril (D) Haunch

Last Answer : Option A

Description : The pile which supports the load due to friction between pile face and surrounding soil, is generally known as (A) Bearing pile (B) Friction pile (C) Sheet pile (D) Battered pile

Last Answer : Option B

Description : The form work from the slabs excluding props, can be removed only after (A) 1 day (B) 4 days (C) 7 days (D) 14 days

Last Answer : Option B

Description : Cast iron piles (A) Are suitable for works under sea water (B) Resist shocks or vibrations (C) Are suitable for use as batter piles (D) Are useful for heavy vertical loads

Last Answer : Option D

Description : The form work from the slabs excluding props, can be removed only after (A) 1 day (B) 4 days (C) 7 days (D) 14 days

Last Answer : Answer: Option B

Description : Cast iron piles (A) Are suitable for works under sea water (B) Resist shocks or vibrations (C) Are suitable for use as batter piles (D) Are useful for heavy vertical loads

Last Answer : Answer: Option D

Description : Suggest relevant type of foundation with sketch for educational building on black cotton soil with justification. 

Last Answer : Black cotton soil- Pile foundation. In case the depth of black cotton soil is more, the following type of foundation may be provided 1. Strip or pad foundation 2. Pier foundation with ... of expansive soil. They are bored cast-in-situ concrete piles having bulb shaped enlarged base.