Define shoring. Enlist types of shoring. Explain any one type with neat sketch.

1 Answer

Answer :

Shoring:- Shoring is the construction of a temporary structure to support temporarily an unsafe structure. These support walls laterally. Shoring can be used when walls bulge out, when walls crack due to unequal settlement of foundation and repairs are to be carried out to the cracked wall, when an adjacent structure needs pulling down, when openings are to be made in newly or enlarged in a wall.

Types of shoring

1.Raking shore

2.Flying shore

3.Dead shore


1. Raking Shoring

In this method, inclined members known as rakers are used to give lateral supports to walls. A raking shore consists of the following components:

1.Rakers or inclined member

2.Wall plate

3.Needles

4.Cleats

5.Bracing

6.Sole plate

image


2. Flying Shoring : Flying shores is a system of providing temporary supports to the partly walls of the two buildings where the intermediate building is to be pulled down and rebuilt . All types of arrangements of supporting the unsafe structure in which the shores do not reach the ground come under this category. The flying shore consists of wall plates, needles, cleats, horizontal struts (commonly known as horizontal shores) and inclined struts arranged in different forms which varies with the situation. In this system also the wall plates are placed against the wall and secured to it. A horizontal strut is placed between the wall plates and is supported by a system of needle and cleats. The inclined struts are supported by the needle at their top and by straining pieces at their feet. The straining piece is also known as straining sill and is spiked to the horizontal shore. The width of straining piece is the same as that of the strut. When the distance between the walls (to be strutted apart) is considerable, a horizontal shore can not be safe and a trussed framework of members is necessary to perform the function of flying shore.

image


3. Dead Shore OR Vertical Shore : Dead shore is the system of shoring which is used to render vertical support to walls and roofs, floors, etc when the lower part of a wall has been removed for the purpose of providing an opening in the wall or to rebuild a defective load bearing wall in a structure.The dead shore consists of an arrangement of beams and posts which are required to support the weight of the structure above and transfer same to the ground on firm foundation below. 

image

Related questions

Description : Enlist different types of staircase. Explain any one type with a neat sketch.

Last Answer : Types of Staircase: 1. Straight Stair 2. Dog legged Stair 3. Quarter turn Stair 4. Open well Stair 5. Three quarter turn Stair 6. Bifurcated Stair 7. Geometrical Stair 8. Circular ... . This well may be rectangular or of any geometrical shape and it can be used for fixing lift.

Description : Explain the necessity of ‘Scaffolding and Shoring’.

Last Answer : Necessity of scaffolding: 1. To provide a working platform so that the worker can stand on the platform and do the work easily & safely 2. To provide a platform for placing material & logistics( ... have been made stable, or which might become unstable by reason of work carried out on or near them

Description : Define facing, backing, hearting and Through stone with neat sketch.

Last Answer : Facing: The material used in the face of the wall is known as facing. Backing: The material used in the back of the wall is known as backing. Hearting: The inner portion of the wall ... A header stone having length equal to wall width is placed across the wall casted through stone.

Description : List two purposes of shoring

Last Answer : Purposes of Shoring :  Shoring is the construction of a temporary structure to support temporarily an unsafe structure. 1. To repair bulging out wall. 2. To repair the cracks in the wall. 3. To dismantle adjacent structure. 4. To make openings in existing wall. 

Description : Explain the requirements of good formwork with names and materials proposed for beam of size 300 X 450 mm with neat labeled sketch.  

Last Answer : Requirements of good formwork:- 1. It should be adequately strong to withstand an extensive variety of dead and live loads. For instance, self-weight, weight of reinforcement, weight of wet concrete, loads of ... of concreting. 8. It should be lightweight. 9. It should be easy to remove.

Description : Explain raft foundation with neat sketch and explain its suitability. 

Last Answer : Raft Footing: It is suitable where ground is soft. Clayey or marshy having low bearing capacity, and where sub soil water conditions are uncertain. The raft foundation is also used to reduce settlement below highly compressible soils

Description : Explain four defects in plastering with neat sketch.

Last Answer : Following are the defects in plastering: 1) Blistering of plastered surface: it is the defect in which small patches of plaster are swelled out from the plastered surface. 2 ... defect in which there is complete dislocation of some portion of plastered surface which forms the patches. 

Description : Explain timbering and strutting with a neat sketch.

Last Answer : A method of giving the temporary support to the side of deep trench or when subsoil is loose or very soft is known as timbering (i.e. shoring) and strutting. It consists of timber planks and strut to give ... . 2. Box sheeting 3. Vertical sheeting 4. Runner system 5. Sheet piling  

Description : Explain timbering and strutting in excavation with neat sketch.

Last Answer : A method of giving the temporary support to the side of deep trench or when subsoil is loose or very soft is known as timbering (i.e. shoring) and strutting. It consists of timber planks and strut to give ... sheeting 3. Vertical sheeting 4. Runner system  5. Sheet Piling 

Description : Define settlement of foundation and its types. Enlist various causes and suggest remedial measures for the same.

Last Answer : Settlement of foundation: Due to the self-weight and the live load of the structure and due to compressibility of the soil supporting the foundation of the structure, settlement of the ... of earthquake loads and other earthquake resisting methods during design and construction of buildings.

Description : Describe in brief with neat sketch: i) English bond ii) Flemish bond

Last Answer : English bond : The Bond with alternate courses of headers and stretchers with a closer placed next to quoin header is called as the English Bond. Points Should be Remembered for English bond: 1. A ... . 4. Flemish Bond is slightly economical as a number of brick bats can be used.

Description : Enlist any four types of floor finishes.

Last Answer : Four types of floor finishes:- 1)Shahabad flooring 2) Kota flooring 3) Marble flooring 4) Granite flooring 5) Kadappa 6) Mosaic tiles 7) Pavement blocks 8)Tiled flooring 9) Tremix floor 10)Vitrified tiles 11) IPS 12) Ceramic

Description : Enlist and draw various fixtures and fastenings for doors and windows. 

Last Answer : Types of Fixtures and Fastenings for Doors and Windows Hinges Hinge is fixture which helps the door to rotate freely along its axis. There are so many types of hinges are there which are as ... them are padlock, mortise lock, rim lock, cupboard lock and lever handle lock etc.

Description : Enlist functions of Sill and Lintel

Last Answer : Functions of Sill: 1. To prevent the exposed masonry wall top from weathering. 2. To support the frame of window / Door. 3. To give good finish to wall openings Functions of Lintel: 1. To transfer the ... to side. 2. It holds chajja. 3. To prevent load on frame. 4. To strengthen the wall.

Description : Suggest relevant type of foundation with sketch for educational building on black cotton soil with justification. 

Last Answer : Black cotton soil- Pile foundation. In case the depth of black cotton soil is more, the following type of foundation may be provided 1. Strip or pad foundation 2. Pier foundation with ... of expansive soil. They are bored cast-in-situ concrete piles having bulb shaped enlarged base.

Description : Suggest relevant type of foundation with sketch for a residential building with Marshy soil at greater depth with justification and explanation.

Last Answer : Raft foundation is suitable for a residential building with Marshy soil at greater depth It is suitable where ground is soft, Clayey or marshy having low bearing capacity and where sub soil water ... of thick reinforced concrete slab covering the entire area of the bottom of the structure.

Description : Draw neat sketches of any three shallow foundations and suggest suitability of them for different loading and soil conditions.

Last Answer : Types of shallow foundation with their suitability: 1. Wall Footing: Wall footings are used for individual columns, walls and bridge piers where the bearing soil layer is within 3m (10 feet) from the ground surface. Soil ... bearing capacity of soil.    9. Slab Base:   10.Gusseted base:  

Description : Draw a neat labeled sectional view showing different components of building from foundation to parapet, for a load bearing brick masonry wall.

Last Answer : Draw a neat labeled sectional view showing different components of building from foundation to parapet, for a load bearing brick masonry wall.

Description : Enlist different types of traffic island and explain any one in brief with neat sketch.

Last Answer : The different types of traffic island are as follow: (1) Rotary or central islands. (2) Channelising or refuse islands. (1) Rotary or central islands: A traffic island constructed in ... each site of road intersection. A few typical designs of Channelising islands are illustrated below:

Description : Explain the types of probable cause of non-structural cracks observed in building construction along with preventive measures for any one of crack. 

Last Answer : Cause of cracks:   Cause # 1. Movement Due To Creep: Creep of a material is defined as the property due to which the material continues to deform with time under sustained stress. ... contraction and slip joints at appropriate location. Painting top roof with reflective finish such as white wash.

Description : Define substructure and superstructure. Give their components also.

Last Answer : Substructure: - A part of structure lying below the ground surface is known as substructure. components of substructure :-1) foundation Superstructure: - A part of structure lying above the ground surface is called ... Beam 6) Roof 7) Doors 8) Windows 9) Lintel 10)Sill 11) Staircase 12) Parapet. 

Description : Define the job layout and site clearance.

Last Answer : job layout: A plan in which the arrangement for placing site office, store room, labour quarter, medical aid center, godowns for keeping construction material and other facility are properly prepared is ... plant, roots, old construction etc. to prepare a leveled ground for marking of layout.  

Description : Define the terms Newel post and Headroom in vertical communication.

Last Answer : Newel post : This is the vertical member which is placed at the ends of flights to connect the end of strings and hand rail.  Headroom : The vertical distance between the nosing of one flight and bottom of flight immediately above is known as the headroom.

Description : Define ‘Formwork’ in building construction.

Last Answer : Formwork:- The temporary casing provided to support concrete is known as formwork.

Description : Define the term ‘Landing and Pitch’ used in stair.

Last Answer : Landing: - It is flat platform at the top or bottom of a flight between the floors. Pitch: - It is the angle which the line of nosing of the stair makes with floor.

Description : Define the terms substructure and superstructure used in building construction.

Last Answer : Substructure: - A part of structure lying below the ground surface is known as substructure.  Superstructure: - A part of structure lying above the ground surface is called superstructure.

Description : Define formwork and state the requirements of a good formwork.

Last Answer : Formwork: It is a temporary ancillary construction used as a mould for the structure, in which concrete is placed and in which it hardens and matures. Following are the requirements of good formwork:- ... be constructed so tight that it does not allow the cement paste to leak through the joints.

Description : Define underpinning

Last Answer : Underpinning : The process of placing a new foundation under an existing one or strengthening an existing foundation is called underpinning of foundation.

Description : Define job layout

Last Answer : Job Layout: A systematic arrangement of various jobs / resources required for construction project around it, are chalked out on drawing so as to achieve economy, Safety & convenience.

Description : Enlist any four operations carried out in forging process and explain fullering with neat sketch.

Last Answer : Operations carried out in forging process:  a) Upsetting b) Drawing Down c) Setting down d) Welding e) Bending f) Cutting g) Punching Fullering: In ... sledge hammer. The force is applied on the top fuller which results in decreasing the cross section at that point.

Description : Suggest the roofing material for various types of pitched roofs with justification.

Last Answer : Roof covering is an essential component of pitched roof to be placed over the framework Types of roof covering Thatch covering: It is a very old roofing method and has been used in both ... slate roof pitches as low as 15°. Light weight roofing: Used for wide span industrial structures

Description : Explain the procedure of preparation of surface along with the method of application of color wash paint on the wall.

Last Answer : The correct preparation of surface plays an important role in preserving the properties and life of the paint. For these the procedure is as follows: 1.If the receiving surface is rough, it should be made smooth ... of color wash paint on the wall. 1.By Brushing. 2.By Spraying. 3. By Rollers.

Description : Explain the requirement of good formwork.

Last Answer : Requirements of good formwork : 1. It should be strong enough to resist the pressure or the weight of the fresh concrete and the superimposed loads due to equipment, men etc., if any. This requires ... be less. 11. It should be easily possible to give the required geometrical shape to the form.

Description : Explain the causes of non – structural cracks in building construction and remedial measures.

Last Answer : The important causes responsible for cracks in building are : 1. Due to movement of ground. 2. Due to temperature variation. 3. Due to moisture changes. 4. Due to effect of ... be good workmanship. 6. Uneven settlement of foundation should be avoided by resting foundation on hard strata.

Description : Explain in brief Guniting and Grouting.

Last Answer : Guniting-Process of applying cement and sand (1:3) mixture under pressure (20 -30N/cm2)on concrete surface in order to repair concrete work. It is a process of repairing concrete work or ... masonry. The process of placing a grout material into cavities of concrete or masonry is called grouting.

Description : Explain the procedure of internal plastering a newly built brick wall.

Last Answer : Procedure : The mix ratio of mortar in case of cement plastering depends upon the nature of the work to be plastered. For rich plastering work at sensitive places (e.g. in side bathrooms, W.C. etc.), 1:3 ... a steel float. It is then allowed to set for 2 days and cured for more than 8 to 10 days.

Description : Explain the foundation layout of load bearing structure by centre-line method.

Last Answer : Foundation layout of load bearing structure by centre line method: 1.One corner of the foundation plan is fixed by measuring the distance from the border of the plot and wooden peg with a nail on ... are marked with nail / cross line on plaster for further reference to establish centre line.

Description : The type of pointing in which upper side of mortar joints is kept about 12 mm inside the face of the masonry and bottom is kept flushed with face of wall, is (A) Truck pointing (B) Recessed pointing (C) Struck pointing (D) Grooved pointing

Last Answer : Option C

Description : State the classification of building as per type of construction. 

Last Answer : Following are the classification of building as per type of construction: 1. Residential Buildings. 2. Public Buildings. 3. Institutional Buildings. 4. Assembly building. 5. Business Buildings. ... . Storage Buildings. 8. Hazardous Buildings. 9. Framed structure. 10. Load bearing structure

Description : Raft foundation are generally preferred to when the area required for individual footing, is more than (A) 25% to total area (B) 30% of total area (C) 40% to total area (D) 50% of total area

Last Answer : Option D

Description : Pick up the correct statement from the following: (A) Isolated footing is provided under column to transfer the load safely to soil bed (B) Column footings may have steps or projections in the ... ) Heavily loaded column base must be provided steel reinforcement in both directions (D) All the above

Last Answer : Option D

Description : The pile provided with one or more bulles in its vertical shaft, is generally known as (A) Under-ream pile (B) Friction pile (C) Bearing pile (D) Sheet pile

Last Answer : Option A

Description : The Auger borings are not common (A) In soils that require lateral support (B) In cohesive soils (C) In soft soils (D) None of the above

Last Answer : Option A

Description : Pitched and sloping roofs are suitable for (A) Coastal regions (B) Plain regions (C) Covering large areas (D) All of the above

Last Answer : Option A

Description : A wall constructed to resist the pressure of an earth filling, is called (A) Retaining wall (B) Breast wall (C) Buttress (D) Parapet wall

Last Answer : Option A

Description : Pick up the correct statement from the following: (A) The pile driven in sand is called sand pile (B) The drilled hole filled with sand is called sand pile (C) The sand piles are used for bearing purposes (D) None of these

Last Answer : Option A

Description : The position of a brick when laid on its side 9 cm × 9 cm with its frog in the vertical plane, is called (A) Brick on edge (B) Brick on end (C) Brick on bed (D) Brick held vertically

Last Answer : Option B

Description : The foundation which consists of a thick reinforced cement slab covering whole area to support heavy concentrated structural loads, is known as (A) Combined footing (B) Strap footing (C) Raft footing (D) None of these

Last Answer : Option C

Description : For different layers of cement concrete floor. Pick up the incorrect statement from the following: (A) The lowest layer consists of consolidated ground (B) A 10 cm thick clean sand is laid on consolidated ground (C) ... sand (D) A 10 cm thick cement concrete (1 : 2 : 4) is laid on top layer

Last Answer : Option D