If code of a fracture is OFW-422 then it means.
(i) AT welding with transverse crack.
(ii) Flash butt welding with transverse crack.
(iii) At welding with horizontal crack.*
(iv) None of the above.

1 Answer

Answer :

(iii) At welding with horizontal crack.*

Related questions

Description : Where Portion sample tests(test piece) should be conducted? (i) At desire by RDSO (ii) At Zonal CMT’s organisation or the Flash Butt Welding plant. * (iii) In RDSO campus (iv) As decided by in charge of the plant

Last Answer : At Zonal CMT’s organisation or the Flash Butt Welding plant.

Description : Tandem rig test with 450 probe for AT weld detects. (i) Horizontal longitudinal defect in weld. (ii) Vertical oriented defect in AT weld.* (iii) Transverse defect in AT weld. (iv) Defect in flange of AT welds.

Last Answer : (ii) Vertical oriented defect in AT weld.*

Description : Which gauge is used to measure the height of rail at the time of aligning of rails for AT welding? (i) Height gauge.* (ii) Vertical gauge (iii) Horizontal gauge (iv) As decided by site supervisor

Last Answer : (iv) As decided by site supervisor

Description : Min. breaking load of 60kg weld during transverse breaking load test is? (i) 110 MT (ii) 115 MT* (iii) 90 MT (iv) 120 MT

Last Answer : (ii) 115 MT*

Description : Min. breaking load of 52kg weld during transverse breaking load test is? (i) 90MT* (ii) 100 MT (iii) 110 MT (iv) 120 MT

Last Answer : (i) 90MT*

Description : Minm. deflection during transverse breaking load test is? (i) 5 mm (ii) 10 mm (iii) 15 mm* (iv) 20 mm

Last Answer : (iii) 15 mm*

Description : Side looking 700 2MHZ probe is tested for detecting. (i) Flaw in head (ii) Flaw in web (iii) Half moon crack in flange.* (iv) For all above.

Last Answer : iii) Half moon crack in flange

Description : In AT welding process what is the role of asbestos powder & slag ? (i) To separate closing pin from portion* (ii) To hold the portion (iii) Both above are correct (iv) None of the above

Last Answer : (i) To separate closing pin from portion*

Description : In AT welding process what is the role of closing pin ? (i) To hold the portion before melt (ii) To hold the asbestos powder & slag (iii) Both above are correct* (iv) None of the above

Last Answer : (iii) Both above are correct*

Description : What is the testing frequency of new AT weld ? (i) Just after the welding (ii) After 7 days of welding (iii) With in the one month of welding* (iv) None of the above

Last Answer : iii) With in the one month of welding*

Description : In how many time final grinding should be done of new AT weld ? (i) Just after the welding (ii) After 8 hrs of welding (iii) With in 24 hrs* (iv) None of the above

Last Answer : iii) With in 24 hrs*

Description : In how many time rough riding should be done of new AT weld ? (i) Just after the welding* (ii) After 8 hrs of welding (iii) After 24 hrs (iv) None of the above

Last Answer : i) Just after the welding*

Description : How many detonators are planted during protection of track for welding site ? (i) One (ii) Two (iii) Three* (iv) None of the above

Last Answer : iii) Three*

Description : Ist detonator is planted at a distance of (i) 1200 Mt. from welding site .* (ii) 600 mtrs from welding site (iii) 30 mtrs from welding site (iv) None of the above

Last Answer : (i) 1200 Mt. from welding site .*

Description : Banner flag is planted at a distance of (i) At the site of work (ii) At 1200 mtrs from welding site (iii) At 30 mtrs from welding site (iv) 600 Mt. from welding site .*

Last Answer : iv) 600 Mt. from welding site .

Description : Weather date of welding is marked on weld? (i) Yes (ii) As decided by the site supervisor (iii) No* (iv) None of the above

Last Answer : (iii) No*

Description : Rails used for A T Welding shall not normally be welded? (i) 20 years old . (ii) 30 years old (iii) 40 years old (iv) 50 years old*

Last Answer : iv) 50 years old*

Description : Name the paint used in A.T. Welding painting? (i) Black Paint (ii) Bituminous black IS:9862-1981.* (iii) Any type of black paint (iv) None of the above

Last Answer : (ii) Bituminous black IS:9862-1981.*

Description : When was the collar painting done ? (i) After the welding * (ii) after one week of welding (iii) After 15 days of welding (iv) None of the above

Last Answer : (i) After the welding *

Description : Last flag man is deputed at which distance from last detonator during protection of welding site . (i) 30 mts (ii) 50 mts (iii) 45 (iv) 60 mts

Last Answer : (iv) 60 mts

Description : What will happen if slag is not used above the layer of asbestos powder? (i) Auto tapping* (ii) High welding (iii) Low welding (iv) Nothing will happen

Last Answer : (i) Auto tapping*

Description : After AT Welding First train is to be passed after ? (i) 20 Minutes from pouring of weld metal. (ii) 35 Minutes from pouring of weld metal. (iii) 30 Minutes from pouring of weld metal.* (iv) 25 Minutes from pouring of weld metal.

Last Answer : (iii) 30 Minutes from pouring of weld metal.*

Description : Weather traffic block is required for execution of AT Welding? (i) Yes.* (ii) No (iii) As decided by site supervisor (iv) As per site condition

Last Answer : (i) Yes.

Description : Weather protection of track is required during block for execution of AT Welding? (i) Yes.* (ii) No (iii) As decided by site supervisor (iv) As per site condition

Last Answer : (i) Yes.*

Description : What are the recognized systems for pre heating of rails ends for AT Welding? (i) Oxygen –LPG & Compressed air petrol both* (ii) Only Oxygen –LPG (iii) Only Compressed air petrol both (iv) both are correct

Last Answer : ) Oxygen –LPG & Compressed air petrol both*

Description : Name the material which is separated from molten steel during chemical reaction of A.T welding? (i) Aluminium oxide (slag). * (ii) Ferrous Oxide (iii) Aluminium (iv) Ferrous

Last Answer : (i) Aluminium oxide (slag). *

Description : What is Pre Heating Temperature of rail ends in AT Welding? (i) 300 ± 20oC (ii) 400 ± 20oC (iii) 500 ± 20oC (iv) 600 ± 20oC *

Last Answer : (iv) 600 ± 20oC *

Description : During AT welding reaction is ? (i) Exothermic .* (ii) Endothermic (iii) No Reaction (iv) Heating

Last Answer : (i) Exothermic .*

Description : Type of competency certificate issued after TW-1 course? (i) Competency for two years (ii) Provisional competency.* (iii) Competency for six months (iv) Competency to do welding independently

Last Answer : (ii) Provisional competency.*

Description : How rejected portion are to be disposed-off? (i) By Igniting 5 Portions at a time in pit away from store?* (ii) By throwing them away (iii) By dispose off in a pit (iv) By using it in Branch/Yard lines for welding

Last Answer : (i) By Igniting 5 Portions at a time in pit away from store?*

Description : In new Rail as well as second hand rails how much end bends of the rails in vertical are permitted when checked with one meter straight edge before welding? (i) +0.5mm, -0 mm in vertical * (ii) +0.2mm, -.3 mm in vertical (iii) +0.3mm, -2 mm in vertical (iv) 0 mm, +.5 mm in vertical

Last Answer : (i) +0.5mm, -0 mm in vertical *

Description : In new Rail as well as second hand rails how much end bends of the rails in lateral direction are permitted when checked with one metre straight edge before welding? (i) ± 0.2 mm in lateral direction (ii) ± 0.3 mm in lateral direction (iii) ± 0.5 mm in latera

Last Answer : (iii) ± 0.5 mm in latera

Description : If digital DRT is calibrated for 300 mm longitudinal wave using 00 double crystal probe then 60kg rail ---------peak will appear at (i) 5.2 (ii) 5.7* (iii) 7.8 (iv) 8.6

Last Answer : ii) 5.7*

Description : The physical quantity, which oscillates in most waves, is (i) mass (ii) energy (iii) Amplitude* (iv) wavelength

Last Answer : iii) Amplitude*

Description : The amplitude of a wave is ______. (i) the distance the wave moves in one second (ii). the distance the wave moves in one time period of the wave (iii) the maximum distance moved by the medium particles on either side of the mean position* (iv) the distance equal to one wave length

Last Answer : iii) the maximum distance moved by the medium particles on either side of the mean position*

Description : The frequency of a wave travelling at a speed of 500 ms-1 is 25 Hz. Its time period will be ______. (i) 20 s (ii) 0.05 s (iii) 25 s (iv) 0.04 s

Last Answer : (iv) 0.04 s

Description : During periodic testing of an AT weld with 700 probe, a bunch of moving signals of less than 40% but more than 10% is observed in the head of weld, the joint will be. (i) Good joint.* (ii) DFWR (iii) DFWO (iv) OBSW

Last Answer : i) Good joint.*

Description : On a branch line one new AT Weld with 00 probe shows a signal of 58 is. (i) DFWO* (ii) DFWR (iii) IMRW (iv) OBSW

Last Answer : i) DFWO*

Description : DFWR weld shall be replaced. (i) Within 2 months of detection. (ii) Within 1 year of detection. (iii) Within 3 months of detection.* (iv) after 3 days of detection.

Last Answer : (iii) Within 3 months of detection.*

Description : Marking of DFWO weld is. (i) Two red point circle on both faces of weld.* (ii) Two red point cross on both faces of weld. (iii) One red point circle on both faces of weld. (iv) None of the above.

Last Answer : i) Two red point circle on both faces of weld.*

Description : For rolling mark 60 kg/Sail/X/2010 the first testing in the field after initial testing of rails in rail manufacturing plant, will be done. (i) After test free period of 25%. (ii) After passage of every 40 ... period.* (iii) After passage of 200 GMT. (iv) On the basis of annual GMT of the section.

Last Answer : (ii) After passage of every 40 GMT traffic during test free period.*

Description : The gap between probing face and probing shoe should be. (i) 0.4 mm (ii) 0.2mm * (iii) 3mm (iv) 1mm.

Last Answer : (ii) 0.2mm *

Description : Sensitivity calibration against temp. variation shall be carried out. (i) At least once in month* (ii) quarterly. (iii) at least once in six months (iv) Any of above.

Last Answer : i) At least once in month*

Description : On Rajdhani routes testing frequency of rail testing for rail section of 60kg with annual GMT 80, will be. (i) 4 months (ii) 1 1⁄2 months (iii) 1 months* (iv) None of above.

Last Answer : (iii) 1 months*

Description : The increased gain of 10 dbs for single line & ‘D’ marks rails on double/multiple lines shall be employed for classification of defects. (i) defect in weld (ii) defects in rail. * (iii) for both defects on weld & rail. (iv) None of above.

Last Answer : ii) defects in rail. *

Description : Addition gain of 10 db is used for testing. (i) ‘D’ marked rails on single lines. (ii) ‘D’ marked rails on double lines. (iii) Testing on single line and ‘D’ marked rails on double/multiple lines section.* (iv) None of above.

Last Answer : (iii) Testing on single line and ‘D’ marked rails on double/multiple lines section.*

Description : Total no. of probes fitted on digital double rail tester for rail testing are (i) 12 (ii) 8 (iii) 14* (iv) 16.

Last Answer : (iii) 14*

Description : By 00 probe in AT weld testing with normal gain setting. (i) Area below N.axis can be tested. (ii) Area below N.axis can not be tested.* (iii) Only web below N.axis can be tested. (iv) All above are correct.

Last Answer : (ii) Area below N.axis can not be tested.*

Description : 450 probe is used for detecting defect in; (i) FB weld (ii) AT weld (iii) FB weld, AT weld & SEJ (iv) All above*

Last Answer : (iv) All above*

Description : What is the meaning of HAZ ? (i) Heat around Zone. (ii) Heat alongwith Zone (iii) Heat affected Zone* (iv) Heat added zero.

Last Answer : (iii) Heat affected Zone*