When was the collar painting done ?
(i) After the welding *
(ii) after one week of welding
(iii) After 15 days of welding
(iv) None of the above

1 Answer

Answer :

(i) After the welding *

Related questions

Description : Name the paint used in A.T. Welding painting? (i) Black Paint (ii) Bituminous black IS:9862-1981.* (iii) Any type of black paint (iv) None of the above

Last Answer : (ii) Bituminous black IS:9862-1981.*

Description : Painting of weld is done up to (i) 10 CM minimum both side of weld & on welded surface .* (ii) 15 CM minimum both side of weld & on welded surface (iii) 20 CM minimum both side of weld & on welded surface (iv) None of the above

Last Answer : (i) 10 CM minimum both side of weld & on welded surface .*

Description : What is the testing frequency of new AT weld ? (i) Just after the welding (ii) After 7 days of welding (iii) With in the one month of welding* (iv) None of the above

Last Answer : iii) With in the one month of welding*

Description : In how many time final grinding should be done of new AT weld ? (i) Just after the welding (ii) After 8 hrs of welding (iii) With in 24 hrs* (iv) None of the above

Last Answer : iii) With in 24 hrs*

Description : In how many time rough riding should be done of new AT weld ? (i) Just after the welding* (ii) After 8 hrs of welding (iii) After 24 hrs (iv) None of the above

Last Answer : i) Just after the welding*

Description : What is the duration for supervisors course (TW-3)? (i) One week * (ii) Two weeks (iii) As decided by TPP/LKO (iv) 3 working days

Last Answer : (i) One week

Description : What is the duration for Refresher course for welders (TW-2)? (i) One week* (ii) Two weeks (iii) As decided by TPP/LKO (iv) 3 working days

Last Answer : (i) One week*

Description : What is the duration for Initial course for welders (TW-1)? (i) Two weeks* (ii) One week (iii) As decided by TPP/LKO (iv) 3 working days

Last Answer : (i) Two weeks*

Description : After AT Welding First train is to be passed after ? (i) 20 Minutes from pouring of weld metal. (ii) 35 Minutes from pouring of weld metal. (iii) 30 Minutes from pouring of weld metal.* (iv) 25 Minutes from pouring of weld metal.

Last Answer : (iii) 30 Minutes from pouring of weld metal.*

Description : Type of competency certificate issued after TW-1 course? (i) Competency for two years (ii) Provisional competency.* (iii) Competency for six months (iv) Competency to do welding independently

Last Answer : (ii) Provisional competency.*

Description : If code of a fracture is OFW-422 then it means. (i) AT welding with transverse crack. (ii) Flash butt welding with transverse crack. (iii) At welding with horizontal crack.* (iv) None of the above.

Last Answer : (iii) At welding with horizontal crack.*

Description : In AT welding process what is the role of asbestos powder & slag ? (i) To separate closing pin from portion* (ii) To hold the portion (iii) Both above are correct (iv) None of the above

Last Answer : (i) To separate closing pin from portion*

Description : In AT welding process what is the role of closing pin ? (i) To hold the portion before melt (ii) To hold the asbestos powder & slag (iii) Both above are correct* (iv) None of the above

Last Answer : (iii) Both above are correct*

Description : How many detonators are planted during protection of track for welding site ? (i) One (ii) Two (iii) Three* (iv) None of the above

Last Answer : iii) Three*

Description : Ist detonator is planted at a distance of (i) 1200 Mt. from welding site .* (ii) 600 mtrs from welding site (iii) 30 mtrs from welding site (iv) None of the above

Last Answer : (i) 1200 Mt. from welding site .*

Description : Banner flag is planted at a distance of (i) At the site of work (ii) At 1200 mtrs from welding site (iii) At 30 mtrs from welding site (iv) 600 Mt. from welding site .*

Last Answer : iv) 600 Mt. from welding site .

Description : Weather date of welding is marked on weld? (i) Yes (ii) As decided by the site supervisor (iii) No* (iv) None of the above

Last Answer : (iii) No*

Description : Rails used for A T Welding shall not normally be welded? (i) 20 years old . (ii) 30 years old (iii) 40 years old (iv) 50 years old*

Last Answer : iv) 50 years old*

Description : Last flag man is deputed at which distance from last detonator during protection of welding site . (i) 30 mts (ii) 50 mts (iii) 45 (iv) 60 mts

Last Answer : (iv) 60 mts

Description : What will happen if slag is not used above the layer of asbestos powder? (i) Auto tapping* (ii) High welding (iii) Low welding (iv) Nothing will happen

Last Answer : (i) Auto tapping*

Description : Which gauge is used to measure the height of rail at the time of aligning of rails for AT welding? (i) Height gauge.* (ii) Vertical gauge (iii) Horizontal gauge (iv) As decided by site supervisor

Last Answer : (iv) As decided by site supervisor

Description : Weather traffic block is required for execution of AT Welding? (i) Yes.* (ii) No (iii) As decided by site supervisor (iv) As per site condition

Last Answer : (i) Yes.

Description : Weather protection of track is required during block for execution of AT Welding? (i) Yes.* (ii) No (iii) As decided by site supervisor (iv) As per site condition

Last Answer : (i) Yes.*

Description : What are the recognized systems for pre heating of rails ends for AT Welding? (i) Oxygen –LPG & Compressed air petrol both* (ii) Only Oxygen –LPG (iii) Only Compressed air petrol both (iv) both are correct

Last Answer : ) Oxygen –LPG & Compressed air petrol both*

Description : Name the material which is separated from molten steel during chemical reaction of A.T welding? (i) Aluminium oxide (slag). * (ii) Ferrous Oxide (iii) Aluminium (iv) Ferrous

Last Answer : (i) Aluminium oxide (slag). *

Description : What is Pre Heating Temperature of rail ends in AT Welding? (i) 300 ± 20oC (ii) 400 ± 20oC (iii) 500 ± 20oC (iv) 600 ± 20oC *

Last Answer : (iv) 600 ± 20oC *

Description : During AT welding reaction is ? (i) Exothermic .* (ii) Endothermic (iii) No Reaction (iv) Heating

Last Answer : (i) Exothermic .*

Description : Where Portion sample tests(test piece) should be conducted? (i) At desire by RDSO (ii) At Zonal CMT’s organisation or the Flash Butt Welding plant. * (iii) In RDSO campus (iv) As decided by in charge of the plant

Last Answer : At Zonal CMT’s organisation or the Flash Butt Welding plant.

Description : How rejected portion are to be disposed-off? (i) By Igniting 5 Portions at a time in pit away from store?* (ii) By throwing them away (iii) By dispose off in a pit (iv) By using it in Branch/Yard lines for welding

Last Answer : (i) By Igniting 5 Portions at a time in pit away from store?*

Description : In new Rail as well as second hand rails how much end bends of the rails in vertical are permitted when checked with one meter straight edge before welding? (i) +0.5mm, -0 mm in vertical * (ii) +0.2mm, -.3 mm in vertical (iii) +0.3mm, -2 mm in vertical (iv) 0 mm, +.5 mm in vertical

Last Answer : (i) +0.5mm, -0 mm in vertical *

Description : DFWR weld shall be replaced. (i) Within 2 months of detection. (ii) Within 1 year of detection. (iii) Within 3 months of detection.* (iv) after 3 days of detection.

Last Answer : (iii) Within 3 months of detection.*

Description : For rolling mark 60 kg/Sail/X/2010 the first testing in the field after initial testing of rails in rail manufacturing plant, will be done. (i) After test free period of 25%. (ii) After passage of every 40 ... period.* (iii) After passage of 200 GMT. (iv) On the basis of annual GMT of the section.

Last Answer : (ii) After passage of every 40 GMT traffic during test free period.*

Description : What is the time of removal the tensor from the newly executed A T Weld? (i) 15 minutes after pouring. (ii) 20 minutes after pouring* (iii) 25 minutes after pouring. (iv) 30 minutes after pouring.

Last Answer : (ii) 20 minutes after pouring*

Description : Trimming of AT weld should be done by ? (i) Chisel (ii) Trimmer* (iii) Both (iv) None of the above

Last Answer : ii) Trimmer*

Description : USFD testing of new AT weld will be done by ? (i) JE/SSE sectional (ii) Incharge SSE (iii) USFD machine operator* (iv) None of the above

Last Answer : (iv) None of the above

Description : Marking on weld should be done (i) On centre of the rail head (ii) 10 mm below the top surface of rail head.* (iii) 10 mm above the bottom surface of rail head. (iv) None of the above

Last Answer : ii) 10 mm below the top surface of rail head.*

Description : Marking on weld should be done which side? (i) Non gauge face side of A.T. weld * (ii) Gauge face side of A.T. weld (iii) On web of non gauge face side of A.T. weld (iv) On web of gauge face side of A.T. weld

Last Answer : (i) Non gauge face side of A.T. weld

Description : Distance between the two detonators should be (i) 15 Mt. (ii) 10 Mt.* (iii) 20 Mt (iv) None of the above

Last Answer : (ii) 10 Mt.*

Description : Normal Reaction time in SPW technique? (i) 17 ± 3 seconds. (ii) 15 ± 3 seconds (iii) 23 ± 3 seconds (iv) 20 ± 3 seconds*

Last Answer : (iv) 20 ± 3 seconds*

Description : Minm. deflection during transverse breaking load test is? (i) 5 mm (ii) 10 mm (iii) 15 mm* (iv) 20 mm

Last Answer : (iii) 15 mm*

Description : Finishing tolerances are measured by? (i) On 30 cm scale (ii) 1 MT straightedge or 10 CM straightedge.* (iii) On 15 cm straight edge (iv) On 30 cm straight edge

Last Answer : (ii) 1 MT straightedge or 10 CM straightedge.*

Description : In new Rail as well as second hand rails how much end bends of the rails in lateral direction are permitted when checked with one metre straight edge before welding? (i) ± 0.2 mm in lateral direction (ii) ± 0.3 mm in lateral direction (iii) ± 0.5 mm in latera

Last Answer : (iii) ± 0.5 mm in latera

Description : After how much time lining of crucible should be changed ? (i) After every weld (ii) After 7 welds (iii) After every 10 welds* (iv) None of the above

Last Answer : (iii) After every 10 welds*

Description : After declare good in USFD testing what is the joggling criteria ? (i) Joggle will be open from the AT weld* (ii) Joggling with two far end bolting (iii) joggling with four tight bold (iv) None of the above

Last Answer : (i) Joggle will be open from the AT weld*

Description : Colour of rail ends becomes after preheating ? (i) Golden * (ii) Pink Red (iii) Red (iv) Yellow

Last Answer : (i) Golden

Description : Risers are broken at? (i) cold. * (ii) Hot (iii) After 5 mints (iv) After 3 mints

Last Answer : (i) cold. *

Description : What is the validity after supervisors course (TW-3)? (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.* (ii) 2 years (iii) 5 Years (iv) 10 Years

Last Answer : (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.*

Description : What is the validity after Refresher course for welders (TW-2)? (i) Six monyhs (ii) One year (iii) Two years.* (iv) All are wrong

Last Answer : (iii) Two years.*

Description : Second coat of paint is done after minim. of (i) 2 Hrs after first coat (ii) 4 Hrs after first coat (i) 6 Hrs after first coat (iv) 8 Hrs. after first coat

Last Answer : (iv) 8 Hrs. after first coat

Description : The physical quantity, which oscillates in most waves, is (i) mass (ii) energy (iii) Amplitude* (iv) wavelength

Last Answer : iii) Amplitude*