Marking of DFWO weld is.
(i) Two red point circle on both faces of weld.*
(ii) Two red point cross on both faces of weld.
(iii) One red point circle on both faces of weld.
(iv) None of the above.

1 Answer

Answer :

i) Two red point circle on both faces of weld.*

Related questions

Description : During periodic testing of an AT weld with 700 probe, a bunch of moving signals of less than 40% but more than 10% is observed in the head of weld, the joint will be. (i) Good joint.* (ii) DFWR (iii) DFWO (iv) OBSW

Last Answer : i) Good joint.*

Description : On a branch line one new AT Weld with 00 probe shows a signal of 58 is. (i) DFWO* (ii) DFWR (iii) IMRW (iv) OBSW

Last Answer : i) DFWO*

Description : Marking on weld should be done (i) On centre of the rail head (ii) 10 mm below the top surface of rail head.* (iii) 10 mm above the bottom surface of rail head. (iv) None of the above

Last Answer : ii) 10 mm below the top surface of rail head.*

Description : Marking on weld should be done which side? (i) Non gauge face side of A.T. weld * (ii) Gauge face side of A.T. weld (iii) On web of non gauge face side of A.T. weld (iv) On web of gauge face side of A.T. weld

Last Answer : (i) Non gauge face side of A.T. weld

Description : The increased gain of 10 dbs for single line & ‘D’ marks rails on double/multiple lines shall be employed for classification of defects. (i) defect in weld (ii) defects in rail. * (iii) for both defects on weld & rail. (iv) None of above.

Last Answer : ii) defects in rail. *

Description : Trimming of AT weld should be done by ? (i) Chisel (ii) Trimmer* (iii) Both (iv) None of the above

Last Answer : ii) Trimmer*

Description : Painting of weld is done up to (i) 10 CM minimum both side of weld & on welded surface .* (ii) 15 CM minimum both side of weld & on welded surface (iii) 20 CM minimum both side of weld & on welded surface (iv) None of the above

Last Answer : (i) 10 CM minimum both side of weld & on welded surface .*

Description : After declare good in USFD testing what is the joggling criteria ? (i) Joggle will be open from the AT weld* (ii) Joggling with two far end bolting (iii) joggling with four tight bold (iv) None of the above

Last Answer : (i) Joggle will be open from the AT weld*

Description : Till USFD testing of new AT weld what is criteria for joggling ? (i) Joggling with two far end bold (ii) Joggling with two tight clamps* (iii) Leave without joggling till its testing (iv) None of the above

Last Answer : (ii) Joggling with two tight clamps*

Description : DFWR weld shall be replaced. (i) Within 2 months of detection. (ii) Within 1 year of detection. (iii) Within 3 months of detection.* (iv) after 3 days of detection.

Last Answer : (iii) Within 3 months of detection.*

Description : Tandem rig test with 450 probe for AT weld detects. (i) Horizontal longitudinal defect in weld. (ii) Vertical oriented defect in AT weld.* (iii) Transverse defect in AT weld. (iv) Defect in flange of AT welds.

Last Answer : (ii) Vertical oriented defect in AT weld.*

Description : By 00 probe in AT weld testing with normal gain setting. (i) Area below N.axis can be tested. (ii) Area below N.axis can not be tested.* (iii) Only web below N.axis can be tested. (iv) All above are correct.

Last Answer : (ii) Area below N.axis can not be tested.*

Description : 450 probe is used for detecting defect in; (i) FB weld (ii) AT weld (iii) FB weld, AT weld & SEJ (iv) All above*

Last Answer : (iv) All above*

Description : After how much time lining of crucible should be changed ? (i) After every weld (ii) After 7 welds (iii) After every 10 welds* (iv) None of the above

Last Answer : (iii) After every 10 welds*

Description : USFD testing of new AT weld will be done by ? (i) JE/SSE sectional (ii) Incharge SSE (iii) USFD machine operator* (iv) None of the above

Last Answer : (iv) None of the above

Description : What is the testing frequency of new AT weld ? (i) Just after the welding (ii) After 7 days of welding (iii) With in the one month of welding* (iv) None of the above

Last Answer : iii) With in the one month of welding*

Description : In how many time final grinding should be done of new AT weld ? (i) Just after the welding (ii) After 8 hrs of welding (iii) With in 24 hrs* (iv) None of the above

Last Answer : iii) With in 24 hrs*

Description : In how many time rough riding should be done of new AT weld ? (i) Just after the welding* (ii) After 8 hrs of welding (iii) After 24 hrs (iv) None of the above

Last Answer : i) Just after the welding*

Description : New AT weld should be entered in TMS by ? (i) Sectional JE/SSE* (ii) Incharge SSE (iii) Welder (iv) None of the above

Last Answer : (i) Sectional JE/SSE*

Description : Weather date of welding is marked on weld? (i) Yes (ii) As decided by the site supervisor (iii) No* (iv) None of the above

Last Answer : (iii) No*

Description : What is the time of removal the tensor from the newly executed A T Weld? (i) 15 minutes after pouring. (ii) 20 minutes after pouring* (iii) 25 minutes after pouring. (iv) 30 minutes after pouring.

Last Answer : (ii) 20 minutes after pouring*

Description : Main advantage of 3-piece P F Mould is? (i) To overcome fin defect.* (ii) To prevent the flaw of molten metal (iii) To make proper weld size (iv) None to the above

Last Answer : (i) To overcome fin defect.*

Description : Defect of High joint is due to ? (i) Early trimming of weld (ii) Excess provision of height during alignment.* (iii) Early grinding of weld (iv) None of above

Last Answer : (ii) Excess provision of height during alignment.

Description : Defect of low joint is due to? (i) Excess height (ii) Early trimming of weld (iii) Early grinding of weld (iv) Nil/Less provision of height during alignment.

Last Answer : (iv) Nil/Less provision of height during alignment.

Description : Defect of cracks in weld is mainly due to? (i) Early opening of mould.* (ii) Early trimming of weld (iii) Early grinding of weld (iv) None of above

Last Answer : (i) Early opening of mould.*

Description : Full form of SPW? (i) Special pre heated weld (ii) Short preheated weld.* (iii) Short post heated weld (iv) None of above

Last Answer : (ii) Short preheated weld.*

Description : How many nos. of sleepers should be loosened either side of the proposed weld? (i) 3 sleepers (ii) 5 sleepers.* (iii) 2 sleepers (iv) 4 sleepers

Last Answer : (ii) 5 sleepers.

Description : After AT Welding First train is to be passed after ? (i) 20 Minutes from pouring of weld metal. (ii) 35 Minutes from pouring of weld metal. (iii) 30 Minutes from pouring of weld metal.* (iv) 25 Minutes from pouring of weld metal.

Last Answer : (iii) 30 Minutes from pouring of weld metal.*

Description : Minimum traffic block required for execution of AT Weld ? (i) 70 minutes (ii) 70-75 minute.* (iii) 60 mints (iv) 1 hrs and 30 mints

Last Answer : (ii) 70-75 minute.*

Description : Min. breaking load of 60kg weld during transverse breaking load test is? (i) 110 MT (ii) 115 MT* (iii) 90 MT (iv) 120 MT

Last Answer : (ii) 115 MT*

Description : Min. breaking load of 52kg weld during transverse breaking load test is? (i) 90MT* (ii) 100 MT (iii) 110 MT (iv) 120 MT

Last Answer : (i) 90MT*

Description : hat is the minimum distance between AT Weld and other joint exist in track? (i) 2 Mt. (ii) 3 Mt. (iii) 4 Mt.* (iv) 4.5 Mt.

Last Answer : (iii) 4 Mt.*

Description : What is the function of Zircon wash? (i) To maintain good quality of weld (ii)To achieve good finish of the weld surface.* (ii) Both above are correct (iv) Both are incorrect

Last Answer : (ii)To achieve good finish of the weld surface.*

Description : Quantity is not a part of the weld symbol (i)Dark circle (ii) Open circle (iii) Angle of weld (iv)Starting and stopping allowance for welding

Last Answer : (iv)Starting and stopping allowance for welding

Description : Colour of rail ends becomes after preheating ? (i) Golden * (ii) Pink Red (iii) Red (iv) Yellow

Last Answer : (i) Golden

Description : The colour of bag containing Portion for 110 UTS ? (i) Red (ii) Green (iii) Pink (iv) Black*

Last Answer : iv) Black*

Description : he colour of bag containing Portion for 90 UTS ? (i) Red (ii) Green * (iii) Pink (iv) Black

Last Answer : ii) Green *

Description : The colour of bag containing Portion for 72 UTS ? (i) Pink (ii) Green (iii) Red * (iv) Black

Last Answer : (iii) Red *

Description : In AT welding process what is the role of asbestos powder & slag ? (i) To separate closing pin from portion* (ii) To hold the portion (iii) Both above are correct (iv) None of the above

Last Answer : (i) To separate closing pin from portion*

Description : In AT welding process what is the role of closing pin ? (i) To hold the portion before melt (ii) To hold the asbestos powder & slag (iii) Both above are correct* (iv) None of the above

Last Answer : (iii) Both above are correct*

Description : What are the recognized systems for pre heating of rails ends for AT Welding? (i) Oxygen –LPG & Compressed air petrol both* (ii) Only Oxygen –LPG (iii) Only Compressed air petrol both (iv) both are correct

Last Answer : ) Oxygen –LPG & Compressed air petrol both*

Description : How much rail ends are cleaned with Kerosene Oil and steel wire brush? (i) Minimum 100 mm both side (ii) Minimum 50 mm both side.* (iii) No need (iv) As decided by site supervisor

Last Answer : (ii) Minimum 50 mm both side.*

Description : How many detonators are planted during protection of track for welding site ? (i) One (ii) Two (iii) Three* (iv) None of the above

Last Answer : iii) Three*

Description : Distance between the two detonators should be (i) 15 Mt. (ii) 10 Mt.* (iii) 20 Mt (iv) None of the above

Last Answer : (ii) 10 Mt.*

Description : What is the validity after Refresher course for welders (TW-2)? (i) Six monyhs (ii) One year (iii) Two years.* (iv) All are wrong

Last Answer : (iii) Two years.*

Description : Type of competency certificate issued after TW-1 course? (i) Competency for two years (ii) Provisional competency.* (iii) Competency for six months (iv) Competency to do welding independently

Last Answer : (ii) Provisional competency.*

Description : What is the duration for supervisors course (TW-3)? (i) One week * (ii) Two weeks (iii) As decided by TPP/LKO (iv) 3 working days

Last Answer : (i) One week

Description : What is the duration for Refresher course for welders (TW-2)? (i) One week* (ii) Two weeks (iii) As decided by TPP/LKO (iv) 3 working days

Last Answer : (i) One week*

Description : What is the duration for Initial course for welders (TW-1)? (i) Two weeks* (ii) One week (iii) As decided by TPP/LKO (iv) 3 working days

Last Answer : (i) Two weeks*

Description : The physical quantity, which oscillates in most waves, is (i) mass (ii) energy (iii) Amplitude* (iv) wavelength

Last Answer : iii) Amplitude*