Pick up the correct statement from the following:
(A) The difference of latest occurrence time and earliest expected time, is called slack
(B) The activities connecting the events having zero slack, lie on the critical path
(C) The critical path consumes the maximum time
(D) All the above

1 Answer

Answer :

(D) All the above

Related questions

Description : Pick up the correct statement from the following: (A) Forward pass is used for calculating earliest expected time (B) Backward pass is used for calculating the latest occurrence time (C) Maximum value of earliest ... time is used if there is more than one value of any event (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) Earliest expected time is denoted by TE (B) Latest occurrence time is denoted by TL (C) Contractual obligation time is denoted by Ts (D) All the above

Last Answer : (D) All the above

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : Pick up the incorrect statement from the following: (A) The activity is the time consuming part of a project (B) The beginning and end of a job, are called events (C) The activity ... maximum time, is called a node (D) Logically and sequentially connected activities and events form a network

Last Answer : (C) The activity which consumes maximum time, is called a node

Description : Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer. (A) A is correct but R is not correct (B) R is correct but A is not correct (C) Both A and R is correct (D) Both A and R is incorrect

Last Answer : (A) A is correct but R is not correct

Description : Pick up the incorrect statement from the following a. The activity which consumes maximum time, is called a node b. The activity is the time consuming part of a project c. The beginning ... of a job, are called events d. Logically and sequentially connected activities and events form a network

Last Answer : a. The activity which consumes maximum time, is called a node

Description : Backward pass calculations are done to find ________ occurrence times of events a. Tentative b. Definite c. Latest d. Earliest

Last Answer : c. Latest

Description : Forward pass calculations are done to find _____ occurrence times of events a. Exact b. Earliest c. Latest d. Approximate

Last Answer : b. Earliest

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : All activities lying on critical path have slack time equal to (A) 0 (B) 1 (C) 2 (D) None of above

Last Answer : (A) 0

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : Critical path moves along the activities having total float as (a) Positive (b) Negative ( c) Zero (d) Unity

Last Answer : ( c) Zero

Description : The basic difference between PERT and CPM is that a. PERT deals with events and CPM with activities b. Critical Path is determined in PERT only c. Costs are considered on CPM only d. Guessed times are used in PERT and evaluated times in CPM.

Last Answer : a. PERT deals with events and CPM with activities

Description : The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is (A) 19 (B) 14 (C) 24 (D) None of these

Last Answer : (A) 19

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : Pick up the correct statement from the following: (A) Programme Evaluation and Review Technique, is event oriented (B) Programme Evaluation and Review Technique is not event oriented (C) Critical Path Method is event oriented (D) Critical Path method is event oriented

Last Answer : (A) Programme Evaluation and Review Technique, is event oriented

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having (A) Longest duration (B) Highest cost slope (C) Least cost slope (D) Shortest duration

Last Answer : (C) Least cost slope

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : While scheduling a project by C.P.M. (A) A project is divided into various activities (B) Required time for each activity is established (C) Net work is drawn by connecting the activities and the events (D) All the above

Last Answer : (D) All the above

Description : Select the incorrect statement. (A) Earliest start of an activity is the early event time of the node it leaves. (B) Latest finish of an activity is the late event time of the node it enters. (C) Latest start of an activity is its latest finish minus its duration. (D) None of the above

Last Answer : (D) None of the above

Description : Total float for any activity is defined as the difference between (A) Its latest finish time and earliest start time for its successor activity (B) Its latest start time and earliest start ... earliest finish time (D) Its earliest finish time and earliest start time for its successor activity

Last Answer : (B) Its latest start time and earliest start time

Description : In time-cost optimization of a project, crashing is done. (A) On all the activities (B) On all the activities lying on the critical path (C) Only on activities lying on the ... critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

Last Answer : D

Description : At the completion of the forward and backward passes, the slack for an activity is given by the a. Difference between early start and early finish b. Difference between early start and ... c. Difference between latest start and early finish d. Difference between latest start and latest finish

Last Answer : c. Difference between latest start and early finish

Description : Crash project duration is obtained by summing the (A) Normal durations for all the activities (B) Crash durations for all activities (C) Crash durations for all the activities along the ... along the critical path obtained by taking into account the crash duration for all the activities.

Last Answer : (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

Description : If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good (A) EF = ES + D (B) LS = LF - D (C) LF = LS + D (D) All the above

Last Answer : (D) All the above

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description : During consolidation process of clayey soils, indicate the sequence of occurrence of the following events in the order from first to last : 1. Load being taken up by the pore water 2. Load being taken up by the soil grains 3. Drainage of ... 1, 2 and 3 (b) 2, 3 and 1 (c) 1, 3 and 2 (d) 2, 1 and 3

Last Answer : (c) 1, 3 and 2

Description : While determining the yield of open wells by the pumping test  (A) Velocity of recharging water, increases with depression head  (B) Depression head resulting at critical velocity, is called critical ... (D) Maximum safe yield of an open well, is expected at critical depression head 

Last Answer : (D) Maximum safe yield of an open well, is expected at critical depression head 

Description : Which of the following statements is correct regarding float' for anactivity? a) Time between its earliest start time and earliest finish time b) Time between its latest start time and latest ... start time and earliest finish time d) Time between earliest finish time and latest finish time

Last Answer : d) Time between earliest finish time and latest finish time

Description : Pick up the correct statement from the following: (A) The lines of sight while observing back sight and fore sight lie in the same horizontal plane (B) The staff readings are measurements made ... readings are taken, coincides with the level surface through the telescope axis (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) At a particular speed of operation, the head produced decreases with the increase of discharge (B) At zero discharge, discharge valve remaining closed ... which efficiency of a pump is maximum, is known as normal discharge (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following:  (A) The pH value of neutral water is 7  (B) The maximum acidity is obtained when pH value is zero . (C) The maximum alkalinity is obtained when pH value is 14  (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following:  (A) The bending stress in a section is zero at its neutral axis and maximum at the outer fibres  (B) The shear stress is zero at the outer ... (C) The bending stress at the outer fibres, is known as principal stress  (D) All the above 

Last Answer : (D) All the above 

Description : Pick up the correct statement from the following: (A) The tides at any place occur a little less than 1 hour later, each succeeding day (B) The influence of the earth's gravity alone produces level-tidal ... ) The spinning force is maximum at the equator and zero at the poles (D) All of the above

Last Answer : (D) All of the above

Description : ....................... deals with the concepts such as critical path, float, events, etc. a. Game theory b. Decision theory c. Queuing theory d. Network analysis

Last Answer : d. Network analysis

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : In PERT analysis, the time estimates of activities and probability of their occurrence follow (A) Normal distribution curve (B) Poisson's distribution curve (C) Beta distribution curve (D) None of the above

Last Answer : (C) Beta distribution curve

Description : For completion of a project, the critical path of the network represents (A) Minimum time (B) Maximum time (C) Maximum cost (D) Minimum cost

Last Answer : (A) Minimum time

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : Activities lying on critical path are called ............................ a. Critical activities b. Non-critical activities c. Dummy activities d. None of these

Last Answer : a. Critical activities

Description : If a nuclear reactor produces more fissile nuclear fuel than it consumes, then it is called a __________ reactor. (A) Critical (B) Breeder (C) Fertile (D) Heterogeneous

Last Answer : (B) Breeder

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : ............................ is the sequence of activities which determines the total project duration. a. Critical path b. Network c. Non-critical activities d. None of these

Last Answer : a. Critical path

Description : Pick up the correct statement from the following: (A) The direction of the littoral drift depends upon the direction of the wave with respect to the coastline (B) The direction of a river opening to the sea ... avoid a build up of sand on one side and erosion on the other (D) all of the above

Last Answer : (D) all of the above

Description : Pick up the correct statement from the following: (A) The phenomenon of quicksand generally occurs in the cohesionless soil (B) At critical hydraulic gradient, the saturated sand becomes quick (C) The critical gradient depends on the void ratio and the specific gravity (D) All the above

Last Answer : (D) All the above