Pick up the incorrect statement from the following:
(A) The difference between the earliest start time and latest finish time of any activity, is the
maximum time available for the activity
(B) The difference between the maximum time available for the job and actual time it
consumes, is called total float
(C) The difference between the latest start time and earliest start time of an activity, is called
total float
(D) None of thes
(A) The difference between the earliest start time and latest finish time of any activity, is the
maximum time available for the activity
(B) The difference between the maximum time available for the job and actual time it
consumes, is called total float
(C) The difference between the latest start time and earliest start time of an activity, is called
total float
(D) None of thes