In retaining and breast walls, weep holes are provided at
(A) 50 cm vertical height and 50 cm centre to centre horizontally
(B) 100 cm vertical height and 100 cm centre to centre horizontally
(C) 100 cm vertical height and 120 cm centre to centre horizontally
(D) 120 cm vertical height and 100 cm centre to centre horizontally

1 Answer

Answer :

Answer: Option C

Related questions

Description : Weep holes are provided in retaining and breast walls (A) To drain off the water from the filling (B) To ventilate the stone masonry (C) To add architectural beauty (D) To increase compaction of the earth retained

Last Answer : Answer: Option A

Description : Pick up the incorrect statement from the following: (A) The retaining wall should be structurally capable to resist the applied earth pressure (B) The section of the retaining wall should be so ... off water from the earth retained, weep holes are provided near the top of the retaining wall

Last Answer : Answer: Option D

Description : The walls which are necessary on the hill side of roadway where earth has to be retained from slipping is known as (A) Retaining wall (B) Breast wall (C) Parapet wall (D) None of the above

Last Answer : Answer: Option B

Description : The stepped structure provided for lateral support of a structure, is (A) Retaining wall (B) Breast wall (C) Buttress (D) Parapet wall

Last Answer : Answer: Option C

Description : Weep holes are provided in a) piers b) trestle piers c) foundation d) abutments*

Last Answer : d) abutments*

Description : In counterfort type retaining walls (i) The vertical slab is designed as a continuous slab (ii) The heel slab is designed as a continuous slab (iii) The vertical slab is designed as a cantilever (iv) The heel slab is designed ... (ii) (B) (i)and(iv) (C) (ii) and (iii) (D) (iii) and (iv)

Last Answer : Answer: Option A

Description : Side face reinforcement shall be provided in the beam when depth of the web in a beam exceeds (A) 50 cm (B) 75 cm (C) 100 cm (D) 120 cm

Last Answer : Answer: Option B

Description : Parapet walls along hill roads, are provided (A) To retain the back filling (B) To prevent the hill from sliding (C) To prevent the wheels of the vehicle from coming on the retaining wall (D) None of these

Last Answer : Answer: Option C

Description : Construction joints are generally provided in concrete (A) Roads (B) Retaining walls (C) Lining of canals (D) All the above

Last Answer : Answer: Option D

Description : In T-shaped R C. retaining walls, the main reinforcement in the stem is provided on (A) The front face in one direction (B) The front face in both directions (C) The inner face in one direction (D) The inner face in both directions

Last Answer : Answer: Option C

Description : In counterfort retaining walls, the main reinforcement in the stem at support is (A) Not provided (B) Provided only on inner face (C) Provided only on front face (D) Provided both on inner and front faces

Last Answer : Answer: Option B

Description : While calculating the overtaking sight distance, the height of the object above road surface, is assumed (A) 50 cm (B) 75 cm (C) 100 cm (D) 120 cm

Last Answer : Answer: Option D

Description : Cantilever retaining walls can safely be used for a height not more than (A) 3 m (B) 4 m (C) 5 m (D) 6 m

Last Answer : Answer: Option D

Description : Retaining walls are generally constructed with dry rubble stones with 60 cm top width and (A) 1 : 2 front batter (B) 1 : 3 front batter (C) 1 : 4 front batter (D) 1 : 5 front batter

Last Answer : Answer: Option B

Description : The temperature reinforcement in the vertical slab of a T-shaped R.C. retaining wall is (A) Not needed (B) Provided equally on inner and front faces (C) Provided more on inner face than on front face (D) Provided more on front face than on inner face

Last Answer : Answer: Option D

Description : Total pressure on the vertical face of a retaining wall of height h acts parallel to free surface and from the base at a distance of (A) h/4 (B) h/3 (C) h/2 (D) 2h/3

Last Answer : Answer: Option B

Description : In the design of a front counterfort in a counterfort retaining wall, the main reinforcement is provided on (i) Bottom face near counterfort (ii) Top face near counterfort (iii) Bottom face near centre of span (iv) Top ... ) (B) Only (ii) (C) Both (i) and (iv) (D) Both (ii) and (iii)

Last Answer : Answer: Option C

Description : If is the overall height of a retaining wall retaining a surcharge, the width of the base slab usually provided, is (A) 0.3 H (B) 0.4 H (C) 0.5 H (D) 0.7 H

Last Answer : Answer: Option D

Description : In a cantilever retaining wall without a heel slab (A) Thickness of the stem is kept same throughout (B) Base slab is made 10 cm thicker than the stem (C) Width of the base slab is kept 0.7 time the total height of the wall (D) All the above

Last Answer : Answer: Option D

Description : For stairs spanning horizontally, the minimum waist provided is (A) 4 cm (B) 6 cm (C) 8 cm (D) 12 cm

Last Answer : Answer: Option D

Description : Statistics , Problems with Two Projectors ? From the top of a 100 meter high tower an object is thrown at a 30 ° angle with a horizontal speed of 50 ms . At the same time another object from ... সাথে with the same velocity horizontally . At what time and at what height will the two objects meet ?

Last Answer : answer:

Description : For a continuous slab of 3 m × 3.5 m size, the minimum overall depth of slab to satisfy vertical deflection limits is (A) 50 mm (B) 75 mm (C) 100 mm (D) 120 mm

Last Answer : (B) 75 mm

Description : For a continuous slab of 3 m x 35 m size, the minimum overall depth of slab to satisfy vertical deflection limits is (a) 120 mm (b) 100 mm (c) 75 mm (d) 50 mm

Last Answer : (a) 120 mm

Description : The wall constructed for the stability of an excavated portion of a road on the hill side, is known as (A) Retaining wall (B) Breast wall (C) Parapet wall (D) All the above

Last Answer : Answer: Option B

Description : The wall constructed for the stability of a back filling portion of a road on the downhill side, is known as (A) Retaining wall (B) Breast wall (C) Parapet wall (D) All the above

Last Answer : Answer: Option A

Description : Can you tell me what to use to "seal" the weep holes on my house?

Last Answer : Could you find an old screen (sometimes you can buy it on the roll by the sqft) and cut it to size? Cut it a bit bigger and use removeable caulk to adhere it to the hole perhaps.

Description : Pick up the incorrect statement from the following: (A) Horizontal D.P.C. is provided at plinth level in internal walls (B) D.P.C. is provided under door and verandah openings (C) Vertical D.P.C. is not provided in internal walls (D) Cement concrete is a rigid damp-proofing material

Last Answer : Answer: Option B

Description : no super elevation is provided on a road along curves, pot holes may develop at (A) Inner edge of the road (B) Outer edge of the road (C) Centre of the road (D) Nowhere on the road

Last Answer : Answer: Option B

Description : What is the function of shear keys in the design of retaining walls?

Last Answer : In determining the external stability of retaining walls, failure modes like bearing failure, sliding and overturning are normally considered in design. In considering the criterion of sliding, the sliding ... instead of 0.8φ in the previous case and the sliding resistance can be enhanced.

Description : For the design of retaining walls, the minimum factor of safety against overturning is taken as (A) 1.5 (B) 2.0 (C) 2.5 (D) 3.0

Last Answer : Answer: Option B

Description : Which of the following R.C. retaining walls is suitable for heights beyond 6 m? (A) L-shaped wall (B) T-shaped wall (C) Counterfort type (D) All of the above

Last Answer : Answer: Option C

Description : Stones used for the construction of retaining walls must be (A) Soft (B) Hard (C) Light (D) Heavy

Last Answer : Answer: Option D

Description : Refractory bricks are used for (A) Retaining walls (B) Columns (C) Piers (D) Combustion chambers

Last Answer : Answer: Option D

Description : A heavy stone is suitable for (A) Arches (B) Rubble masonry (C) Roads (D) Retaining walls

Last Answer : Answer: Option D

Description : The cement, widely used in retaining walls, is (a) R.H.C (b) L.H.C (c) S.R.C. (d) O.P.C.

Last Answer : (b) L.H.C

Description : For laying a sewer line in a trench of 2 m width, an offset line is marked on the ground parallel to the given centre line at a distance of A. 100 cm B. 120 cm C. 140 cm D. 160 cm

Last Answer : ANS: D

Description : If depth of slab is 10 cm, width of web 30 cm, depth of web 50 cm, centre to centre distance of beams 3 m, effective span of beams 6 m, the effective flange width of the beam, is (A) 200 cm (B) 300 cm (C) 150 cm (D) 100 cm

Last Answer : Answer: Option C

Description : A steel rod of sectional area 250 sq. mm connects two parallel walls 5 m apart. The nuts at the  ends were tightened when the rod was heated to 100°C. If steel = 0.000012/C°, Esteel = 0.2  MN/mm2 , the ... N/mm2 (B) 100 N/mm2 (C) 120 N/mm2 (D) 150 N/mm2 Answer: Option 

Last Answer : (C) 120 N/mm

Description : If the maximum shear stress at the end of a simply supported R.C.C. beam of 6 m effective span is 10 kg/cm2 , the share stirrups are provided for a distance from either end where, is (A) 50 cm (B) 100 cm (C) 150 cm (D) 200 cm

Last Answer : Answer: Option C

Description : Pick up the incorrect statement from the following: (A) Space between the exterior walls of a warehouse and bag piles should be 30 cm (B) Cement bags should preferably be piled on wooden planks (C) Width and height of the pile should not exceed 3 m and 2.70 m respectively (D) None of these

Last Answer : Answer: Option D

Description : At what height must top rails be fitted above working platform? a. Between 90 cm (35 inches) and 110 cm (43 inches) b. Between 100 cm (39 inches) and 120 cm (47 inches) c. Between 95 cm (38 inches) and 115 cm ( 45 inches) d. Between 105 cm (41 inches)and 125 cm (49 inches)

Last Answer : c. Between 95 cm (38 inches) and 115 cm ( 45 inches)

Description : A retaining wall 6m high supports a backfill with a surcharge angle of 10°. The back of the wall is inclined to the vertical at a positive batter angle of 5°. If the angle of wall friction is 7°, then the resultant ... inclined to the horizontal at an angle of (A) 7° (B) 10° (C) 12° (D) 17

Last Answer : (C) 12°

Description : A failure wedge develops if a retaining wall (A) Moves away from the backfill (B) Moves towards the backfill (C) Sinks downwards (D) Stresses equally by vertical and horizontal forces

Last Answer : Answer: Option A

Description : The major principal stress in an element of cohesion-less soil within the backfill of a retaining wall is (A) Vertical if the soil is in an active state of plastic equilibrium (B) Vertical if the ... state of plastic equilibrium (C) Inclined at 45° to the vertical plane (D) None of the above

Last Answer : Answer: Option A

Description : The thickness of base slab of a retaining wall generally provided, is (A) One half of the width of the stem at the bottom (B) One-third of the width of the stem at the bottom (C) One fourth of the width of the steam at the bottom (D) Width of the stem at the bottom

Last Answer : Answer: Option D

Description : Pick up the incorrect statement from the following: (A) In the stem of a retaining wall, reinforcement is provided near the earth side (B) In the toe slab of a retaining wall, reinforcement is ... slab of a retaining wall, reinforcement is provided at the top of the slab (D) None of these

Last Answer : Answer: Option D

Description : Pick up the correct statement from the following: (A) The breakwater which can be used as a platform for loading and unloading of cargo is called a mole (B) The brick masonry retaining wall which is ... wall (C) Three types of break waters are generally provided in harbours (D) All of the above

Last Answer : (D) All of the above

Description : The main reinforcement in the toe of a T-shaped R C. retaining wall is provided on (i) Top face parallel to the wall (ii) Top face perpendicular to the wall (iii) Bottom face parallel to the wall (iv) ... (i) and (ii) are correct (C) (iii) and (iv) are correct (D) Only (iv) is correct

Last Answer : Answer: Option D

Description : The main reinforcement in the heel of a T-shaped R.C. retaining wall is provided on (A) Top face perpendicular to wall (B) Bottom face perpendicular to wall (C) Both top and bottom faces perpendicular to wall (D) None of these

Last Answer : Answer: Option A