A process that involves continuously improving and detailing a plan as more detail become 

available is termed as

(A) project analysis

(B) project enhancing

(C) progressive deliberation

(D) progressive elaboration

1 Answer

Answer :

(D) progressive elaboration

Related questions

Description : A planning method, which provides details of the work to accomplish, but also provide some  preliminary description of the work to be done in later phases is called : 1. Progressive detailing  2. Rolling wave  3. Strategic  4. Operational

Last Answer : 2. Rolling wave

Description : Ryan, a newly hired systems analyst/consultant, is about to begin a systems project.  Where will Ryan look first to locate the identifiable tasks he will record in his work plan?  a. ... . the project planning software available at the local bookstore  e. the website of his old college professor

Last Answer : c. the company training materials for the company methodology

Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work  with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram

Last Answer : a. layered description

Description : Which phase of the RUP is used to establish a business case for the  system? a) Transition b) Elaboration c) Construction d) Inception

Last Answer : d) Inception

Description : During the planning development process, at times it is necessary to make certain assumptions to enhance the project plan when the data is not available. In regard to making those assumptions, ... upon historical data used for the project.  4. Senior management predefines the budget constraints.

Last Answer : 1. The assumptions will be considered as true, real, or certain.

Description : A(n) _ is a review of the quality plan, procedures, data collection, and analysis by  an outside group. Select one: a. scope document b. project appraisal c. cost performance index d. analogous estimate e. quality audit

Last Answer : e. quality audit

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : For the best model suitable for the project, in which of the phase  the developers decide a roadmap for project plan? a. Design b. System Analysis c. Coding d. Testing

Last Answer : b. System Analysis

Description : How does a project differ from an ongoing work effort?  A. It is unique B. It involves more than one person C. It has a project manager D. It is not a repetitive process that follows an organization’s existing procedures  (Ans.)

Last Answer : D. It is not a repetitive process that follows an organization’s existing procedures  (Ans.)

Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : Andrew has joined as the Project Manager of a project. One of the project documents  available to Andrew lists down all the risks in a hierarchical fashion. What is this document  called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : Which one of the following statements best describes the use of an issue log? a. A summary of all possible alternative resolutions of an issue. b. A summary of all the project issues, their ... for capturing all issues. d. A tool to ensure that the issue management process is adhered to.

Last Answer : b. A summary of all the project issues, their analysis and status.

Description : Feasibility analysis is the first stage in the process of project development. (True/False)

Last Answer : Ans. True

Description : The process of assigning values for the time and effort needed to perform a system  project is called _____.  a. analysis  b. estimation  c. identifying  d. planning

Last Answer : b. estimation

Description : The process of assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes ... Risk Analysis B. Risk Identification C. Qualitative Risk Analysis D. Risk Management Planning

Last Answer : C. Qualitative Risk Analysis

Description : Which one of the following statements best describes the use of an issue log?  a. A summary of all possible alternative resolutions of an issue.  b. A summary of all the project issues, their ... for capturing all issues.  d. A tool to ensure that the issue management process is adhered to.

Last Answer : b. A summary of all the project issues, their analysis and status.

Description : Evaluation process of proposed projects or groups of projects is known as: A. Project Analysis B. Project Compilation C. Project selection D. Project Documentation

Last Answer : C. Project selection

Description : Process Analysis is a function of: A. Performance Analysis B. Quality Metrics C. Process Improvement Plan D. Quality Improvement Plan

Last Answer : C. Process Improvement Plan

Description : Process Analysis is a function of: A. Performance Analysis B. Quality Metrics C. Process Improvement Plan D. Quality Improvement Plan

Last Answer : C. Process Improvement Plan

Description : The National Mission for Sustainable Agriculture (NMSA) aims at which of the following? a. Enhancing agricultural productivity, protection of resources such as land, water, biodiversity and ... mechanism. d. Providing Irrigation benefits to the farmers to ensure early completion of projects.

Last Answer : a. Enhancing agricultural productivity, protection of resources such as land, water, biodiversity and genetic resources by developing strategies to make agriculture more resilient to climate change.

Description : Traditional Work Breakdown Structures tend to  a. focus on the design of the system as oppose to the needs of the current phase and  iteration  b. force too many levels of detail early on for large ... project and difficult to compare across projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : Work that continues throughout the project and does not relate to  any specific phase of development is termed a(n) a) Milestone b) Project function c) Activity d) Task e) Baseline.

Last Answer : b) Project function

Description : In the project management theory, balancing scope, schedule, and cost goals is often termed as (A) triangular dilemma (B) triple constraint (C) fundamental trade-off (D) project portfolio management

Last Answer : (B) triple constraint

Description : An uncertain event or condition that, if it occurs, has a positive or negative effect on a project objectives is termed. A. Random Chance B. Disaster C. Risk

Last Answer : C. Risk

Description : . A key aspect of managing a project involves: a. defining which operational systems to put in place. b. identifying routine tasks. c. ensuring ongoing operations are maintained. d. planning to achieve defined objectives

Last Answer : d. planning to achieve defined objectives.

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.

Description : Project planning involves three processes:____ review, and __

Last Answer : Ans. Identification, analysis

Description : Project closure involves releasing the final product to the customer, handing over the  project documentation, manuals, source code, and network layouts. (True/False)

Last Answer : Ans. True

Description :  A key factor in staffing a project involves motivating people to meet the project’s  objectives, and the most effective way to do this is through the use of money and bonuses.

Last Answer : Ans: False

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description : A key aspect of managing a project involves:  a. defining which operational systems to put in place. b. identifying routine tasks.  c. ensuring ongoing operations are maintained.  d. planning to achieve defined objectives.

Last Answer : d. planning to achieve defined objectives.

Description : )A new project was initiated that involves new technology and subsequently has never been  done before. What type of contract would to owner want to issue to reduce or eliminate as much  risk as possible. 1. Firm ... 2. Cost plus fix fee  3. Cost plus incentive fee  4. Lump sum  5. A and D

Last Answer : 5. A and D

Description : ___________ involves allocating resources by detailing what activities haveto be done, the order in which they are to be completed, who is to do each,and when they are to be complete(d) (a) Benchmarking ; (b) Budgeting ; (c) Scheduling ; (d) Competitor intelligence

Last Answer : (b) Budgeting ;

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description : Once a change has been requested what is the next step in the change control process? a. Evaluate the change. b. Advise the sponsor. c. Update the change log. d. Update the project plan.

Last Answer : a. Evaluate the change.

Description : Scheduling can best be defined as the process used to determine: a. overall project duration. b. project cost estimating. c. the project management plan. d. sub-contractor’s responsibilities.

Last Answer : a. overall project duration.

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager

Last Answer : b) project

Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager

Last Answer : b) project

Description :  According to PMBOK, project management process groups are iterative, which  was originally defined by Walter Shewhart and later modified by Edward Deming.  Generally, one outcome from a previous process can serve ... -Do-Check-Act cycle c. Project phases d. PM processes e. HR process cycle

Last Answer : b. Plan-Do-Check-Act cycle

Description : When a project manager starts to plan a new project budget, the cost  of which project management process group is expected to be lowest? Select one: a. Initiating b. Executing c. Monitoring and controlling d. Closing e. Planning

Last Answer : d. Closing

Description : Quality planning is the process of developing a quality plan for (A) team (B) project (C) customers (D)project manager

Last Answer : (D)project manager

Description : The methods and regulation used to define goals, plan and monitor tasks and resources, identify and resolve issues, and control costs and budgets for a specific project is known as … a. project management. b. Process Management c. Process d. Activities

Last Answer : a. project management.

Description : _____ is the process of planning and controlling the development of a system within a  specified time frame at a minimum cost with the right functionality.  a. Project management  b. Symantic timeline  c. Task identification  d. Time estimation  e. Work plan

Last Answer : a. Project management

Description : Which of the following is the most important element of Project Management Plan that is  useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : The main purpose of the Project Management Plan is to:  a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk  of alternative options.  b ... managing the project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for  managing the project.

Description : Once a change has been requested what is the next step in the change control process?  a. Evaluate the change.  b. Advise the sponsor.  c. Update the change log.  d. Update the project plan

Last Answer : a. Evaluate the change.

Description : Scheduling can best be defined as the process used to determine:  a. overall project duration.  b. project cost estimating.  c. the project management plan.

Last Answer : a. overall project duration.

Description : A mean for monitoring and controlling organization's strategic projects is A. Project Monitoring process B. Project Portfolio Process C. Project Portfolio Plan D. Project Portfolio Phase

Last Answer : B. Project Portfolio Process